Mounting frustration as BRT project lags
The metro is facing growing frustration over the prolonged delays with the Bus Rapid Transit (BRT) Line 2B expansion along Lynnwood Road.
Both residents and councillors are raising the alarm about the sluggish progress.
Line 2B of the A Re Yeng system starts at the N1 interchange on Atterbury Road, runs down Atterbury into Lynnwood Road and continues to Loftus Versfeld Stadium in Arcadia.
The route is seen as a vital link for east-west commuters, connecting suburbs, schools, universities, and business districts.
Ward councillor Siobhan Muller said the project, which was supposed to be completed in November 2024, appears to be going 'backwards' rather than moving forward.
According to Muller, the physical building of the project began in 2023.
'For the last three months, it hasn't just stagnated; it's been going in reverse,' Muller said.
'There are ripple effects for everyone, from people trying to access the University of Pretoria to those commuting along Lynnwood Road or dropping children off at nearby schools.'
She said the construction delays were being compounded by issues around land expropriation, service relocations, and requests for project extensions.
'This project was meant to ease traffic and benefit the city, but we are now in June and nowhere near completion. It urgently needs to move faster.'
Echoing her concerns, DA councillor Dikeledi Selowa criticised the metro administration, calling the repeated delays a failure in governance.
'This project is only at 61% completion, even after a six-month extension,' Selowa said.
'It is clear that this administration has failed to properly finalise the expropriation process and relocation of services, leaving Tshwane exposed to potential legal action.'
According to Tshwane spokesperson Lindela Mashigo, the metro has now set a revised completion date of July 18.
However, he said the Roads and Transport Department is reviewing a report submitted by the project consultant, requesting yet another extension.
Mashigo identified the key causes of delay as land expropriation challenges and slow progress by the contractor.
He confirmed the current overall project progress at 62%, with some sections more advanced than others:
– King's Highway culvert section: 83%
– Culvert upgrade: 90%
– Justice Mahomed intersection: 96%
– Lynnwood and Atterbury intersection: 46.8%
– University and Roper intersection: 25%
When asked about the status of land acquisition and service relocation, Mashigo said the expropriation process has been concluded.
'The city is currently processing compensation payments and negotiating remaining agreements.'
ALSO READ: Tshwane energy summit pushes for small nuclear reactors as future power solution
Do you have more information about the story?
Please send us an email to bennittb@rekord.co.za or phone us on 083 625 4114.
For free breaking and community news, visit Rekord's websites: Rekord East
For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok.
At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!
Stay in the know. Download the Caxton Local News Network App
Stay in the know. Download the Caxton Local News Network App here

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Citizen
2 days ago
- The Citizen
Dark streets in Mnandi finally see the light
A long-anticipated streetlight installation project is officially underway in Ward 48, bringing renewed hope for safety and improved infrastructure to residents of Mnandi. According to DA councillor Themba Fosi, this marks a significant milestone in a broader plan spearheaded by the DA during its leadership of the metro. Streetlights will first be installed along Lochner and Tulip roads, as well as Constantia Avenue, in a move that has been widely welcomed by residents. Residents have long called for better lighting to combat crime and improve visibility at night. This development comes after extensive engagements between Fosi and local community leader Gary Watkins, who highlighted ongoing safety concerns due to poorly lit streets. 'We heard the calls from residents and made it a priority to respond, despite the tight budgetary environment. When we were still leading the city, we initiated a phased rollout plan that would begin with arterial roads to ensure that the greatest number of people benefited,' said Fosi. While he welcomed the progress, he expressed concern over the city's recent trajectory under the current administration. 'I feel we are regressing a bit with service delivery under the new coalition government,' Fosi said. 'All the wins we had last year have not continued. The sporadic theft of cables has prevailed, the grass has not been cut, and broken infrastructure causing outages are now taking longer to repair. But I will continue to fight for residents. I will continue to push the administration to do good, taking into account that Region 4 is a revenue spinner in the city.' Do you have more information about the story? Please send us an email to bennittb@ or phone us on 083 625 4114. For free breaking and community news, visit Rekord's websites: Rekord East For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading! Stay in the know. Download the Caxton Local News Network App Stay in the know. Download the Caxton Local News Network App here


The Citizen
2 days ago
- The Citizen
Mounting frustration as BRT project lags
The metro is facing growing frustration over the prolonged delays with the Bus Rapid Transit (BRT) Line 2B expansion along Lynnwood Road. Both residents and councillors are raising the alarm about the sluggish progress. Line 2B of the A Re Yeng system starts at the N1 interchange on Atterbury Road, runs down Atterbury into Lynnwood Road and continues to Loftus Versfeld Stadium in Arcadia. The route is seen as a vital link for east-west commuters, connecting suburbs, schools, universities, and business districts. Ward councillor Siobhan Muller said the project, which was supposed to be completed in November 2024, appears to be going 'backwards' rather than moving forward. According to Muller, the physical building of the project began in 2023. 'For the last three months, it hasn't just stagnated; it's been going in reverse,' Muller said. 'There are ripple effects for everyone, from people trying to access the University of Pretoria to those commuting along Lynnwood Road or dropping children off at nearby schools.' She said the construction delays were being compounded by issues around land expropriation, service relocations, and requests for project extensions. 'This project was meant to ease traffic and benefit the city, but we are now in June and nowhere near completion. It urgently needs to move faster.' Echoing her concerns, DA councillor Dikeledi Selowa criticised the metro administration, calling the repeated delays a failure in governance. 'This project is only at 61% completion, even after a six-month extension,' Selowa said. 'It is clear that this administration has failed to properly finalise the expropriation process and relocation of services, leaving Tshwane exposed to potential legal action.' According to Tshwane spokesperson Lindela Mashigo, the metro has now set a revised completion date of July 18. However, he said the Roads and Transport Department is reviewing a report submitted by the project consultant, requesting yet another extension. Mashigo identified the key causes of delay as land expropriation challenges and slow progress by the contractor. He confirmed the current overall project progress at 62%, with some sections more advanced than others: – King's Highway culvert section: 83% – Culvert upgrade: 90% – Justice Mahomed intersection: 96% – Lynnwood and Atterbury intersection: 46.8% – University and Roper intersection: 25% When asked about the status of land acquisition and service relocation, Mashigo said the expropriation process has been concluded. 'The city is currently processing compensation payments and negotiating remaining agreements.' ALSO READ: Tshwane energy summit pushes for small nuclear reactors as future power solution Do you have more information about the story? Please send us an email to bennittb@ or phone us on 083 625 4114. For free breaking and community news, visit Rekord's websites: Rekord East For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading! Stay in the know. Download the Caxton Local News Network App Stay in the know. Download the Caxton Local News Network App here


Daily Maverick
08-06-2025
- Daily Maverick
‘No problem,' says Joburg as R1bn tender goes to officials' families or friends
The City of Johannesburg defends the award of massive transport contracts to politically connected families, despite concerns from the Auditor-General and civic watchdogs A week after Auditor-General revealed that the City of Johannesburg had awarded R972-million in dodgy family-linked tenders, city spokesperson Nthatisi Modingoane has confirmed that the metro government sees no problem and will not investigate. Six awards (or contracts) valued at almost R1-billion were made to the family of either a city official or councillor for the extension of the BRT/Rea Vaya bus system in 2023. The extension of the city transport service is eight years behind schedule, and a final deadline for the end of 2024 was also missed. 'There is no regulatory provision that prohibits the Municipality to award contracts to the category of people in question (spouse, child or parent of a person in service of state either actively or in the past twelve months). Therefore, the question whether the City failed in oversight and due diligence is misplaced,' said Modingoane. The Auditor-General has a different view. 'Although there is no legislation that prohibits municipalities from making awards to suppliers in which close family members or business associates of employees or councillors have an interest, such awards create conflicts of interest for these employees or councillors and/or their close family members or business associates. The possibility of undue influence cannot be discounted, especially if the person could have influenced the procurement processes for these awards, potentially creating opportunities for irregularities.' While Modingoane confirmed the awards were made for the BRT/Rea Vaya extension, he would not provide further details. He said the connected council official had not sat in on the award decision. Asked if the award would be rescinded or investigated, Modingoane said, 'To rescind such an award will be unlawful and the Municipality will be exposed to litigation risks as a result'. He said that the transactions had been disclosed in the city's annual financial statements as required by law, and no further investigation was necessary. BRT-Rea Vaya veers off track When cities commit to ending spatial inequality (which means that poor black people live on the outskirts while the middle and wealthy classes live in the city near opportunities and amenities), there are two ways to do so: provide transport for workers to get to economic opportunities or increase social housing near jobs. In Johannesburg, the rapid bus transport system was an innovative idea to mediate apartheid planning by making it cheap, easy and fast for workers living on the city's outskirts to go into town, to where they worked, or to get around. The city, which began as a gold mining town, was built along the ultimate apartheid master plan. Black people were housed in dormitory towns and suburbs far out of the white city in enclaves easily controlled by security forces if they resisted – the violent response to the 1976 student rebellion was the obvious example of how it worked. The BRT/Rea Vaya incorporates the taxi industry and co-owns two companies that run the system, PioTrans and Litsamaiso. The city pays BRT/Rea Vaya for trips made. The system has not been without conflict, especially with PioTrans. Its expansion to the north (the so-called Phase 1C) of the project has fallen prey to serial infrastructure and leadership weaknesses that beset local government, which Maluleke highlighted. The city has expanded north, and job opportunities are increasingly available in the new nodes. Phase 1C would almost double the number of buses and take people to where the opportunities are. But new stations lie dormant as delays have repeatedly impacted on roll-out. The weaknesses include corruption (as the R972-million contracts suggest), institutional capacity, effective project governance, ineffective planning, procurement and contract management weaknesses and a lack of accountability for poor performance. Maluleke's report lays bare all these factors. Phase 1C is eight years behind schedule, and the Johannesburg Development Agency (JDA) missed a pledge to get it running by the end of 2024. Daily Maverick regularly tracks the route to check, and progress is still far from complete. This detracts from the effort to end spatial inequality and get young people into jobs — Gauteng and Johannesburg have among the highest youth unemployment rates. Because it is subsidised, trips on the Rea Vaya are cheaper than other forms of public transport. Intervention delivers little Johannesburg is under soft intervention by the Presidency because of its rapidly collapsing infrastructure and services, but after 100 days, most residents say the impacts on the ground are imperceptible. In the past week, there have been multiday water cuts in the east of the city and power outages in the near west and across the inner city as underground fires roar through cabling. Last week, Mayor Dada Morero launched a 'bomb squad' to help him improve city management. MMC for Transport Kenny Kunene said, 'I have not heard anything about it (the R972-million dodgy tenders).' He said he would investigate and revealed that when he started his job in 2021, R23-million had been stolen from the BRT and officials had been suspended, but reinstated after the ANC intervened. He had ensured they exited as part of an anti-corruption plan, he told Daily Maverick. Failing management Johannesburg's audit outcome was unqualified with findings. (For context: the board of a private sector CEO of a company with a budget of R88-billion – Joburg's budget – would sack a CEO for this outcome.) The city lost R2.9-billion in water and R4.93 billion in electricity. Auditors ensured city finance officials reduced fruitless and wasteful expenditure to R1.48-million in 2023/24. Over the past three years, this figure stood at R354-million. The AG said the quality of its submitted statements was poor, but good on publication after remediation. The quality of its performance reports was poor. The overall status of its financial controls was poor. The BRT/Rea Vaya delays symbolise this failing management. The AG also found that 'The City of Johannesburg did not coordinate effectively with its entities. This was due to misalignment between the metro and its entities on expectations and plans, obligations, budgets and timelines for the successful delivery of key projects.' The DA has lodged a formal complaint with the Special Investigating Unit over the R1-billion in awards to companies that are linked to current and former councillors, said its head of caucus, Belinda Kayser-Echeozonjoku. 'This shocking report paints a grim picture of a city where public money is seemingly treated as a personal piggy bank by those elected to serve it. At a time when Joburg's streets are crumbling, power outages are the norm and basic service delivery is in freefall, it is unacceptable that councillors may be benefiting from a broken procurement system.' Risk is that nothing will be done – Corruption Watch 'The worrying thing is that it is a sizeable amount – it may be six officials (or six awards to one official) or their relatives who cost Joburg residents just under R1-billion. 'The official response is quite disturbing. The biggest risk is that nothing will be done, and another big transport infrastructure is threatened. Metro governments are regressing in terms of their reports to the Auditor-General,' said Moepeng Talane of Corruption Watch, who assesses all AG reports for the organisation. 'It's worrying and urgently needs the intervention of the provincial governments,' she said. DM