logo
SWB: Sibu water woes traced to leaks at hospital, airport

SWB: Sibu water woes traced to leaks at hospital, airport

Borneo Post7 hours ago

Abdul Malik, flanked by Sia (left) and Loh, responds to a question posed during the press conference.
SIBU (June 21): The ongoing water supply issues affecting Kemuyang, Sibu Jaya, Rascom Camp and the surrounding areas have been primarily attributed to leaks in the pipeline supplying water to the mentioned areas.
Speaking at a press conference here today, Sibu Water Board (SWB) general manager Abdul Malik Abdullah revealed that investigations had pinpointed two key premises with suspected major internal pipeline leaks: Sibu Hospital, and Sibu Airport.
'In the case of Sibu Hospital, we have observed a noticeable increase in water consumption, from approximately 0.5 MLD (million litres per day) to 1MLD.
'Additionally, a review of the hospital's water bills also raised concerns. Typically, their monthly bill is around RM15,000.
'However, last month, it spiked to RM30,000.
'As for Sibu Airport, daily water consumption has doubled from 0.3MLD to 0.6MLD,' he said, adding that both locations had been notified of these matters.
In view of this, he said the board had slightly reduced the sluice valve opening to regulate water flow to these two locations while awaiting repair works.
According to Abdul Malik, many pipelines are ageing, with some already in service for about 30 years.
He also highlighted that the water demand in Sibu had reached its peak at 195MLD, matching the combined production capacity of the existing plants: 150MLD from the Salim Water Treatment Plant, and 45MLD from the Bukit Lima treatment facility.
'This means the system is operating at full capacity. Even minor water disruptions or leaks can impact the overall supply,' he added.
To address the issue, Abdul Malik said several main projects had been approved, with some currently being implemented.
'The Salim water treatment plant will increase its capacity from 150MLD to 300MLD, with RM300 million allocated by the Sarawak government,' he said, adding that the project commenced in May last year and should reach completion by mid-2027.
'Upon completion, Sibu's total water production capacity will increase to 345MLD, including output from the Bukit Lima water treatment plant, boosting the reserve margin in order to water usage, in which we anticipate until 2036.'
Abdul Malik also said the Sarawak government had approved RM170 million for replacement of 360km stretch of ageing pipes in phases, from this year until 2028.
'This year, five packages worth RM51 million are being implemented as part of the overall project. The Sarawak government has allocated RM1.1 billion for the initiative, with RM170 million allocated to SWB,' he said.
Furthermore, Abdul Malik pointed at the Sungai Sadit acute plant as among the mitigation measures, pending the completion of the upgrading works on the Salim water treatment plant.
'This acute system, with 4MLD production capacity, will increase our water reserves.'
He also said the non-revenue water (NRW) reduction project, expected to be completed by April 2026, should lead to water savings of 15MLD.
In addition, the Rural Water Supply Department (JBALB)'s project, an acute plant in Nibong Tada, once completed, would eliminate the need for SWB to supply 2MLD of water to JBALB.
Among those present at the press conference were SWB senior manager (customer service and distribution) Loh Wei Lun and assistant executive (non-revenue water) Sia Yew Tatt. disruption pipeline leaks Sibu SWB water

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

SWB: Sibu water woes traced to leaks at hospital, airport
SWB: Sibu water woes traced to leaks at hospital, airport

Borneo Post

time7 hours ago

  • Borneo Post

SWB: Sibu water woes traced to leaks at hospital, airport

Abdul Malik, flanked by Sia (left) and Loh, responds to a question posed during the press conference. SIBU (June 21): The ongoing water supply issues affecting Kemuyang, Sibu Jaya, Rascom Camp and the surrounding areas have been primarily attributed to leaks in the pipeline supplying water to the mentioned areas. Speaking at a press conference here today, Sibu Water Board (SWB) general manager Abdul Malik Abdullah revealed that investigations had pinpointed two key premises with suspected major internal pipeline leaks: Sibu Hospital, and Sibu Airport. 'In the case of Sibu Hospital, we have observed a noticeable increase in water consumption, from approximately 0.5 MLD (million litres per day) to 1MLD. 'Additionally, a review of the hospital's water bills also raised concerns. Typically, their monthly bill is around RM15,000. 'However, last month, it spiked to RM30,000. 'As for Sibu Airport, daily water consumption has doubled from 0.3MLD to 0.6MLD,' he said, adding that both locations had been notified of these matters. In view of this, he said the board had slightly reduced the sluice valve opening to regulate water flow to these two locations while awaiting repair works. According to Abdul Malik, many pipelines are ageing, with some already in service for about 30 years. He also highlighted that the water demand in Sibu had reached its peak at 195MLD, matching the combined production capacity of the existing plants: 150MLD from the Salim Water Treatment Plant, and 45MLD from the Bukit Lima treatment facility. 'This means the system is operating at full capacity. Even minor water disruptions or leaks can impact the overall supply,' he added. To address the issue, Abdul Malik said several main projects had been approved, with some currently being implemented. 'The Salim water treatment plant will increase its capacity from 150MLD to 300MLD, with RM300 million allocated by the Sarawak government,' he said, adding that the project commenced in May last year and should reach completion by mid-2027. 'Upon completion, Sibu's total water production capacity will increase to 345MLD, including output from the Bukit Lima water treatment plant, boosting the reserve margin in order to water usage, in which we anticipate until 2036.' Abdul Malik also said the Sarawak government had approved RM170 million for replacement of 360km stretch of ageing pipes in phases, from this year until 2028. 'This year, five packages worth RM51 million are being implemented as part of the overall project. The Sarawak government has allocated RM1.1 billion for the initiative, with RM170 million allocated to SWB,' he said. Furthermore, Abdul Malik pointed at the Sungai Sadit acute plant as among the mitigation measures, pending the completion of the upgrading works on the Salim water treatment plant. 'This acute system, with 4MLD production capacity, will increase our water reserves.' He also said the non-revenue water (NRW) reduction project, expected to be completed by April 2026, should lead to water savings of 15MLD. In addition, the Rural Water Supply Department (JBALB)'s project, an acute plant in Nibong Tada, once completed, would eliminate the need for SWB to supply 2MLD of water to JBALB. Among those present at the press conference were SWB senior manager (customer service and distribution) Loh Wei Lun and assistant executive (non-revenue water) Sia Yew Tatt. disruption pipeline leaks Sibu SWB water

KPKM Approved 220 Agricultural Projects Under Land Use Optimisation Programme
KPKM Approved 220 Agricultural Projects Under Land Use Optimisation Programme

Barnama

time2 days ago

  • Barnama

KPKM Approved 220 Agricultural Projects Under Land Use Optimisation Programme

KUALA LUMPUR, June 20 (Bernama) -- A total of 220 projects have been approved under the Land Use Optimisation Programme in collaboration with state governments nationwide for 2024 and 2025, as of May 30. In a statement today, the Ministry of Agriculture and Food Security (KPKM) announced that the projects encompass crop cultivation, livestock, fisheries, agro-tourism, and capacity-building for farmers, planters, fishermen and breeders. 'Through Budget 2025, the Federal government has allocated RM300 million to execute various agricultural development initiatives in partnership with state governments. 'This programme includes improving, upgrading and carrying out agricultural activities on land which is under the joint jurisdiction of state governments and KPKM,' the statement read. The matter was announced at the first meeting of the Minister of Agriculture and Food Security with State Agriculture Executive Councillors for 2025, held in Putrajaya yesterday. In addition to two papers for consideration and five papers for information, the meeting also discussed a proposal for the official handover of 51 National Satellite Farm complexes built by the Department of Veterinary Services using federal funds on state-owned land in Negeri Sembilan, Johor and Perak. 'This move aims to streamline the leasing and maintenance of immovable assets by the respective state authorities in a lawful and organised manner. 'The meeting agreed that the handover would resolve issues of unclear asset ownership and enable state governments to manage and maintain the assets more systematically, ensuring the continuity of livestock operations and optimal use of existing infrastructure,' the statement read. Meanwhile, on the role of state executive councillors addressing 'grey areas' in rice bowl zones, one of the proposals raised was to transfer assets with unclear ownership to the state or district Department of Irrigation and Drainage (JPS), to ensure more efficient and effective padi field irrigation management.

Helping disabled youths lead
Helping disabled youths lead

The Star

time2 days ago

  • The Star

Helping disabled youths lead

Sia (front row, sixth from left) with members of Milad after receiving the donated items which will go to 42 OKU recipients. — MUHAMAD SHAHRIL ROSLI/The Star Applications open for training focused on assisting organisations with OKU staff, advising on special needs A TRAINING programme is available for youths with special needs to become leaders when it comes to dealing with people with disabilities (OKU). Malaysia Independent Living Association for Disabled (Milad) is calling for applicants aged 18 to 30 who are interested in becoming professional trainers. Milad will select 16 trainees, who must be registered with the Welfare Department, for the Disability Inclusion Leadership Training (DILT) programme. Programme head and Milad president Sia Siew Chi, who will be one of the trainers, said, 'We want the trained disabled individuals to become professional trainers who can assist organisations with OKU staff, as well as advise on the needs of people with disabilities. 'We welcome people with any type of disability, such as visual, hearing or physical impairments, to apply.' She said those with good public-speaking abilities would have an advantage. 'Applicants who are OKU cardholders from across Malaysia, passionate about disability rights and committed to beco­ming inclusion trainers, are encouraged to apply,' Sia said after receiving donations of medical supplies at Milad's centre in Petaling Jaya, Selangor. The 18-month programme starting in July is funded by Unicef, with technical support from the Disability Equality Training (DET) Forum, Asia-Pacific Development Centre on Disability, and Japan International Cooperation Agency. It is the first of its kind in Malaysia, designed exclusively for OKU to enable them to become professional trainers who meet the certification standards of Human Resources Development Corporation (HRD Corp). The programme will include a 14-day in-person DET workshop, weekly two-hour online mentorship, Independent Living Programme training, one-day practical facilitation experience and five-day Train-the-Trainer workshop for HRD Corp certification. Applications should include the person's name, background and contact information, and be sent to miladmalaysia@ by June 30. Details can be found at At the event, 42 persons with disabilities received donations of urinary bags and adult diapers worth RM5,826 from an anonymous donor. 'While 11 of them are able to collect the items from us, the rest will have their donated supplies delivered to their homes. 'The donor has been generous over the years, regularly sponsoring essential items for OKU. 'These items are costly and any sponsorship to fund them is greatly apprecia­ted by the disabled community,' Sia said, adding that many of the recipients were bedridden.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store