Maine rail operator asks feds to remove safety signal at Rigby Yard
Jun. 21—The freight rail company CSX Transportation wants to remove a safety signal on the approach to Rigby Yard in South Portland, where it recently began moving trains by remote control using a system that workers say is having connectivity issues.
The request to "retire" the signal, which alerts train crews to changing or unsafe track conditions, has raised safety concerns among workers in the yard and people who live in neighborhoods that flank one of the largest and busiest rail facilities in the Northeast.
They say removing the signal, located in Scarborough at the west end of Rigby Yard, would endanger rail workers, nearby residents and passengers on the Amtrak Downeaster, which shares tracks with CSX freight trains.
"It's an accident waiting to happen," said Joyce Mendoza, who lives in Thornton Heights, a neighborhood that developed as home base to many railroad workers after Rigby Yard was built in the 1920s.
Workers say CSX wants to remove the signal in part because it interferes with remote-control operations that began in the yard this month. They say the system has experienced "connectivity issues" likely exacerbated by thick tree cover near the yard and the Route 1/Main Street overpass.
"Without the safety signal at the west end, if the (remote-control system) fails, a train could roll right onto the tracks that the Amtrak Downeaster uses," said Dave Stevenson, a legislative director for the union that represents about 35 conductors and engineers at Rigby Yard. "Any incident within that 3-mile stretch has the potential to obstruct the Amtrak line."
REDUCE RADIO COMMUNICATIONS
Submitted in May, the company's application to the Federal Railroad Administration seeks permission to retire the signal and related track control operations. CSX says the signal is triggered whenever crews pull trains west for headroom, which is needed to switch tracks or move cars. Then, crews must contact the yard dispatcher and request that the signal be cleared.
"Retiring the Rigby West signal would reduce these radio communications, which would allow both dispatchers and train crews to focus on critical operational and safety-related communications in and out of Rigby Yard," the application states.
The application doesn't mention remote-control operations.
Stevenson, with the International Association of Sheet Metal, Air, Rail and Transportation Workers, noted that remote-control rail yards have been established successfully in other parts of the U.S. "But the layout of Rigby Yard isn't set up to handle remote-control operations," he said.
A rail worker posted an anonymous response to the application on the federal website.
"I am concerned that removing (the signal) will eliminate the current added protection between switching operations and the high-speed main line that Amtrak uses," the employee wrote. "By eliminating this signal, crews (could) switch freely up to the double-track main line...which could potentially result in a catastrophic event."
The employee explained that removing the signal would expand the perimeter of Rigby Yard and require approaching train crews to contact yard crews from 2 miles away, which would be "practically if not impossible to hear" using hand-held radios.
SAFETY THREAT TO WORKERS AND PUBLIC
The Brotherhood of Railroad Signalmen and the Maine AFL-CIO joined the opposition, submitting comments by Friday's deadline.
"The current signal is a safety feature that should not be eliminated just because it is not in line with a new (remote-control) operational preference or because there is a desire to eliminate a worker and reduce labor costs," said Adam Goode, the AFL-CIO's legislative director.
Goode said the union supports remote-control operations when they can be implemented responsibly, but removing the signal at Rigby Yard "is nothing more than a way to cut corners that will limit the safety of rail workers and the public."
Opponents said they have contacted U.S. Rep. Chellie Pingree, D-1st District, for assistance in preserving the signal.
"We're closely monitoring the Federal Railroad Administration's review of CSX's petition," Pingree said Friday in an emailed statement. "It's essential that any changes to rail operations uphold the highest safety standards to protect workers, passengers and surrounding neighborhoods."
Safety is the company's top priority, CSX spokesperson Austin Staton said Friday. Applying to remove the signal is part of an effort to streamline operations and reduce redundant radio communications between crews and dispatchers, Staton said.
"No changes will be made unless the (administration) determines they meet all federal safety standards," Staton said in an emailed statement. "We are fully aligned with the (administration's) oversight and remain committed to protecting our employees, the surrounding community and passenger rail service."
Representatives of the Federal Railroad Administration and the Northern New England Passenger Rail Authority, which operates the Downeaster, didn't respond to requests for interviews or written comments.
One year ago, CSX and Amtrak officials announced plans to install so-called "positive train control" technology along more than 100 miles of track between Brunswick and Haverhill, Massachusetts. Amtrak would kick in $50 million for the project and CSX would do the work.
The advanced safety system would anticipate and automatically slow or stop trains to avoid collisions, derailments, unauthorized movements into work zones, misaligned track switches and other problems. They said the system, which uses sensors and GPS technology, would be installed in early 2026 and create "opportunities for potential increases in Downeaster frequencies," the website says.
Rail officials had determined in 2018 that the advanced safety technology wasn't necessary because the Downeaster made fewer than 12 trips per day. The train makes five round trips daily between Brunswick and Boston.
The Maine Department of Transportation's state rail plan calls for "(increasing) rail capacity and trackage at Rigby Yard in South Portland to reduce congestion" by 2026, but it provides no numbers for its current or future use.
When it was built, Rigby Yard had the capacity to hold as many as 2,000 rail cars.
Mendoza, who lives near Rigby Yard, said she believes the ultimate goal is to run trains entirely by remote control — without any conductors or engineers aboard. She worries what that might mean for people who live and work nearby.
"These trains are carrying volatile and hazardous materials," she said. "We're in the blast zone. Anything that reduces the safety of the yard is a great concern for us."
Copy the Story Link

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
13 hours ago
- Yahoo
Pilot and passenger die in plane crash near Vermilion, Alberta
VERMILION — A pilot and passenger have died in a plane crash near an airport in central Alberta. RCMP say they were dispatched to the crash shortly after noon on Saturday, and the plane was located approximately 1.2 kilometres short of the local airport runway in Vermilion, Alta. Police say there were two occupants in the plane — the 46-year-old female pilot who was a resident of Slave Lake, Alta., and a 76-year-old male passenger, a resident of Mannville, Alta. Neither survived the crash. Cpl. Gina Slaney said she did not know the aircraft type, but said it was small. Police say the Transportation Safety Board will be investigating what happened. This report by The Canadian Press was first published June 21, 2025. The Canadian Press Error in retrieving data Sign in to access your portfolio Error in retrieving data Error in retrieving data Error in retrieving data Error in retrieving data

Yahoo
a day ago
- Yahoo
Maine rail operator asks feds to remove safety signal at Rigby Yard
Jun. 21—The freight rail company CSX Transportation wants to remove a safety signal on the approach to Rigby Yard in South Portland, where it recently began moving trains by remote control using a system that workers say is having connectivity issues. The request to "retire" the signal, which alerts train crews to changing or unsafe track conditions, has raised safety concerns among workers in the yard and people who live in neighborhoods that flank one of the largest and busiest rail facilities in the Northeast. They say removing the signal, located in Scarborough at the west end of Rigby Yard, would endanger rail workers, nearby residents and passengers on the Amtrak Downeaster, which shares tracks with CSX freight trains. "It's an accident waiting to happen," said Joyce Mendoza, who lives in Thornton Heights, a neighborhood that developed as home base to many railroad workers after Rigby Yard was built in the 1920s. Workers say CSX wants to remove the signal in part because it interferes with remote-control operations that began in the yard this month. They say the system has experienced "connectivity issues" likely exacerbated by thick tree cover near the yard and the Route 1/Main Street overpass. "Without the safety signal at the west end, if the (remote-control system) fails, a train could roll right onto the tracks that the Amtrak Downeaster uses," said Dave Stevenson, a legislative director for the union that represents about 35 conductors and engineers at Rigby Yard. "Any incident within that 3-mile stretch has the potential to obstruct the Amtrak line." REDUCE RADIO COMMUNICATIONS Submitted in May, the company's application to the Federal Railroad Administration seeks permission to retire the signal and related track control operations. CSX says the signal is triggered whenever crews pull trains west for headroom, which is needed to switch tracks or move cars. Then, crews must contact the yard dispatcher and request that the signal be cleared. "Retiring the Rigby West signal would reduce these radio communications, which would allow both dispatchers and train crews to focus on critical operational and safety-related communications in and out of Rigby Yard," the application states. The application doesn't mention remote-control operations. Stevenson, with the International Association of Sheet Metal, Air, Rail and Transportation Workers, noted that remote-control rail yards have been established successfully in other parts of the U.S. "But the layout of Rigby Yard isn't set up to handle remote-control operations," he said. A rail worker posted an anonymous response to the application on the federal website. "I am concerned that removing (the signal) will eliminate the current added protection between switching operations and the high-speed main line that Amtrak uses," the employee wrote. "By eliminating this signal, crews (could) switch freely up to the double-track main could potentially result in a catastrophic event." The employee explained that removing the signal would expand the perimeter of Rigby Yard and require approaching train crews to contact yard crews from 2 miles away, which would be "practically if not impossible to hear" using hand-held radios. SAFETY THREAT TO WORKERS AND PUBLIC The Brotherhood of Railroad Signalmen and the Maine AFL-CIO joined the opposition, submitting comments by Friday's deadline. "The current signal is a safety feature that should not be eliminated just because it is not in line with a new (remote-control) operational preference or because there is a desire to eliminate a worker and reduce labor costs," said Adam Goode, the AFL-CIO's legislative director. Goode said the union supports remote-control operations when they can be implemented responsibly, but removing the signal at Rigby Yard "is nothing more than a way to cut corners that will limit the safety of rail workers and the public." Opponents said they have contacted U.S. Rep. Chellie Pingree, D-1st District, for assistance in preserving the signal. "We're closely monitoring the Federal Railroad Administration's review of CSX's petition," Pingree said Friday in an emailed statement. "It's essential that any changes to rail operations uphold the highest safety standards to protect workers, passengers and surrounding neighborhoods." Safety is the company's top priority, CSX spokesperson Austin Staton said Friday. Applying to remove the signal is part of an effort to streamline operations and reduce redundant radio communications between crews and dispatchers, Staton said. "No changes will be made unless the (administration) determines they meet all federal safety standards," Staton said in an emailed statement. "We are fully aligned with the (administration's) oversight and remain committed to protecting our employees, the surrounding community and passenger rail service." Representatives of the Federal Railroad Administration and the Northern New England Passenger Rail Authority, which operates the Downeaster, didn't respond to requests for interviews or written comments. One year ago, CSX and Amtrak officials announced plans to install so-called "positive train control" technology along more than 100 miles of track between Brunswick and Haverhill, Massachusetts. Amtrak would kick in $50 million for the project and CSX would do the work. The advanced safety system would anticipate and automatically slow or stop trains to avoid collisions, derailments, unauthorized movements into work zones, misaligned track switches and other problems. They said the system, which uses sensors and GPS technology, would be installed in early 2026 and create "opportunities for potential increases in Downeaster frequencies," the website says. Rail officials had determined in 2018 that the advanced safety technology wasn't necessary because the Downeaster made fewer than 12 trips per day. The train makes five round trips daily between Brunswick and Boston. The Maine Department of Transportation's state rail plan calls for "(increasing) rail capacity and trackage at Rigby Yard in South Portland to reduce congestion" by 2026, but it provides no numbers for its current or future use. When it was built, Rigby Yard had the capacity to hold as many as 2,000 rail cars. Mendoza, who lives near Rigby Yard, said she believes the ultimate goal is to run trains entirely by remote control — without any conductors or engineers aboard. She worries what that might mean for people who live and work nearby. "These trains are carrying volatile and hazardous materials," she said. "We're in the blast zone. Anything that reduces the safety of the yard is a great concern for us." Copy the Story Link

Yahoo
a day ago
- Yahoo
Santa Fe 2926 gets approval to run on track outside Albuquerque for first time in decades
Jun. 20—People drive for miles to catch "raily" cool locomotive legends, such as Union Pacific's Big Boy No. 4014. They cheer and hug their loved ones as they listen to the click-clack of wheels on the tracks and watch plumes of steam blow into the air. People in Albuquerque experienced that magical moment in 2021 when the 1944 Atchison, Topeka & Santa Fe 2926 steam locomotive ran on its own power for the first time in over half a century. Those in neighboring communities, however, have not had that opportunity to see the 2926 . But that will change. The New Mexico Department of Transportation, New Mexico Rail Runner and New Mexico Heritage Rail have agreed to allow the ATSF 2926 to expand the amount of main line track it can run from about 3 miles to about 20 miles on either side of Albuquerque, between Bernalillo and Los Lunas, New Mexico Heritage Rail announced in a June 15 news release. "This is huge," said Mathew Casford, New Mexico Heritage Rail vice president and chief of rail operations. "This is the culmination of a dream that guys who were involved with this locomotive had way before I was involved." The expanded access applies to non-revenue deadhead moves — no freight or passengers — enabling the 2926 and its support equipment to travel for staging, maintenance and community outreach, the release stated. "This is exciting, really exciting," said John Taylor, Steam Locomotive & Railroad Society at-large board member. Taylor was one of dozens and dozens of people who helped restore the 2926. It is unclear, however, when people in Los Lunas or Bernalillo will be able to see the Santa Fe icon . "It could be within a year or two, if the stars align," Taylor said. "But there (are) a lot of stars." 'See what steam power is' The Santa Fe 2926 was built in 1944, and it was one of the last Class 2900 4-8-4 steam locomotives built by Baldwin Locomotive Works. "They were the engines for the war effort," Taylor said. "They were the engines for bringing freight. They were the engines for tourism, and they really turned New Mexico, essentially, into the state that she is today." After traveling a million miles, the locomotive was retired in Belen in 1955. A year later, it was donated to the city of Albuquerque, which put it in Coronado Park as part of the city's 250th anniversary celebration, he said. The Santa Fe 2926 sat in the park until 2000 when the Steam Locomotive & Railroad Society — doing business as New Mexico Heritage Rail — bought it for $1 and moved it to its current location, on 1833 Eighth NW, the restoration site for the 2926. Members of the society have put thousands of man-hours and dollars into refurbishing the locomotive. "It was rusty, covered with asbestos," Taylor said. "We stripped it down. We cleaned it up. We repaired everything, and we made it go, and we did it with volunteers." After two decades of restoration efforts, the Santa Fe 2926 ran under its own power for the first time on July 24, 2021 . In the past few years, the locomotive appeared at Tractor Brewing Company, Wells Park and the Rail Yards. But now, the Santa Fe 2926 will be able to go as far as Los Lunas. "To let the people see what steam power is and what it represents is a really important thing," Taylor said. New Mexico Heritage Rail is developing operating schedules in coordination with New Mexico Rail Runner to ensure a "seamless integration with existing freight and passenger services," according to a news release. "These practice runs will allow the organization to test equipment, train crews, and demonstrate consistent, safe operations — essential steps before any public trips can be offered," the release stated. "This is going to be a persistent, slow process," Casford said. In the meantime, people can see the 2926 at the restoration site from 9 a.m. to 2 p.m. Wednesdays and Saturdays or during New Mexico Railroad Days the last weekend of September. "This isn't just a locomotive," Casford said, "it's a rolling classroom and a tribute to the people and industry that helped shape New Mexico."