Stony Plain Road businesses dreading expedited construction plan for Valley Line West LRT

Stony Plain Road businesses dreading expedited construction plan for Valley Line West LRT

CBC12-02-2025

A series of staggered full and partial road closures to build the Valley Line West LRT has businesses in the Stony Plain Road area worried.
Business owners made their concerns heard during Tuesday's urban planning committee meeting at city hall.
Traffic woes have already plagued the construction area along Stony Plain Road, 156th Street and 87th Avenue for several years.
More major road closures are set to come along the LRT route, as the city and project builder Marigold Infrastructure Partners start partial and full closures to speed up its construction.
With the expedited construction schedule, the LRT expansion is set to be complete in 2028.
WATCH | Some business owners worry as Edmonton wants to speed up Valley Line West construction:
Edmonton plans to speed up Valley Line West construction. But there's a catch
Duration 1:55
The City of Edmonton is looking to quicken the road construction portion of the Valley Line West project, as construction enters it's fourth year. As CBC's Travis McEwan reports, it will come with phased intersection closures until the end of November.
Restaurant El Corazon is one of many businesses that have had to deal with reduced clientele because of access cut off by construction.
"Although we can all agree that the construction needs to be expedited, closing down major intersection is not the answer," said El Corazon owner Percy Wiredu during the meeting.
"There are over 400 employees and thousands of patrons that use 142nd street to access the West Block. Road closure on 142nd Street would see job losses, significant reduction in traffic to the businesses, which ultimately would lead to business closures."
The $2.6-billion project, now in its fourth year of construction, is the largest infrastructure project the City of Edmonton has undertaken.
The accelerated roadwork plan involves a three-phase approach from April to November:
Phase 1 (April to July) 104th Avenue corridor (106th Street to 121st Street) Stony Plain Road at 124th Street (full closure) Stony Plain Road at 156th Street 87th Avenue at Meadowlark Road
Phase 2 (July to September) 104th Avenue corridor (106th Street to 121st Street) Stony Plain Road at 142nd Street 95th Avenue at 156th Street
Phase 3 (September to November) 104th Avenue corridor (106th Street to 121st Street) Stony Plain Road at 149th Street
Marian Switzer owns The Gilded Rabbit Art and Framing along 149th Street and Stony Plain Road. She's worried she'll lose half of the store's revenue with a full closure of a major intersection. (Madeleine Cummings/CBC)
Marian Switzer, another business owner in the area, said she's worried she'll lose half of her store's revenue with a full closure of a major intersection. She owns The Gilded Rabbit Art and Framing along 149th Street and Stony Plain Road
"The timing for my phase two, phase three also hits us at a really inconvenient time," Switzer said during the meeting.
"September to December is our busiest time of the store. It's where we make half of our money for the year. That's what keeps us going through the summer.
"It's been a lot. It's been COVID, construction, inflation, possible looming tariffs coming from the States."
A common concern from the business community was a lack of consultation on the part of city administration when it came to determining options that would allow for some traffic for people to check out businesses.
"The crux of the issue is that the plan completely cuts off access from all neighbourhoods to the south, as well as all traffic from both westbound and downtown, westbound from downtown and eastbound into downtown," said Stewart Fraser with land developer and builder Cantiro.
Cantiro developed the West Block, at 142nd Street and Stony Plain Road, which houses businesses like El Corazon.
"What guarantees do we have that this work will be completed in the proposed nine-week timeline? What really irks me about this plan is the blatant disregard for the directly affected stakeholders," Fraser said.
This frustration was also voiced by Mayor Amarjeet Sohi who called on administration and Marigold Infrastructure to communicate more with the business community to reach solutions that would alleviate the hit to vehicle traffic.
The push to complete roadwork is being spearheaded by Ward Nakota Isga Coun. Andrew Knack.
"I saw a lot more progress on the roads in 2024 than I did in 2022 and 2023, so let's see that multiplied instead of the first two years, which was, if I'm just being very blunt, it was disappointing," Knack said about Marigold's progress on the project.
"Let's get moving, get the work started, get it done as per that new schedule, and I think that'll be better for everyone."
Committee voted unanimously to have administration take the feedback presented during Tuesday's meeting and determine what can be done to address specific concerns.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

The rise and fall of Canada's alleged grandparent scam king

time4 days ago

The rise and fall of Canada's alleged grandparent scam king

Headlines Latest News Podcasts (new window) The rise and fall of Canada's alleged grandparent scam king. Photo: CBC He flaunted fortune and success. Now he's wanted for allegedly masterminding Canada's largest grandparent scam network. Wearing a close-fitting dress shirt, skinny jeans and black leather loafers, 42-year-old Gareth West stood in front of a modest, white-walled home on the outskirts of Montreal in 2022 and laid out the blueprint to get rich through real estate. He said he planned to demolish the home and turn it into a bustling office complex, earning millions. The most successful developers are the ones who have the greatest foresight, he said, speaking in a promotional video. By many measures, West was successful. He moonlighted as an amateur bodybuilder, drove expensive cars, owned a yacht, travelled often and hosted parties at his home in Montreal and his penthouse in downtown Toronto. Except West's public persona as a real estate developer, carefully crafted through years of buying apartment complexes in southern Ontario and building homes in the Montreal suburbs, was a facade. A CBC News investigation has identified West as the man authorities say is behind a large-scale criminal network that stole at least $30 million from vulnerable seniors. Read the full report (new window) 'The relationship is not great,' former ambassador says, 'and frankly, it shouldn't be'. 'This is why we are police,' says officer as he detailed search for missing 3-year-old. 1 hour ago Courts and Crime Warning comes as Canada and India agree to reinstate top diplomats 18 hours ago Federal Politics 2 Canadian universities in global top 10 for advancing UN sustainability targets 18 hours ago Sustainable Development Productive regions in higher-income countries could be hit hard despite adaptation

Attainable Homes Calgary bringing 230 below-market townhomes to former David D. Oughton School site
Attainable Homes Calgary bringing 230 below-market townhomes to former David D. Oughton School site

Calgary Herald

time4 days ago

  • Calgary Herald

Attainable Homes Calgary bringing 230 below-market townhomes to former David D. Oughton School site

Article content The homes will range in price, according to Tait, with one-bedroom units selling for around $170,000 and five-bedroom homes selling for between $300,000 and $330,000, which is well below market rates. Article content There are currently hundreds of Calgarians on Attainable Homes Calgary's wait list, according to Tait, who said the non-profit has helped more than 1,100 families buy a home in the last 15 years. Article content 'The intent is for people that work hard, are on fixed incomes,' he said. 'We're looking for people that contribute very strongly to Calgary's economy, Calgary's cultural life, that just can't be in a market home right now, so we use that income eligibility limit to guide our sale decisions.' Article content There are also rules in place to prohibit owners from renting out their units, running a home-based business or secondary suite, or operating their townhome as a short-term vacation rental. Article content Article content 'We make sure that these aren't used as investment properties,' Tait said. 'The owner lives in the unit and we've got protections in place to ensure that happens.' Article content To help families afford the homes, Tait said Attainable Homes Calgary runs a down payment assistance loan program. Through the program, the non-profit's clients only need to contribute an initial $2,000. The agency then loans whatever is required for the buyer to reach the federally mandated five per cent minimum down payment. The interest-free loan is returned when the buyer eventually sells the home. Article content CMLC looking into developing park-and-ride lots along LRT In addition to the former David D. Oughton site, CMLC president and CEO Kate Thompson said the civic partner is advancing several other housing initiatives on municipally owned land. At Wednesday's event, she mentioned CMLC is exploring the feasibility of developing transit-oriented communities (TOCs) along the CTrain network, specifically the city-owned park-and-ride lots at the Anderson, Fish Creek-Lacombe and Dalhousie stations. The first phase of community engagement for those potential projects will begin this month, according to Thompson, who added additional surveys and engagement will follow as site analysis progresses. CMLC is also progressing its East Village master plan, with four residential projects featuring more than 900 homes currently moving through the city's regulatory processes. Construction of the first 162 of those units will begin later this year as part of Bankside Properties' Library Square project, which Thompson noted will include two six-storey residential dwellings just east of the central library. Article content

Eglinton Crosstown LRT train operations have been transferred to TTC, Metrolinx interim CEO says
Eglinton Crosstown LRT train operations have been transferred to TTC, Metrolinx interim CEO says

Toronto Star

time5 days ago

  • Toronto Star

Eglinton Crosstown LRT train operations have been transferred to TTC, Metrolinx interim CEO says

The Eglinton Crosstown LRT is one step closer to opening. Train operations for the Eglinton Crosstown LRT have been transferred over to the TTC, Metrolinx's interim CEO Michael Lindsay and Transportation Minister Prabmeet Sarkaria confirmed Tuesday. 'Major milestones have been met,' Lindsay said at a news conference to announce the groundbreaking of the East Harbour Transit Hub. 'As of today or tomorrow, movement of trains on the line is actually governed by the TTC, as it will be when the line is in revenue service.' This doesn't mean that the project has officially been handed over, TTC spokesperson Stuart Green explained. In order for that to happen, the project has to reach 'substantial completion,' which requires the approval of an independent certifier, Green added. ARTICLE CONTINUES BELOW 'The good news, though, is that this week, train operations were transferred into our Transit Control Centre from a temporary control centre as testing, training and construction continue,' Green said. Operator and driver training has been completed, Lindsay confirmed, adding that 'we are relentlessly stress-testing both (the) system and vehicles.' 'We're doing the things for this line that, frankly, were not done for projects like the Ottawa LRT,' he added. The $2.1-billion Ottawa LRT, much like the Eglinton line, was plagued with delays and flaws. Problems with the project included a massive sinkhole during construction, and after the line opened in 2019, repeated derailments and even service shutdowns caused by freezing rain. ACS Infrastructure Canada and EllisDon were part of both the Ottawa and Eglinton LRT construction consortiums. With 25 stops stretching from Mount Dennis in the west to Kennedy in the east, the 19-kilometre Eglinton Crosstown LRT was initially meant to be ready by 2020. A pandemic and several lawsuits, as well as software glitches, have hampered the line's opening, even after the Star received an exclusive tour of the LRT in May 2023. The completion of the LRT had been promised, then pushed back, for three years, until the transit agency declined to give a projected opening in 2023, instead announcing it would give the public three-months' advance notice instead. ARTICLE CONTINUES BELOW ARTICLE CONTINUES BELOW Gta With Eglinton Crosstown LRT, Metrolinx says it's trying to avoid a repeat of this transit project nightmare Andy Takagi Testing and more testing for the LRT As of now, the Crosstown is still undergoing tests to check how the trains are performing, and Lindsay added, 'that's going pretty well.' The purpose of all this rigorous testing, Lindsay said, is to demonstrate 'to ourselves, collectively, that it's going to perform the way that we want it to on the day that it opens.' Once the Crosstown system 'achieves a certain level of stability,' Lindsay explained, there will be two further steps for testing. The first will be a 14-day trial run of the line, followed by a 30-day revenue service demonstration, where the system will run 'as it will run when it is open to the public, (but) with no passengers on it.' After those two trials, following the 'substantial completion' of the project, the LRT will undergo a 'bedding-in period' of more testing — which Lindsay said was implemented as a direct recommendation in the aftermath of the Ottawa LRT's troublesome rollout. September opening for the Crosstown Lindsay said 'if everything goes according to plan' with the testing, the LRT is expected to open for a September or fall opening, with the caveat that 'we cannot, cannot open that system if it is not going to perform.' ARTICLE CONTINUES BELOW ARTICLE CONTINUES BELOW The province will be the one to decide an opening date, the TTC's Green added, 'when we are confident the line is ready for safe and reliable operations.' The Star reported in March that the Eglinton Crosstown LRT is expected to open in September, according to sources close to the project. Star Exclusive Eglinton Crosstown LRT finally has an opening date, according to sources Andy Takagi Coun. Josh Matlow, whose ward straddles Eglinton Avenue between Dufferin Street and Mount Pleasant Road, is calling for a public inquiry into the Crosstown's long journey to completion. 'Today they're boasting about something that they shouldn't be boasting about,' Matlow said. 'They should actually be humble about the fact that this has been a mess. It has hurt people, it's hurt businesses and there needs to be accountability for that.' Matlow questioned whether Metrolinx would learn lessons about the mistakes and delays that hampered the Crosstown. 'There needs to be daylight shone in so that the public can trust that they've learned from these mistakes and that they'll do it better,' he added. ARTICLE CONTINUES BELOW ARTICLE CONTINUES BELOW Premier Doug Ford, asked for his comments on the 14-year-long wait for the Crosstown's opening, praised Lindsay, calling him 'brilliant and a champion.' 'This has been way too long,' said Ford, who has been premier for seven years of the LRT's 14 years of construction. 'It was a mess for years. But we inherited a mess, now it's going to come to fruition.' 'Safety is the No. 1 priority,' said Ford, who added his thanks to the TTC for its partnership. 'It'll be up to them to make it happen. Let's get it done.' With files from Ben Spurr and Mahdis Habibinia. Correction – June 17, 2025 This article was updated from a previous version that mistakenly said the Eglinton LRT had officially been handed over to the TTC. In fact, train operations for the transit line have been transferred to the TTC.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store