Eglinton Crosstown LRT train operations have been transferred to TTC, Metrolinx interim CEO says
The Eglinton Crosstown LRT is one step closer to opening.
Train operations for the Eglinton Crosstown LRT have been transferred over to the TTC, Metrolinx's interim CEO Michael Lindsay and Transportation Minister Prabmeet Sarkaria confirmed Tuesday.
'Major milestones have been met,' Lindsay said at a news conference to announce the groundbreaking of the East Harbour Transit Hub. 'As of today or tomorrow, movement of trains on the line is actually governed by the TTC, as it will be when the line is in revenue service.'
This doesn't mean that the project has officially been handed over, TTC spokesperson Stuart Green explained. In order for that to happen, the project has to reach 'substantial completion,' which requires the approval of an independent certifier, Green added.
ARTICLE CONTINUES BELOW
'The good news, though, is that this week, train operations were transferred into our Transit Control Centre from a temporary control centre as testing, training and construction continue,' Green said.
Operator and driver training has been completed, Lindsay confirmed, adding that 'we are relentlessly stress-testing both (the) system and vehicles.'
'We're doing the things for this line that, frankly, were not done for projects like the Ottawa LRT,' he added.
The $2.1-billion Ottawa LRT, much like the Eglinton line, was plagued with delays and flaws. Problems with the project included a massive sinkhole during construction, and after the line opened in 2019, repeated derailments and even service shutdowns caused by freezing rain. ACS Infrastructure Canada and EllisDon were part of both the Ottawa and Eglinton LRT construction consortiums.
With 25 stops stretching from Mount Dennis in the west to Kennedy in the east, the 19-kilometre Eglinton Crosstown LRT was initially meant to be ready by 2020.
A pandemic and several lawsuits, as well as software glitches, have hampered the line's opening, even after the Star received an exclusive tour of the LRT in May 2023. The completion of the LRT had been promised, then pushed back, for three years, until the transit agency declined to give a projected opening in 2023, instead announcing it would give the public three-months' advance notice instead.
ARTICLE CONTINUES BELOW
ARTICLE CONTINUES BELOW
Gta
With Eglinton Crosstown LRT, Metrolinx says it's trying to avoid a repeat of this transit project nightmare
Andy Takagi
Testing and more testing for the LRT
As of now, the Crosstown is still undergoing tests to check how the trains are performing, and Lindsay added, 'that's going pretty well.'
The purpose of all this rigorous testing, Lindsay said, is to demonstrate 'to ourselves, collectively, that it's going to perform the way that we want it to on the day that it opens.'
Once the Crosstown system 'achieves a certain level of stability,' Lindsay explained, there will be two further steps for testing.
The first will be a 14-day trial run of the line, followed by a 30-day revenue service demonstration, where the system will run 'as it will run when it is open to the public, (but) with no passengers on it.'
After those two trials, following the 'substantial completion' of the project, the LRT will undergo a 'bedding-in period' of more testing — which Lindsay said was implemented as a direct recommendation in the aftermath of the Ottawa LRT's troublesome rollout.
September opening for the Crosstown
Lindsay said 'if everything goes according to plan' with the testing, the LRT is expected to open for a September or fall opening, with the caveat that 'we cannot, cannot open that system if it is not going to perform.'
ARTICLE CONTINUES BELOW
ARTICLE CONTINUES BELOW
The province will be the one to decide an opening date, the TTC's Green added, 'when we are confident the line is ready for safe and reliable operations.'
The Star reported in March that the Eglinton Crosstown LRT is expected to open in September, according to sources close to the project.
Star Exclusive
Eglinton Crosstown LRT finally has an opening date, according to sources
Andy Takagi
Coun. Josh Matlow, whose ward straddles Eglinton Avenue between Dufferin Street and Mount Pleasant Road, is calling for a public inquiry into the Crosstown's long journey to completion.
'Today they're boasting about something that they shouldn't be boasting about,' Matlow said. 'They should actually be humble about the fact that this has been a mess. It has hurt people, it's hurt businesses and there needs to be accountability for that.'
Matlow questioned whether Metrolinx would learn lessons about the mistakes and delays that hampered the Crosstown.
'There needs to be daylight shone in so that the public can trust that they've learned from these mistakes and that they'll do it better,' he added.
ARTICLE CONTINUES BELOW
ARTICLE CONTINUES BELOW
Premier Doug Ford, asked for his comments on the 14-year-long wait for the Crosstown's opening, praised Lindsay, calling him 'brilliant and a champion.'
'This has been way too long,' said Ford, who has been premier for seven years of the LRT's 14 years of construction. 'It was a mess for years. But we inherited a mess, now it's going to come to fruition.'
'Safety is the No. 1 priority,' said Ford, who added his thanks to the TTC for its partnership. 'It'll be up to them to make it happen. Let's get it done.'
With files from Ben Spurr and Mahdis Habibinia.
Correction – June 17, 2025
This article was updated from a previous version that mistakenly said the Eglinton LRT had officially been handed over to the TTC. In fact, train operations for the transit line have been transferred to the TTC.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


CBC
a day ago
- CBC
Toronto business owners say King Street construction, road closure costing them
Just over two weeks after a major Toronto intersection was closed for a construction project that's expected to take much of the summer, some King Street business owners say they're already losing business due to reduced traffic and noise. The intersection of King Street E. and Church Street was closed to all traffic on June 2, and is scheduled to remain so until mid-August, according to the city. The closure is part of a joint project by the city and the TTC to replace aging streetcar tracks, as well as a 142-year-old water main. Spokespersons for the TTC and the city told CBC Toronto that work is currently on schedule. But in the meantime, transit has been rerouted off a portion of King Street, and some business owners say the construction is costing them. WATCH | Toronto downtown intersection will be closed until mid-August: King-Church intersection to be closed until mid-August 17 days ago Duration 3:00 Graham Wong, founder and CEO of LAUFT, where professionals rent on-demand work spaces, says the noise and traffic diversions aren't convenient for clients. "When they start to drill, it gets very loud. And so you can imagine that if someone has a video call, or they have a team meeting, they certainly want to have that ability to focus," he said, adding that the closure started earlier than expected. "So there were some juggling things that we had to do for clients, and saying, possibly, maybe, you move your meeting to another location that we have." He said the business is getting by, but if the project is delayed into September, it would start to conflict with the company's busy season as workers return from vacations. Another business owner on the street, Arti Joshi, says her spa Atmana opened near King and Church in the winter, and had started to break even last month. But revenue has decreased 70 per cent in June compared to May, she says, and the construction is keeping people away. "We're getting calls, but then when they see that this road is blocked, they don't want to come this way. So it's really hitting our business," she said. And for those who do make it, Joshi says the spa experience hasn't been as relaxing as in previous months. "Because I am in the lower level... I had to actually cancel my guests from coming in, because the entire place was vibrating and rattling," she said. Joshi says the drilling has improved since construction started, but the project is still disrupting business. "I just wish this gets over soon. We love this spot." Councillor proposes removing transit priority The road closure has also had a broader impact, forcing transit and vehicles to divert on side streets, adding to downtown congestion. Coun. Brad Bradford said Thursday that he wants the city to increase traffic flow in the area by temporarily removing transit priority on King Street while streetcars and buses are diverted for construction. He says he'll bring a motion forward at next week's council meeting to that effect. "There are no streetcars using this transit priority corridor right now. It is a transit priority corridor in name only," he told reporters at a news conference downtown Thursday. "This is a simple step that would immediately relieve the pressure on adjacent east-west routes and help ease some of the traffic congestion across the entire downtown core." Bradford, who represents the Beaches-East York ward in the city's east end, said he's responding to what he's heard from constituents, as well as businesses and people from across the city, about "what a nightmare it is to get into downtown Toronto." Bradford was also asked if he intended to run for mayor next year, but declined to confirm.


Calgary Herald
2 days ago
- Calgary Herald
Attainable Homes Calgary bringing 230 below-market townhomes to former David D. Oughton School site
Article content The homes will range in price, according to Tait, with one-bedroom units selling for around $170,000 and five-bedroom homes selling for between $300,000 and $330,000, which is well below market rates. Article content There are currently hundreds of Calgarians on Attainable Homes Calgary's wait list, according to Tait, who said the non-profit has helped more than 1,100 families buy a home in the last 15 years. Article content 'The intent is for people that work hard, are on fixed incomes,' he said. 'We're looking for people that contribute very strongly to Calgary's economy, Calgary's cultural life, that just can't be in a market home right now, so we use that income eligibility limit to guide our sale decisions.' Article content There are also rules in place to prohibit owners from renting out their units, running a home-based business or secondary suite, or operating their townhome as a short-term vacation rental. Article content Article content 'We make sure that these aren't used as investment properties,' Tait said. 'The owner lives in the unit and we've got protections in place to ensure that happens.' Article content To help families afford the homes, Tait said Attainable Homes Calgary runs a down payment assistance loan program. Through the program, the non-profit's clients only need to contribute an initial $2,000. The agency then loans whatever is required for the buyer to reach the federally mandated five per cent minimum down payment. The interest-free loan is returned when the buyer eventually sells the home. Article content CMLC looking into developing park-and-ride lots along LRT In addition to the former David D. Oughton site, CMLC president and CEO Kate Thompson said the civic partner is advancing several other housing initiatives on municipally owned land. At Wednesday's event, she mentioned CMLC is exploring the feasibility of developing transit-oriented communities (TOCs) along the CTrain network, specifically the city-owned park-and-ride lots at the Anderson, Fish Creek-Lacombe and Dalhousie stations. The first phase of community engagement for those potential projects will begin this month, according to Thompson, who added additional surveys and engagement will follow as site analysis progresses. CMLC is also progressing its East Village master plan, with four residential projects featuring more than 900 homes currently moving through the city's regulatory processes. Construction of the first 162 of those units will begin later this year as part of Bankside Properties' Library Square project, which Thompson noted will include two six-storey residential dwellings just east of the central library. Article content


Cision Canada
2 days ago
- Cision Canada
Finlay Minerals announces the commencement of the 2025 PIL & ATTY Property Exploration Programs
VANCOUVER, BC, June 18, 2025 /CNW/ - Finlay Minerals Ltd. (TSXV: FYL) (OTCQB: FYMNF) ("Finlay" or the "Company") is pleased to announce the start of the 2025 exploration programs for its PIL and ATTY Properties within the Toodoggone Mining District of Northern British Columbia. These programs are fully funded under the Earn-In Agreements with Freeport-McMoRan Mineral Properties Canada Inc. ("Freeport"). Under these agreements, Freeport can earn up to an 80% interest in each property by investing $35 million in exploration expenditures and making cash payments of $4.1 million over a period of six years. (Reference #1). The exploration programs at PIL and ATTY are designed to best outline and prioritize as many targets as possible for drill testing in 2026. The 2025 programs at both PIL and ATTY will consist of the following activities with Finlay acting as Operator: Detailed, property-wide ,100 metre ("m") line-spaced airborne magnetic surveys; extensive induced polarization ("IP") geophysical surveys; detailed geological and alteration mapping and expanded rock and soil sampling on up to 8 target areas on the PIL and up to 3 target areas on the ATTY depending on weather and conditions. The exploration crews are anticipated to arrive on the PIL Property in the coming week and the exploration programs are expected to extend into late August. Finlay will provide additional updates on the progress and results of the exploration programs as they become available in the coming months. Finlay's President and CEO, Ilona Lindsay, states: " The proposed exploration programs for 2025 will permit us to continue to advance these promising projects through systematic exploration," says Lindsay. "We are excited to build on the successes of previous exploration campaigns, especially given the highly encouraging results seen at the PIL South and in the Wrich area. Freeport's expertise and funding significantly enhances our ability to carry out systemic and comprehensive exploration across both properties. This is a transformative opportunity for Finlay Minerals." PIL Property: Exploration on the PIL Property will focus on the western Toodoggone porphyry corridor that includes Freeport and Amarc's newly discovered AuRORA Au-Cu porphyry system, Centerra Gold's Kemess North and Kemess East Deposits and the former Kemess South Mine – refer to Figure 1. Exploration will be prioritized at and around the PIL South Target, working on the theory that the major porphyry centres occur along northeast-southwest trends within this corridor. In 2024, drilling at PIL South intercepted Cu-Au porphyry mineralization. Other targets on the PIL Property include favorable geological, alteration, and surface geochemical environments with other porphyry indicators such as high-sulphidation systems. Details of the PIL Property exploration targets can be found in the Company's PIL Technical Presentation on the Finlay website at ATTY Property: Exploration work on the ATTY Property will focus on the Wrich target which is adjacent to the SWT target on the Joy Property. The SWT target hosts a >2 kilometre ("km") copper geochemical anomaly that is open to the south and extends onto the ATTY Property for another 1.2 km to the southeast. Details of the ATTY Property exploration targets can be found in the Company's ATTY Technical Presentation on the Finlay website at Freeport negotiated Earn-In agreements on both the PIL and ATTY Properties whereby Freeport can earn an 80% interest in each property by spending $35 million in exploration expenditures and $4.1 million cash payments of over six years (Reference # 1). Freeport-McMoRan (FCX) is a leading international metals company focused on copper, with major operations in the Americas and Indonesia and significant reserves of copper, gold, and molybdenum. References: Qualified Person: Wade Barnes, P. Geo. and Vice President, Exploration for Finlay Minerals and a qualified person as defined by National Instrument 43-101, has approved the technical content of this news release. About Finlay Minerals Ltd. Finlay is a TSXV company focused on exploration for base and precious metal deposits with five properties in northern British Columbia: The ATTY Property covers 3,875 hectares (" ha") of sub-alpine terrain in the southern Toodoggone region. The Toodoggone is a northwest-trending belt of Triassic to Jurassic arc terranes that hosts numerous significant porphyry Cu-Au ± Ag and associated epithermal Au-Ag deposits. The ATTY Property is in between and contiguous to Centerra Gold's Kemess Project and the JOY Project held by Amarc Resources and Freeport-McMoRan. The ATTY Property's KEM target has similarities to the Kemess North Trend, which hosts the Kemess Underground and Kemess East deposits. The PIL Property, which covers 13,374 ha in the heart of the Toodoggone region, has numerous porphyry Cu-Au ± Ag targets and associated epithermal Au-Ag mineralization. The PIL Property is neighboured by Amarc Resources and Freeport-McMoRan's JOY Project and TDG Gold Corporation's Shasta/Baker and Sofia Properties. The PIL Property is also 25 km northwest of Centerra Gold's past-producing Kemess South Mine and 15 km east of Thesis Gold's Lawyers Project. The Silver Hope Property covers 21,322 ha and surrounds the past-producing Equity Silver Mine in the prospective Skeena Arch region of central B.C. The Silver Hope contains the Main Trend which is a >2 km Cu-Ag-Au mineralized trend with mineralization starting at surface. West of the Main Trend is the West Cu-Mo Porphyry which is also mineralized starting from surface. The Property hosts a network of forestry roads and trails and has all-year access from Houston, BC. The SAY Property covers 26,202 ha and is located 140 km north of Smithers, B.C. The SAY Property is within a 135-km long belt of relatively unexplored Stikine Terrane, with American Eagle Gold's NAK and Amarc Resources and Boliden Mineral Canada's DUKE Cu-Mo-Ag-Au porphyry prospects at the southern end, to HDI Quartz Mountain Resources Ltd.'s Jake Project Cu-Au-Ag porphyry discovery at the north end of the belt. The SPUR and SHEL zones are the most advanced targets on the SAY property. The SPUR is a high-grade Cu-Ag structural controlled vein and breccia target extending for 4.3 km with assays up to 15.8% Cu and 993 g/t Ag. The SHEL target area is a Cu-Mo porphyry identified by historic mapping and drilling. The JJB Property covers 15,423 ha 10 km north of the SAY Property. The JJB Property covers known gossans with associated Cu-Au-Ag geochemical anomalies. Finlay trades under the symbol "FYL" on the TSXV and under the symbol "FYMNF" on the OTCQB. For further information and details, please visit the Company's website at On behalf of the Board of Directors, Robert F. Brown Executive Chairman of the Board & Director Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts responsibility for the adequacy or accuracy of this release. Forward-Looking Information: This news release includes certain "forward-looking information" and "forward-looking statements" (collectively, "forward-looking statements") within the meaning of applicable Canadian securities legislation. All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as "expect", "plan", "anticipate", "project", "target", "potential", "schedule", "forecast", "budget", "estimate", "intend" or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. Forward-looking statements in this news release include statements regarding, among others, the exploration plans for the PIL & ATTY Properties. Although Finlay believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploration successes, and continued availability of capital and financing and general economic, market or business conditions. These forward-looking statements are based on a number of assumptions including, among other things, assumptions regarding general business and economic conditions, the timing and receipt of regulatory and governmental approvals, the ability of Finlay and other parties to satisfy stock exchange and other regulatory requirements in a timely manner, the availability of financing for Finlay's proposed transactions and programs on reasonable terms, and the ability of third-party service providers to deliver services in a timely manner. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. Finlay does not assume any obligation to update or revise its forward-looking statements, whether as a result of new information, future or otherwise, except as required by applicable law. SOURCE Finlay Minerals Ltd.