Salim Water Treatment Plant upgrading works ahead of schedule, expect completion in June 2027, says Julaihi
Julaihi (third left) reviews the progress of the water treatment plant upgrade during the site visit today.
SIBU (April 25): The upgrading project of the Salim Water Treatment Plant in Sibu has reached 17.96 per cent completion, ahead of the initial target of 6.45 per cent, said Sarawak Minister of Utility and Telecommunication, Dato Sri Julaihi Narawi.
He said the upgrade will double the plant's capacity from 150 million litres per day (MLD) to 300 MLD, enabling a 30 per cent water reserve margin for Sibu and its surrounding areas once completed.
'We've seen steady progress since the project started in May 2024.
'This project is not only progressing smoothly but is also ahead of schedule. We expect it to be completed as planned and capable of supplying clean water to 350,000 residents in the Sibu area,' he told reporters after a working visit to the site at Muka Sauk, Sibu Water Board (SWB), Jalan Stabau today.
Julaihi said the RM291 million project, funded entirely by the Sarawak government, carries a contract value of RM269 million.
It is part of the Sarawak Water Supply Master Plan and supports the implementation of the state's water grid system aimed at interconnecting water treatment plants across the state.
At present, Julaihi said Sibu is served by two main plants — Salim (150 MLD) and Bukit Lima (45 MLD) — with a combined capacity of 195 MLD.
However, daily demand has already surpassed this, reaching 200 MLD, resulting in both plants operating beyond capacity.
'As a long-term solution, the Sarawak government has also approved RM1.1 billion for the replacement and upgrade of old pipes across the state, covering 2,740 km of pipelines, to be implemented over five years.
'For the Sibu Division alone, RM170 million has been allocated,' he said.
He also noted that a new water supply system at Sungai Sadit has been completed and will help boost Sibu's water reserve margin.
'This isn't an overnight solution. It's a long-term plan we're executing through the water master plan and the Sarawak water grid system,' said the Sebuyau assemblyman.
Meanwhile, SWB clarified that the total project cost of RM291.4 million includes construction, land acquisition for the raw water pipeline, site supervision, and professional fees.
Key components of the project include the Phase 2 upgrade of the raw water intake from 150 MLD to 300 MLD; construction of an 8 km new raw water pipeline using 1.4m diameter mild steel pipes; upgrading of the Salim Treatment Plant from 150 MLD to 300 MLD; modification of existing components in Salim Treatment Plant Phases 1 and 2 (sludge bridge, generator set, filters); and construction of a 4km treated water pipeline (2km with 1.6m diameter and 2km with 1.2m diameter).
'The project was awarded to contractor Perbena Emas Sdn Bhd through an open tender and granted on April 18, 2024, with a contract value of RM269,099,341.13.
'Construction works began on May 20, 2024, and are expected to be completed by June 25, 2027,' the board stated.
Upon completion, the upgraded plant will be capable of meeting the water supply needs of 350,000 residents in Sibu, Kanowit, Selangau, Maradong, and Rassau through to 2036.
Accompanying Julaihi during the site visit were the Permanent Secretary of the State Ministry of Utility and Telecommunication, Datu Jafri Lias; Rural Water Supply Department (JBALB) director, Ir Ts Awg Mohammad Fadillah Awg Redzuan; and SWB general manager Abdul Malik Abdullah. julaihi narawi Salim Water Treatment Plant Sibu
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Borneo Post
2 days ago
- Borneo Post
SWB: Sibu water woes traced to leaks at hospital, airport
Abdul Malik, flanked by Sia (left) and Loh, responds to a question posed during the press conference. SIBU (June 21): The ongoing water supply issues affecting Kemuyang, Sibu Jaya, Rascom Camp and the surrounding areas have been primarily attributed to leaks in the pipeline supplying water to the mentioned areas. Speaking at a press conference here today, Sibu Water Board (SWB) general manager Abdul Malik Abdullah revealed that investigations had pinpointed two key premises with suspected major internal pipeline leaks: Sibu Hospital, and Sibu Airport. 'In the case of Sibu Hospital, we have observed a noticeable increase in water consumption, from approximately 0.5 MLD (million litres per day) to 1MLD. 'Additionally, a review of the hospital's water bills also raised concerns. Typically, their monthly bill is around RM15,000. 'However, last month, it spiked to RM30,000. 'As for Sibu Airport, daily water consumption has doubled from 0.3MLD to 0.6MLD,' he said, adding that both locations had been notified of these matters. In view of this, he said the board had slightly reduced the sluice valve opening to regulate water flow to these two locations while awaiting repair works. According to Abdul Malik, many pipelines are ageing, with some already in service for about 30 years. He also highlighted that the water demand in Sibu had reached its peak at 195MLD, matching the combined production capacity of the existing plants: 150MLD from the Salim Water Treatment Plant, and 45MLD from the Bukit Lima treatment facility. 'This means the system is operating at full capacity. Even minor water disruptions or leaks can impact the overall supply,' he added. To address the issue, Abdul Malik said several main projects had been approved, with some currently being implemented. 'The Salim water treatment plant will increase its capacity from 150MLD to 300MLD, with RM300 million allocated by the Sarawak government,' he said, adding that the project commenced in May last year and should reach completion by mid-2027. 'Upon completion, Sibu's total water production capacity will increase to 345MLD, including output from the Bukit Lima water treatment plant, boosting the reserve margin in order to water usage, in which we anticipate until 2036.' Abdul Malik also said the Sarawak government had approved RM170 million for replacement of 360km stretch of ageing pipes in phases, from this year until 2028. 'This year, five packages worth RM51 million are being implemented as part of the overall project. The Sarawak government has allocated RM1.1 billion for the initiative, with RM170 million allocated to SWB,' he said. Furthermore, Abdul Malik pointed at the Sungai Sadit acute plant as among the mitigation measures, pending the completion of the upgrading works on the Salim water treatment plant. 'This acute system, with 4MLD production capacity, will increase our water reserves.' He also said the non-revenue water (NRW) reduction project, expected to be completed by April 2026, should lead to water savings of 15MLD. In addition, the Rural Water Supply Department (JBALB)'s project, an acute plant in Nibong Tada, once completed, would eliminate the need for SWB to supply 2MLD of water to JBALB. Among those present at the press conference were SWB senior manager (customer service and distribution) Loh Wei Lun and assistant executive (non-revenue water) Sia Yew Tatt. disruption pipeline leaks Sibu SWB water


The Sun
6 days ago
- The Sun
Berjaya Land partners Sweden's SIBS to develop RM170m housing project in Nuuk, Greenland
KUALA LUMPUR: Berjaya Land Bhd (BLand) is venturing into a RM170 million gross development value residential project in Greenland, an autonomous territory in Denmark, part of the company's plan to expand internationally and bring its experience in building homes to new markets. Group CEO Syed Ali Shahul Hameed said BLand is preparing to submit the necessary drawings to the local authority in Greenland for official approval. 'We have already received pre-approval, which means a similar design has already been reviewed and agreed upon by the Municipality of Nuuk, Greenland's capital. 'With this positive response, we can now move ahead with developing a detailed building plan. I expect that by next summer, we will be ready to begin actual construction,' Syed Ali said during the signing of a memorandum of understanding with SIBS Sdn Bhd (SSB) today. He said demand from the community for home purchases is very high, reflecting strong local interest and a clear need for new housing in Nuuk. To address this demand, BLand, through its wholly owned subsidiary Berjaya Greenland Invest A/S, has acquired land in Nuuk, aiming to provide high-quality residential apartments designed explicitly for Greenland's distinctive climate and infrastructure requirements. 'There is a shortage of available housing for residents in the area, so demand is high. 'Most of the time, as soon as we launch a project, the units sell out quickly. As for pricing, it is still a bit early for me to provide exact numbers, but generally speaking, costs are quite high, largely due to factors such as the cost of materials, including metal. 'However, I believe this is a strong investment opportunity overall,' Syed Ali said. BLand signed the MoU with SSB, a Sweden-based company with a manufacturing facility in Penang, a global leader in modular housing systems. This partnership aims to deliver efficient, climate-resilient homes through modular construction – a modern approach that enables faster deployment, cost savings and long-lasting quality. Currently, the housing project is still in the planning and design stages, but it is expected to launch soon. Besides making more homes available, the project will bring significant economic benefits, creating new jobs, involving local contractors, and supporting long-term city growth. 'Regarding the timeline for project implementation ... while we anticipate that the core construction phase can be completed within approximately one year, the logistics of transporting materials from Penang to Greenland may extend the overall schedule. 'We are committed to a thorough and efficient approach, ensuring that all aspects of the project are executed to the highest standards, despite the geographical and logistical challenges,' Syed Ali said when asked about the project's timeline. He said this project reflects BLand's broader vision of creating high-quality developments that are efficient, adaptable, and built with long-term impact in mind. 'Modular construction provides an innovative and timely approach, enabling us to deliver homes faster and more cost-effectively while supporting local capacity building.' SSB executive director Lawrence Chua Sue Lin said the company is developing a modular housing project, a relatively new concept for Malaysia. In this approach, homes are prefabricated in a factory, completed to a high standard and then transported to the intended site for assembly. This method is highly sustainable and environmentally friendly, as it significantly reduces reliance on manual labour, minimises construction waste, and shortens project timelines. While traditional high-rise construction can take up to three years, Chua said, modular housing can complete projects in less than a year, thanks to the company's current annual production capacity of up to 12,000 modules. 'However, in practice, a typical project might utilise around 6,000 modules. This innovative system not only accelerates delivery but also supports greener, more efficient urban development,' he added. With a particular focus on transforming Nuuk into a premier destination for recreation and ecotourism, Berjaya Greenland Invest aims to foster local economic growth, address critical housing needs, and create meaningful employment opportunities for the community.


New Straits Times
7 days ago
- New Straits Times
Berjaya Land enters Greenland with RM170mil apartment project
KUALA LUMPUR: Berjaya Land Bhd, a subsidiary of Berjaya Corporation, is making its first foray into Greenland with an apartment project in Nuuk, marking the group's expansion into the Arctic region. This strategic move aligns with Berjaya's long-term vision of global diversification and builds on its 2019 acquisition of a 75 per cent stake in Icelandair Hotels ehf for RM223.1 million, strengthening the group's presence in the North Atlantic tourism corridor. Through close engagement with the Municipality of Nuuk, Berjaya Land identified a pressing housing shortage in the city. In response, its wholly owned subsidiary, Berjaya Greenland Invest A/S, secured land parcels to develop high-quality residential apartments tailored to Greenland's climate and infrastructure requirements. In a major step forward, Berjaya Land today signed a Memorandum of Understanding (MoU) with SIBS Sdn Bhd (SIBS), a Sweden-based modular construction company with a manufacturing facility in Penang. The partnership will leverage SIBS' advanced modular housing systems to deliver climate-resilient homes more efficiently and cost-effectively. "We are excited to move forward with this collaboration, which marks a key milestone in our efforts to deliver modern, practical housing solutions that meet real community needs," said Syed Ali Shahul Hameed, group chief executive officer (CEO) of Berjaya Land. He said the first phase of the development will feature 66 apartment units housed in two- to four-storey blocks, with a projected gross development value (GDV) of RM170 million. Syed Ali said that this project reflects Berjaya Land's broader vision of creating high-quality developments that are efficient, adaptable, and built with a long-term impact in mind. "Modular construction offers a smart and timely approach, allowing us to deliver faster and cost-effective homes while supporting local capacity-building. Our focus remains on developing spaces that not only serve today's needs but also lay the groundwork for resilient, connected communities in the years ahead." The housing initiative is currently in the planning and design phase, with launch targeted later this year. Beyond improving housing access, the project is expected to generate meaningful economic benefits, including job creation, local contractor involvement and long-term urban growth, Syed Ali said. He revealed that Berjaya Land is actively collaborating with the Municipality of Nuuk to explore the next phase of development, which may include a hotel and hotel residences to support Greenland's expanding tourism industry. With the opening of Nuuk's new international airport in November 2024, the city is set to emerge as a major Arctic destination, said Syed Ali. He added that Berjaya Land's planned hospitality investment aims to meet this anticipated demand while upholding strong principles of cultural sensitivity and environmental sustainability.