Centre extends Kusum-C solarproject deadline to March 2026

Centre extends Kusum-C solarproject deadline to March 2026

Time of India09-06-2025

Bengaluru: Facing multiple hurdles in going ahead with the centrally sponsored PM-Kusum-C solar project, the state govt received a shot in the arm with the Centre extending the deadline for its implementation to March 2026.
Launched a year ago, Karnataka was supposed to solarise 389 power substations under all five electricity supply companies (Escoms) by Dec 2024. However, the state govt commissioned only about 15 stations, while the work on 370 plus substations is still in progress under PM-Kusum-C (Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyaan). CM Siddaramaiah is scheduled to inaugurate one of the commissioned stations at Gauribidanur in Chikkaballapur district Thursday.
The slow pace of the project in Karnataka is largely attributed to the delay in identifying and acquiring suitable land for setting up solar plants. "The solar plants need to be within a radius of 5-10km from substations, making it easier for the evacuation of power. While in some villages there was govt land, in some other villages, the govt land was not suitable for setting up solar plants, and we had to acquire private land on a lease basis.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Giao dịch CFD với công nghệ và tốc độ tốt hơn
IC Markets
Đăng ký
Undo
Even if there was land, the project agency spent considerable time levelling the ground for setting up solar plants. These hurdles in getting suitable land impacted the project considerably," explained a senior energy department official.
This apart, drawing of transmission lines also turned out to be a major hindrance. "In a few substation limits, the lines had to be drawn over private lands, and farmers were sceptical that they couldn't cultivate any fruit-bearing trees if they allowed any transmission lines over their fields or demanded compensation to allow installation of concrete poles to set up transmission lines...
We had to bypass such fields, and eventually, project implementing agencies had to take transmission lines underground at some locations," explained another engineer.
Acknowledging the delay in the availability of land, energy minister KJ George said efforts were made in every district by taking MLAs into confidence. "I agree that we could commission only a few of the substations. But nearly 90 per cent of the work is in various stages, and in a month or two, they will also be completed, and generation will start," the minister explained.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

CM flying squad to probe MCM sanitation contract
CM flying squad to probe MCM sanitation contract

Time of India

time41 minutes ago

  • Time of India

CM flying squad to probe MCM sanitation contract

Gurgaon: The CM flying squad has initiated an investigation into MCM's sanitation contract with Akanksha Enterprises, demanding documents such as tender details, contractor payments, and supervision records. The probe follows MCM's recent Rs 9.2 crore penalty on the contractor for inadequate service delivery. The contract, initially valid till Feb 2025, was extended to May. "A letter was sent to the MCM officials seeking details of the contract so that the CM flying squad could probe the matter. The civic body was given a week's time to probe the matter," said a ULB official privy to the matter. The contractor submitted an invoice of Rs 13.2 crore for services rendered during these three months. The representative of Akanksha Enterprises, Shishpal Rana, could not be reached despite repeated attempts by TOI. In April, the company also faced a Rs 4.3 crore penalty, during which they alleged bribery among senior MCM officials and payment delays, leading to the transfer of the then MCM commissioner. A sanitation standing committee reviewed the work of the agency between Feb 20, 2025, and May 19, 2025. A meeting was held on June 4 when the committee recommended deducting over Rs 9.17 crore from the agency's Rs 13.17 crore bill, approving only Rs 3.9 crore for payment. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với mức chênh lệch giá thấp nhất IC Markets Đăng ký Undo According to state govt-sanctioned estimates derived from central public health and environment engineering standards (SWM manual of CPPHEO norms, 20216) and the project's request for proposal (RFP), the agency was required to supply 1,997 personnel, 96 tractor trolleys, 468 rickshaw carts, and four earthmovers for sweeping roads in the MCM area. The urban local bodies (ULB) department stipulated that all SWM payments would be processed via the SWM monitoring portal starting Jan 2025. The committee observed a significant gap between the actual deployment figures shown on the SWM portal. It revealed personnel shortfalls of 1,315 in Feb, 1,355 in March, 1,533 in April, and 1,284 in May. Regarding equipment deployment, the committee's review showed that the agency provided only 101 rickshaw carts instead of the required 468 and merely 38 tractor trolleys against the specified 94, indicating substantial shortages in equipment provision for their work in the MCM area for three months.

1.6L water projects helping state ‘catch the rain'
1.6L water projects helping state ‘catch the rain'

Time of India

time41 minutes ago

  • Time of India

1.6L water projects helping state ‘catch the rain'

Lucknow: The 'Catch The Rain 2025' campaign to promote water conservation in the state saw over 1.66 lakh projects launched between Mar 22 and Jun 13, including rainwater harvesting projects, rejuvenation of traditional water sources and massive afforestation efforts. A govt spokesperson said 17,557 projects related to rainwater harvesting were completed, while 16,561 were in progress. Under MGNREGA, 5,714 traditional water body revival works were completed and 5,093 were ongoing. In the same period, 3,825 soak pit and stabilisation pond projects were completed, with another 512 underway. Watershed development saw 66,135 completed works and 52,097 in progress. In addition to this, 20,922 intensive afforestation works were executed, with 23,089 more currently underway. "The Krishi Vigyan Kendras successfully conducted 228 awareness and training programmes, educating farmers, students, rural women and youth on water management techniques. These activities were implemented by the departments of agriculture and horticulture," the official said. Lucknow: The 'Catch The Rain 2025' campaign to promote water conservation in the state saw over 1.66 lakh projects launched between Mar 22 and Jun 13, including rainwater harvesting projects, rejuvenation of traditional water sources and massive afforestation efforts. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với mức chênh lệch giá thấp nhất IC Markets Đăng ký Undo A govt spokesperson said 17,557 projects related to rainwater harvesting were completed, while 16,561 were in progress. Under MGNREGA, 5,714 traditional water body revival works were completed and 5,093 were ongoing. In the same period, 3,825 soak pit and stabilisation pond projects were completed, with another 512 underway. Watershed development saw 66,135 completed works and 52,097 in progress. In addition to this, 20,922 intensive afforestation works were executed, with 23,089 more currently underway. "The Krishi Vigyan Kendras successfully conducted 228 awareness and training programmes, educating farmers, students, rural women and youth on water management techniques. These activities were implemented by the departments of agriculture and horticulture," the official said.

Strict action will be taken against projects lacking proper permissions, says HYDRAA chief
Strict action will be taken against projects lacking proper permissions, says HYDRAA chief

Time of India

timean hour ago

  • Time of India

Strict action will be taken against projects lacking proper permissions, says HYDRAA chief

Hyderabad: At the Times Home Hunt Property Expo held recently, Hyderabad Disaster Management and Asset Protection Agency (HYDRAA) commissioner A V Ranganath cautioned that any new projects lacking proper permissions or built on encroached land will face strict action. 'Only layouts approved before HYDRAA's formation on July 19 last year will be exempt. All others must comply with current regulations,' said Ranganath, noting that unchecked construction contributed significantly to urban issues like flooding and traffic congestion. HYDRAA was set up not just as a watchdog, he said, but also as a proactive body aimed at promoting sustainable and responsible urban development. 'HYDRAA is not just about demolitions. We are focused on creating a healthier, more environmentally conscious real estate ecosystem,' Ranganath added. The authority is working closely with other agencies to rejuvenate lakes, address urban flooding, and improve drainage infrastructure. He also pointed out that traffic congestion alone costs the state nearly Rs 300 crore in infrastructure loss, underscoring the need for better planning. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với mức chênh lệch giá thấp nhất IC Markets Đăng ký Undo 'We received criticism that HYDRAA slowed real estate activity, but there were geopolitical concerns, delays in RERA clearances, and approval bottlenecks at GHMC and HMDA—also played a role. If a project is legally approved, we won't interfere. Our aim is to ensure compliance and environmental responsibility,' he said.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store