India's power grid gets a summer scare

India's power grid gets a summer scare

Mint17 hours ago

New Delhi: India faced a power grid scare last week as electricity withdrawn from the transmission network exceeded the available capacity, raising fears about the grid's stability.
The available transfer capability (ATC) in the western-to-northern corridor was about 22 gigawatts (GW) against the actual flow of 24.14 GW on 15 June, showed a notice sent to utilities by Grid India Corp. ATC is the volume of power that can be safely supplied between two points.
The national power grid controller wrote to the generators and electricity distribution companies (discoms) in the northern region to either lower the withdrawal or ramp up generation.
Also read: NHPC shelves plan for co-promoter stake buy in PTC India
After temperatures eased in May, there was a heat wave in June, which would have increased the demand, mostly in northern India, leading to congestion, said Vikram V, vice-president and co-group head, corporate ratings, ICRA Ltd.
A grid collapse is the worst-case scenario. Nearly 620 million people across 19 states and three Union territories went without electricity for hours together when the northern grid collapsed on 31 July 2012. In a wider blackout, the northern, eastern and north-eastern grids broke down on 1 August 2012.
India now has a unified national grid.
Vikram said instances of overdrawing were quite common till 2014-25, but have declined since then. Usually, in case of congestion, the grid operator may direct the utilities to reduce the offtake to avert any kind of impact on the grid. Issues arise when discoms draw larger than scheduled power from the inter-state grid to meet the high demand, he said.
Addressing entities in the northern region 'over-drawing or under-injecting" power to the grid, the controller's notice said: 'The following regional entities, which are downstream of the congested corridor, are advised to reduce their drawal/increase their generation to decongest the system."
Also read: EESL signs energy efficiency pacts worth ₹500 crore
Grid India told the utilities in western and southern India to increase demand or decrease generation to decongest the corridor.
'This is a warning notice before levy of congestion charges and issued in accordance with the Central Electricity Regulatory Commission (Measures to relieve congestion in real time operation) Regulations 2009," the notice said.
The peak power demand of the country hit 241 GW, the highest this year, on 11 June. That day, the peak demand in the national capital reached 8,231 MW, nearing the record of 8,656 MW recorded last year.
The peak demand on 15 June was 226 GW, also on the higher end.
Tardy grid expansion
Experts suggest that grid expansion is key for reducing incidences of congestion. More so when the installed renewable energy capacity has been rising.
Although the government has an ambitious road map to expand the grid, progress has been slow amid land acquisition and right-of-way issues. Data from the Central Electricity Authority (CEA) showed that in FY25, only 8,830 circuit kilometres (ckm) of transmission lines were added, 37.8% lower than 14,203 ckm in the previous fiscal and way short of the target of 15,253 ckm.
Mint earlier reported that clouds over vast swathes of north India in May had caused abrupt dips in solar power production, raising worries about the stability of the power grid that serves millions of Indians.
Also read: Top power authority mulls sops for critical components as China curbs rare earth supply
In February, the national grid operator asked all electricity companies to be alert and supply power to preserve the grid's stability.
An analysis by the International Energy Agency (IEA) in March said that countries seeking to prevent or address grid congestion should adopt a proactive approach to grid expansion by means of anticipatory planning and regulatory reforms that incentivize investments in line with countries' energy policy priorities.
Congestion can also be mitigated by implementing grid-enhancing technologies, increasing transparency on available capacity, and creating regulatory frameworks and clear price signals to unlock flexibility from consumers, producers and energy-storage assets connected to the grid.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

ACME Solar inks pact to supply 250 MW electricity from RE project in Rajasthan
ACME Solar inks pact to supply 250 MW electricity from RE project in Rajasthan

Time of India

time14 hours ago

  • Time of India

ACME Solar inks pact to supply 250 MW electricity from RE project in Rajasthan

New Delhi: ACME Solar Holdings on Friday said it has inked a pact with state-owned NHPC to supply 250 MW of electricity from a renewable energy project in Rajasthan. The power purchase agreement (PPA) has been signed at a tariff of Rs 4.56 per kWh for a minimum annual Capacity Utilization Factor (CUF) of 40 per cent and to meet 90 per cent of peak power requirement of 4 hours daily, according to a company statement. ACME Solar Holdings Ltd (ACME Solar) signed a 25-year PPA with NHPC Limited, a AAA-rated central government enterprise, for its 250 MW Firm and Dispatchable Renewable Energy (FDRE) project in Rajasthan, the company said. This PPA marks a significant step in strengthening ACME Solar's footprint in the FDRE space while supporting India's clean energy ambitions through an innovative mix of solar, wind, and battery storage technology. The project will be connected to an ISTS (Inter-State Transmission System) substation for which connectivity is already in place. The requisite approval under section 63 of the Electricity Act 2003 for adoption of tariff has been issued by CERC (Central Electricity Regulatory Commission) on June 19, 2025, the company said. With this, the company's PPA-signed portfolio stands at 5,130 MW, of which 2,826.2 MW is already operational, and the balance is under various stages of implementation. ACME Solar's overall portfolio comprises 86 per cent offtake with central government enterprises and the remaining 14 per cent with State discoms. The company is an integrated renewable energy player with a diversified portfolio of 6,970 MW spanning solar, wind, FDRE and hybrid solutions. PTI

India's power grid gets a summer scare
India's power grid gets a summer scare

Mint

time17 hours ago

  • Mint

India's power grid gets a summer scare

New Delhi: India faced a power grid scare last week as electricity withdrawn from the transmission network exceeded the available capacity, raising fears about the grid's stability. The available transfer capability (ATC) in the western-to-northern corridor was about 22 gigawatts (GW) against the actual flow of 24.14 GW on 15 June, showed a notice sent to utilities by Grid India Corp. ATC is the volume of power that can be safely supplied between two points. The national power grid controller wrote to the generators and electricity distribution companies (discoms) in the northern region to either lower the withdrawal or ramp up generation. Also read: NHPC shelves plan for co-promoter stake buy in PTC India After temperatures eased in May, there was a heat wave in June, which would have increased the demand, mostly in northern India, leading to congestion, said Vikram V, vice-president and co-group head, corporate ratings, ICRA Ltd. A grid collapse is the worst-case scenario. Nearly 620 million people across 19 states and three Union territories went without electricity for hours together when the northern grid collapsed on 31 July 2012. In a wider blackout, the northern, eastern and north-eastern grids broke down on 1 August 2012. India now has a unified national grid. Vikram said instances of overdrawing were quite common till 2014-25, but have declined since then. Usually, in case of congestion, the grid operator may direct the utilities to reduce the offtake to avert any kind of impact on the grid. Issues arise when discoms draw larger than scheduled power from the inter-state grid to meet the high demand, he said. Addressing entities in the northern region 'over-drawing or under-injecting" power to the grid, the controller's notice said: 'The following regional entities, which are downstream of the congested corridor, are advised to reduce their drawal/increase their generation to decongest the system." Also read: EESL signs energy efficiency pacts worth ₹500 crore Grid India told the utilities in western and southern India to increase demand or decrease generation to decongest the corridor. 'This is a warning notice before levy of congestion charges and issued in accordance with the Central Electricity Regulatory Commission (Measures to relieve congestion in real time operation) Regulations 2009," the notice said. The peak power demand of the country hit 241 GW, the highest this year, on 11 June. That day, the peak demand in the national capital reached 8,231 MW, nearing the record of 8,656 MW recorded last year. The peak demand on 15 June was 226 GW, also on the higher end. Tardy grid expansion Experts suggest that grid expansion is key for reducing incidences of congestion. More so when the installed renewable energy capacity has been rising. Although the government has an ambitious road map to expand the grid, progress has been slow amid land acquisition and right-of-way issues. Data from the Central Electricity Authority (CEA) showed that in FY25, only 8,830 circuit kilometres (ckm) of transmission lines were added, 37.8% lower than 14,203 ckm in the previous fiscal and way short of the target of 15,253 ckm. Mint earlier reported that clouds over vast swathes of north India in May had caused abrupt dips in solar power production, raising worries about the stability of the power grid that serves millions of Indians. Also read: Top power authority mulls sops for critical components as China curbs rare earth supply In February, the national grid operator asked all electricity companies to be alert and supply power to preserve the grid's stability. An analysis by the International Energy Agency (IEA) in March said that countries seeking to prevent or address grid congestion should adopt a proactive approach to grid expansion by means of anticipatory planning and regulatory reforms that incentivize investments in line with countries' energy policy priorities. Congestion can also be mitigated by implementing grid-enhancing technologies, increasing transparency on available capacity, and creating regulatory frameworks and clear price signals to unlock flexibility from consumers, producers and energy-storage assets connected to the grid.

ACME Solar inks pact with NHPC to supply 250 MW electricity to RE project in Rajasthan
ACME Solar inks pact with NHPC to supply 250 MW electricity to RE project in Rajasthan

Mint

timea day ago

  • Mint

ACME Solar inks pact with NHPC to supply 250 MW electricity to RE project in Rajasthan

ACME Solar Holdings on Friday said it has inked a pact with state-owned NHPC to supply 250 MW of electricity from a renewable energy project in Rajasthan. The power purchase agreement (PPA) has been signed at a tariff of ₹ 4.56 per kWh for a minimum annual Capacity Utilization Factor (CUF) of 40 per cent and to meet 90 per cent of peak power requirement of 4 hours daily, according to a company statement. ACME Solar Holdings Ltd (ACME Solar) signed a 25-year PPA with NHPC Limited, a AAA-rated central government enterprise, for its 250 MW Firm and Dispatchable Renewable Energy (FDRE) project in Rajasthan, the company said. This PPA marks a significant step in strengthening ACME Solar's footprint in the FDRE space while supporting India's clean energy ambitions through an innovative mix of solar, wind, and battery storage technology. The project will be connected to an ISTS (Inter-State Transmission System) substation for which connectivity is already in place. The requisite approval under section 63 of the Electricity Act 2003 for adoption of tariff has been issued by CERC (Central Electricity Regulatory Commission) on June 19, 2025, the company said. With this, the company's PPA-signed portfolio stands at 5,130 MW, of which 2,826.2 MW is already operational, and the balance is under various stages of implementation. ACME Solar's overall portfolio comprises 86 per cent offtake with central government enterprises and the remaining 14 per cent with State discoms. The company is an integrated renewable energy player with a diversified portfolio of 6,970 MW spanning solar, wind, FDRE and hybrid solutions.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store