eThekwini Municipality allocates R10 million for urgent repairs at Durban landfill sites
The eThekwini Municipality landfill sites will receive much needed repairs following the March 2025 floods in Durban.
Image: File
The eThekwini Municipality will spend R10 million to repair March 2025 storm-related damage at the Bisasar Road and Buffelsdraai landfill sites.
The municipality stated that work has begun at Buffelsdraai, but none have yet begun at Bisasar Road in Clare Estate, where a contractor is being sourced by the Cleansing and Solid Waste Unit (CSW).
In a report by CSW, it stated that infrastructure has been compromised and that these landfills are required by law to have waste disposal areas operated to prevent negative impacts such as odour, toxic leachate waters being formed from rainfall infiltration, and landfill gas migration, etc.
The CSW stated that the repairs are deemed critical based on the damage requiring urgent attention.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad loading
The sites were damaged because of rapid runoff coupled with the saturated soils from the rains that had resulted in these landfill sites experiencing flash flooding, which not only overwhelmed the site's infrastructure, but resulted in damages to leachate (toxic waste waters) systems, access erosion and consequential damage to landfill, and extraction pipework infrastructure.
The report stated that CSW engineers have applied a due diligence assessment and categorised the site as bordering on unsafe and requiring a competent contractor/s to make the safe works and mitigate further negative impacts, noting that site teams have exhausted options internally to make good areas with temporary fixes.
Other works will entail specialist works on leachate containment and landfill gas infrastructure, in which tenderers' attention to functionality will be needed.
The report stated that failure to conduct repairs will result in pollution to the environment and a reduction in the waste management service standard for the ratepayers.
Alicia Kissoon, eThekwini Ward 23 councillor, said residents surrounding Clare Estate raised concerns about the strong odours emanating from the Bisasar Road.
Following interventions from CSW, Kissoon said that the landfill gas system is operational, pipe repairs have been completed, and an internal toolbox talk was conducted to ensure that staff avoid the recently damaged area, especially during wet weather.
'The removal of standing uncovered waste and the backlog of waste cover caused by recent flood events is ongoing. The odour control spray system has been ramped up, and operational staff hours have been extended to ensure continued maintenance of control systems. I will continue to monitor the situation and maintain open lines of communication with the department to ensure further mitigation and accountability,' she said.
At a recent council meeting, Sunitha Maharaj, Minority Front councillor, said the Bisasar Road landfill site should have been decommissioned and rehabilitated as it has surpassed its lifespan.
'We support all measures to make landfill sites safe. It may or may not be common knowledge that this site poses serious environmental and health risks. Despite numerous requests from the affected community over the years to close the site, it remains open,' Maharaj said.
zainul.dawood@inl.co.za

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Citizen
2 days ago
- The Citizen
Clarity sought on alleged R700m cost of National Dialogue
The Presidency's plan to hold a major National Dialogue in August is being criticised for its potential cost, lack of oversight, and uncertain agenda. The proposed National Dialogue has the potential to be another watershed moment for South Africa, as the Convention for a Democratic SA was in the early '90s. Picture: Gallo Images/Die Burger There are concerns about the lack of transparency around President Cyril Ramaphosa's proposed National Dialogue that is meant to take place in a few weeks. Ramaphosa said the country will hold the first leg on 15 August, with the second leg expected to take place next year. Local talks will be held before then. The purpose of this convention is to discuss South Africa's problems and find solutions to them. However, it has been met with anger following an announcement that it could cost more than R700 million. Unions and political parties call for accountability The government has stated that there is no definite figure yet. Congress of South African Trade Unions (Cosatu) spokesperson Matthew Parks said he is concerned about the abuse of state funds used for the National Dialogue. 'We can talk about figures like R10 million or R20 million, but R700 million is just ridiculous. 'Government can find ways of ensuring this is done in a manner that is more affordable. We just objected to a VAT hike, it would not make sense for us to agree to this,' he said. Conflicting statements over the proposed budget Parks said Cosatu had engaged with the Presidency and was reassured there is no final figure for how much the dialogue will cost. The amount of R700 million was first estimated by Nkosinathi Biko, executive trustee of the Steve Biko Foundation. ALSO READ: Ramaphosa announces 'Eminent Persons Group' to guide national dialogue – These are the people appointed 'Nothing has been tabled to parliament and Cabinet, so this is random ramblings from some officials and people from foundations,' said Parks. Questions about coordination and purpose Rise Mzansi spokesperson Mabine Seabe said: 'The touted R700 million price tag appears excessive, which is why Rise Mzansi will be engaging with President Cyril Ramaphosa on this matter and timelines both in the buildup to and after the National Dialogue. 'We will use our parliamentary oversight authority to ensure that every rand and cent is accounted for.' ActionSA parliamentary leader Athol Trollip said parliamentarians have not been given intricate details of how the National Dialogue will be coordinated. Presidency spokesperson Vincent Magwenya told SAfm this week: 'There isn't a budget, there isn't a number or a cost that the government has committed to. 'All we have is what has been communicated as a proposal that the foundations have put forward. 'Government is going to be the fiscal custodian of the process and it has not yet engaged in formulating a budget. So the debate about R700 million is completely misplaced and unnecessary.' Dialogue 'must be ambitious' Dr Philani Mthembu from the Institute for Global Dialogue said the dialogue, if done correctly, can be an important tool in addressing problematic legislation and policies. ALSO READ: 'Bring all to dialogue': Experts insist national dialogue must be people-driven 'If this dialogue is compared to the Convention for a Democratic South Africa, then it needs to be ambitious in what it is trying to achieve. 'For instance, we must ask if this will open up the debate on reviewing the constitution, what elements of the constitution are working and which need to be revised. 'This dialogue could discuss issues such as electoral reform and whether we are ready for new systems that will hold those in power to account. 'It has to be ambitious, otherwise if we just discuss issues such as national cohesion and service delivery, we already know these challenges. Discussing the deep issues will have more impact.' A noble idea? Advocate Sipho Mantula, a researcher at Thabo Mbeki African School of Public & International Affairs, said the idea of a national convention is a noble one. 'Conventions are normally called when there is a national crisis or key issues that affect the country, from governance to the rule of law to the socio-cultural and economic conditions.' Mantula said all state organs and institutions should assist in ensuring the success of the National Dialogue and no-one should be left behind. 'It should begin with local conventions and then provincial conventions that ultimately lead to the National Dialogue,' he said. NOW READ: 'A meaningless publicity stunt by a limping president': EFF slams Ramaphosa's national dialogue call

IOL News
2 days ago
- IOL News
KZN government to establish a beef production enterprise for King Misuzulu's financial needs
King Misuzulu kaZwelithini will get his own beef production company to fund his cultural events. Image: Independent Newspapers Archives KwaZulu-Natal Finance MEC Francois Rodgers is in the process of establishing a beef production enterprise which will help the Zulu royal family to be financially independent and save the province more than R60 million which is annually allocated to King Misizulu kaZwelithini and the family. This was revealed by the Democratic Alliance chief whip in the provincial legislature Dr Imran Keeka on Thursday. The party was reflecting on its first anniversary of the Government of Provincial Unity, particularly its role and achievements. The party said one of its achievements is that it has strengthened relations with the AmaZulu Royal Household and its Finance MEC is working on a beef production enterprise to ensure the monarchy's fiscal independence. 'The Treasury under Rodgers is working on establishing a beef production enterprise to ensure the monarchy's fiscal independence,' said Keeka. If Rogers succeeds, he will achieve what has been elusive since 1994. There had been talk of creating a Royal Household Trust which previous provincial government administrations had described as the vehicle that was going to sustain the Zulu royal family financially and end its financial dependence on taxpayers who fund the king and the royal family's financial needs. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Reacting to the announcement, the Zulu royal family's spokesperson Prince Thulani Zulu said the family will comment after the MEC has officially informed his Majesty, King Misuzulu kaZwelithini about the details of the enterprise. Another major achievement listed was Rogers' ability to devise a cost-cutting strategy which has reduced the provincial government's projected over-expenditure from R10 billion to R800 million. The plan is now being implemented. The party described its participation in the GPU as a year of positive change for the people of the province, 'who now have a government focused on placing their needs first and realising the province's true potential'. It said the move from a single majority party government to a partnership consisting of KZN's four leading political parties has not been without its challenges, however, there have been notable successes. The party said its participation in the GPU has allowed it to play a key part in critical decision-making that affects the people of the province. These roles include heading KZN Finance Rodgers, Public Works and Infrastructure which is under MEC Martin Meyer, deputy Speaker through Mmabatho Tembe as well as chairing important portfolio committees such as Health, Cooperative Governance and Traditional Affairs and provincial SCOPA( Standing Committee on Public Accounts).


Eyewitness News
4 days ago
- Eyewitness News
Clinic renovation stalled because health department hasn't paid contractor
The renovation of the Evah Mota Clinic in Tsheseng village in Qwaqwa, Free State, is stalled because the provincial Department of Health owes the contractor millions of rands. The clinic has been closed since 2022 for major renovations. In the meantime, clinic staff are using old church buildings to treat patients, store medication and keep confidential patient files. The contractor, Phunya Consulting, abandoned the clinic site in November after waiting for payment. The department has only paid R7-million of the R10-million renovation cost. GroundUp visited the site last week and found it closed, with security guards stationed outside. At the church building being used temporarily as the clinic, patients were queuing outside to see the doctor, some sitting on the ground. One of the patients, Seipati Makume, said the church building is too small so patients have to wait outside, regardless of the weather. 'There are no chairs. You will stay at the clinic the whole day because the service is very slow. Imagine staying outside while it is raining,' she said. Sipho Mgudlwa, an executive at Phunya Consulting, confirmed that the contractor had left the site in November after the department failed to pay the outstanding balance for work done. 'We invoiced them last year but we did not get the money. We kept on working with our own money until our coffers dried up and we had to stop. 'We wrote letters to the department but we were told that they don't have the budget to pay us. Our last communication was in March,' he said. Mgudlwa said this was not the first time the project had been delayed by a failure to pay. Department spokesperson Mondli Mvambi confirmed that the department had only paid R7-million of the R10-million to the contractor. 'The Evah Mota Clinic is 95% complete with outstanding work on waste management and the water tank.' 'There was a delay in the payment processes to the main contractor which resulted in the contractor going off site.' He said the delay was due to 'cash flow challenges' in the department. 'We are working on mechanisms to get the outstanding work done,' Mvambi said. This article first appeared on GroundUp. Read the original article here.