NV Energy asking to raise rates by more than twice as much as needed, say experts
(Photo: Ronda Churchill/Nevada Current)
The Attorney General's Bureau of Consumer Protection says NV Energy requires less than half of the $224 million rate hike it's asking the Public Utilities Commission to approve for Southern Nevada customers, and criticized the utility for attempting to charge ratepayers for lavish spending on lodging and limos for company gatherings.
The 9% proposed rate hike is expected to cost the average customer an additional $15 to $20 a month.
An expert witness testifying on behalf of the BCP, Mark Garrett, says NV Energy, based on a formula used to determine its revenue requirement, needs a rate hike of $106 million to provide service to its customers in the south.
The utility is asking the PUC to include in the rate hike the cost of constructing Greenlink, a massive transmission line project, while it is still under construction and not benefitting ratepayers.
Greenlink's cost has ballooned from just under $2.5 billion to more than $4.2 billion, and could increase even more, depending on the outcome of President Donald Trump's trade wars with Mexico and Canada.
The increase related to Greenlink alone would hike rates by $60.6 million, or about $3.60 a month, for a little more than two years.
The company argues that including the cost of construction while in progress, which is usually not permitted because it requires customers to pay for a service not yet provided, will generate cash flow, and help maintain credit ratings.
In 2021, NV Energy's then-CEO Doug Cannon told state lawmakers that 'Nevadans will not be asked to pay for this investment until at least five to six years down the road.'
Cannon left the company last month, following the revelation that the utility overcharged some 80,000 customers, some going back as far as 20 years.
'The company is faced with meeting the demands of growth, addressing system reliability, resource adequacy, legislative goals and mandates, and operational needs as it relates to sufficient levels of staffing, technology, and insurance – all of which necessitates investments above those currently reflected in the existing revenue requirement,' NV Energy vice president and chief financial officer Mike Behrens said in testimony submitted to the PUC, justifying the utility's rate requests.
Behrens testified that including the costs of constructing Greenlink, while work is in progress, would help avoid a bond rating downgrade and higher interest rates on future debt.
Garrett, on behalf of the BCP, recommended the cost of constructing Greenlink not be included in the upcoming rate case.
'The company has not demonstrated a financial need,' Garrett countered, and said the claim that charging customers now for constructing the project would save money 'is inaccurate.'
While including the cost of construction in progress in the base rate would save the company $35 million in interest, it would cost customers $52.7 million in higher rates, and 'makes no economic sense for ratepayers,' Garrett testified.
NV Energy is also seeking to recoup $16.4 million in affiliate expenses incurred by the company or its affiliates, such as Berkshire Hathaway Energy, its holding company.
Among the expenses is an invoice for just under $1.3 million for Red Rock Resort, including $14,940 for incidentals, $152,156 for 'guest room attrition,' $575,068 for banquet food and beverages, $17,140 for internet, $78,482 for audio/visual services, and $3,248 for luggage porters.
Nichole Loar of the BCP recommended the PUC disallow all $16.4 million in affiliate expenses – including:
Chauffeured transportation services;
Washington, D.C. office building and related labor;
'Excessive lodging charges' at the Four Seasons Hotel in Washington, D.C. and the J.W. Marriott in Phoenix;
Lobbying expenses;
Outside counsel;
Corporate airfare;
Alcoholic beverages;
Entertainment; and
Charitable donations
'The utility needs to be reminded they operate with a Certificate of Public Convenience and Necessity (given by the PUC), which is a privilege to serve as a monopolistic entity, not a right,' Loar testified.
'The recent proposed increases are placing vulnerable demographics at a heightened risk for heat-related illnesses, such as heatstroke,' Las Vegan Angel DeFazio of the National Toxic Encephalopathy Foundation said in a news release following a consumer input session last week on the proposed increase. She noted that seniors and others on fixed incomes are challenged to cover essential expenses, such as food and medicine, and pay for energy, especially during the summer months when bills skyrocket.
The PUC is expected to hold hearings on the proposed rate hike in September. If approved, rates would increase on Oct. 1.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles
Yahoo
2 days ago
- Yahoo
Britain's risk of power outages this winter lowest since pre-Covid, Neso says
The risk of Britain having power outages this winter is lower than it has been for the past six years, according to forecasts by the public body responsible for keeping the lights on. The National Electricity System Operator (Neso) said there is set to be enough electricity to meet demand over the colder winter months. In its early winter outlook, Neso anticipates an average operational margin – the difference between supply of electricity and demand for it – of 6.6 gigawatts (GW) from the end of October to the end of March. This is the highest expected margin since the 2019-2020 winter and is greater than the 5.2 GW forecast last year. The publicly-owned operator is tasked with ensuring that the supply of and demand for electricity always remains balanced. If supply cannot meet demand then the country risks blackouts. An increase in the margin has been driven by several factors, Neso said, including growth in electricity supply from battery storage at both a national and regional level – which enables power from renewables to be stored and then released when it is needed. It also pointed to an increase in the availability of electricity generation from gas, and from a new power cable, known as the Greenlink interconnector, connecting electricity grids between Wales and Ireland. This increased supply is expected to more than offset an expected rise in demand during peak periods. The slight uptick marks a divergence from previous years, when demand has either stayed the same or fallen, but Neso said it is too early to say what might drive that increase. Neso said it expects there to be around six minutes over the winter period where it might have to resort to special measures to keep the grid running smoothly. In most cases where demand exceeds supply for a period of time, it is managed by the grid operator without any impact on consumers. Neso stressed it was remaining 'vigilant' in its preparation for the winter amid changes in global energy markets. 'Our early view of the winter ahead shows a positive outlook with sufficient margins throughout the colder winter months,' Deborah Petterson, Neso's director of resilience and emergency management said. 'We will continue to monitor developments in global energy markets, remaining vigilant in our preparations to ensure that the resilience and reliability of the electricity network is maintained.'
Yahoo
3 days ago
- Yahoo
Ormat Announces the Completion of Its Acquisition of the Blue Mountain Geothermal Power Plant From Cyrq Energy
ACQUISITION INCREASES ORMAT'S ELECTRICTY SEGMENT GENERATING PORTFOLIO TO 1,268MW POTENTIAL TO UNLOCK ADDITIONAL VALUE THROUGH EXPECTED PPA RENEWAL AND ASSET UPGRADES RENO, Nev., June 18, 2025 (GLOBE NEWSWIRE) -- Ormat Technologies, Inc. (NYSE: ORA), (the 'Company' or 'Ormat'), a leading geothermal and renewable energy company, announced today that it has closed its previously disclosed acquisition of the Blue Mountain geothermal power plant from Cyrq Energy. Under the agreement, Ormat paid $88 million for 100% of the equity interest in the 20MW power plant. The Blue Mountain geothermal power plant is located in Nevada and was originally built with Ormat technology. The 20mw geothermal plant currently delivers power under a PPA with NV Energy ('NVE'), which is set to expire at the end of 2029. As part of the Company's generation capacity growth strategy, Ormat plans to upgrade the power plant and increase its capacity by approximately 3.5MW. Ormat's strategic expansion plans also include the proposed addition of a 13MW solar facility to support the power plant's auxiliaries, pending permit and PPA approval. The overall transaction was funded through bank debt. Doron Blachar, Chief Executive Officer of Ormat Technologies, said, 'The acquisition of the Blue Mountain geothermal power plant enhances our portfolio and reinforces our commitment to sustainable base-load energy solutions. This acquisition not only immediately increases our generating capacity but also provides the potential for a significant upside in revenue generation through our planned upgrades and the potential addition of a solar facility. We are excited about the opportunities this acquisition brings, and we look forward to continuing our partnership with NV Energy as we deliver reliable and clean energy to the people of Nevada.' ABOUT ORMAT TECHNOLOGIES With six decades of experience, Ormat Technologies, Inc. is a leading geothermal company, and the only vertically integrated company engaged in geothermal and recovered energy generation ('REG'), with robust plans to accelerate long-term growth in the energy storage market and to establish a leading position in the U.S. energy storage market. The Company owns, operates, designs, manufactures and sells geothermal and REG power plants primarily based on the Ormat Energy Converter – a power generation unit that converts low-, medium- and high-temperature heat into electricity. The Company has engineered, manufactured and constructed power plants, which it currently owns or has installed for utilities and developers worldwide, totaling approximately 3,400MW of gross capacity. Ormat leveraged its core capabilities in the geothermal and REG industries and its global presence to expand the Company's activity into energy storage services, solar Photovoltaic (PV) and energy storage plus Solar PV. Ormat's current total generating portfolio is 1,558MW with a 1,268MW geothermal and solar generation portfolio that is spread globally in the U.S., Kenya, Guatemala, Indonesia, Honduras, and Guadeloupe, and a 290MW energy storage portfolio that is located in the U.S. ORMAT'S SAFE HARBOR STATEMENT Information provided in this press release may contain statements relating to current expectations, estimates, forecasts and projections about future events that are "forward-looking statements" as defined in the Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical facts, included in this press release that address activities, events or developments that we expect or anticipate will or may occur in the future, including such matters as our projections of annual revenues, expenses and debt service coverage with respect to our debt securities, future capital expenditures, business strategy, competitive strengths, goals, development or operation of generation assets, market and industry developments and the growth of our business and operations, are forward-looking statements. When used in this press release, the words 'may', 'will', 'could', 'should', 'expects', 'plans', 'anticipates', 'believes', 'estimates', 'predicts', 'projects', 'potential', or 'contemplate' or the negative of these terms or other comparable terminology are intended to identify forward-looking statements, although not all forward-looking statements contain such words or expressions. These forward-looking statements generally relate to Ormat's plans, objectives and expectations for future operations and are based upon its management's current estimates and projections of future results or trends. Although we believe that our plans and objectives reflected in or suggested by these forward-looking statements are reasonable, we may not achieve these plans or objectives. Actual future results may differ materially from those projected as a result of certain risks and uncertainties and other risks described under "Risk Factors" as described in Ormat's annual report on Form 10-K filed with the Securities and Exchange Commission ('SEC') on February 27, 2025, and in Ormat's subsequent quarterly reports on Form 10-Q that are filed from time to time with the SEC. These forward-looking statements are made only as of the date hereof, and, except as legally required, we undertake no obligation to update or revise the forward-looking statements, whether as a result of new information, future events or otherwise. Ormat Technologies Contact:Smadar LaviVP Head of IR and ESG Planning & Reporting 775-356-9029 (ext. 65726)slavi@ Investor Relations Agency Contact:Joseph Caminiti or Josh CarrollAlpha IR Group312-445-2870ORA@
Yahoo
7 days ago
- Yahoo
What has happened to Bournemouth Air Festival?
As hopes of a 2026 edition of Bournemouth Air Festival fade, what factors have led to its demise, and will it ever return? The private air show operator that was expected to run the event on a 10-year contract has pulled out of talks. The major sticking point was its plan to close the promenade and seafront between the piers, which the council said it legally could not do. The US-based firm has also blamed the "instability of the financial and political climate" for its decision to withdraw. The free air festival was first held in 2008 and has taken place every August, with the exception of 2020 when Covid restrictions were in place. At its peak, it attracted about 1.3 million visitors to the seaside conurbation, and estimates of how much it annually contributed to the local economy vary from £14m to £59m. But the cost to the council has sky-rocketed in recent years, with hikes across insurance, security, infrastructure and counter-terrorism measures. Bournemouth Christchurch and Poole Council (BCP) said its net budget for the four-day festival had risen from £300,000 in 2019 to £400,000 by 2022. New legislation brought in after the 2017 Manchester Arena bombing is also set to significantly increase costs for all organisers of public events. The authority, which has been run by a coalition since 2023, has already slashed millions from its budget as it grapples with a huge deficit for its special educational needs and disabilities (SEND) services. Half a million people attended the final council-funded air show in 2024, which was scaled back from four days to three, with the final net cost to the council reaching £248,000. In the months that followed, officers explored two options - one was for a sponsor to foot the £400,000 bill of a council-run event, the other was for an external operator to run the air show at no cost to the authority. With no firm offers of sponsorship, but five potential operators raising their hand, things began to look up. But those early discussions led to just two firm expressions of interest and, with one of those requiring financial backing from the council, the initial flurry of enquiries quickly dwindled to a shortlist of one. BCP's destination and leisure councillor Richard Herrett said the prospective organisers had flown from the US to attend the 2024 event, but had drawn up a "wide range of requests that would have created significant financial pressures on the council". A report to BCP councillors said the plan to close off the beach and promenade between Boscombe and Bournemouth piers was to enable "a variety of hospitality offers ranging in price". But the authority said the firm's "non-negotiable" request presented legal difficulties, as fencing off the area would contravene the Open Spaces Act 1906. After the report was published, but before councillors met to discuss it, the company announced it was pulling out. In a letter read to councillors, the operator, whose name was redacted, said: "Several factors led us to this decision, with the most significant being that, without the ability to fence off and restrict access to a significant part of the beach and the surrounding areas, it would be challenging to create a financially sustainable event model. "The instability of the financial and political climate were also factors that would challenge us to deliver the event in a similar manner to our other events." Council leader Millie Earl said: "We are still open to any interest from potential operators or sponsors. "In the meantime, we remain invested in the cultural future of our beautiful area and are continuing to work with our partners and support others where we can." The council says its Bay Run, Arts By the Sea Festival and Christmas in Bournemouth events will still go ahead. But, with 12-months needed to organise the air show, any potential air show sponsor or operator would now be working towards 2027 at the earliest. You can follow BBC Dorset on Facebook, X (Twitter), or Instagram. Bournemouth Air Festival in doubt as sponsor search ends In pictures: Bournemouth Air Festival 2024 BCP Council