Flood relief work in Hinjewadi continues despite PMRDA deadline
The flood relief and infrastructure works by Maharashtra Industrial Development Corporation (MIDC) and Maha-Metro Line-3 contractor Tata Projects is going on despite the June 15 deadline set by Pune Metropolitan Region Development Authority (PMRDA) commissioner Yogesh Mhase following severe waterlogging in Hinjewadi on June 7.
PMRDA and MIDC officials conducted a joint review meeting and inspected the affected areas on Monday.
Heavy waterlogging on June 7 and June 13 turned Hinjewadi IT Park roads into flood zones. MIDC inspection found that barricades installed by the metro authorities in the middle of roads had blocked natural rainwater flow, leading to flooding on one side. The barricades were removed the next day.
MLA Shankar Mandekar visited the site on June 9 along with PMRDA, MIDC, and metro officials. Mhase chaired a meeting with officials on June 11 directing them to act swiftly.
On June 16, MIDC joint CEO Vijay Rathod and PMRDA joint commissioner Deepak Singla visited the site again.
'Work will be completed in 2–3 days,' said Nitin Wankhade, chief engineer, MIDC.
'They have cleaned a few spots and helped reduce waterlogging,' said Pawanjeet Mane, president, Hinjawadi IT Park Residents Welfare Association. He has urged authorities to clean major junctions and the eight-km stretch from NH-48 to Phase 3.
Ravindra Sinha, another resident member, said, 'They have made efforts like opening median gaps and clearing drains. But these are not enough to handle the 20 crore litres of runoff from the 5,000-acre catchment area. Reviving natural streams and removing illegal constructions are the only long-term solutions.'
Mhase said, 'Officials will submit progress report to the chief minister on Wednesday. Road repairs are affected due to continuous rain.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
8 hours ago
- Time of India
Lake levels rise 12% in 24hrs, easing water cut fears
Mumbai: The water stock in the seven lakes that supply to the city saw the steepest single-day increase this monsoon between June 19 and 20, surging from 1.9 lakh million litres (13.19% of total capacity) to 3.64 lakh million litres (25.17%). Earlier this week, on June 17 (Tuesday), the lake stock had dipped below 10%, reaching a worrying 9.78%, prompting the BMC to tap into its reserve stock, which the civic body has stopped following heavy rainfall in the lake catchment areas across Thane, Palghar and Nashik. The seven lakes are: Tansa, Bhatsa, Modak Sagar, Tulsi, Vihar, Upper Vaitarna, and Middle Vaitarna. Officials from the hydraulic department attributed the 12% jump in lake stock to intense rainfall in their catchment areas. The rise has eased fears of immediate water cuts. The civic body usually imposes water cuts in the 5-10% range in June of there is inadequate rainfall. Last year, for instance, a 10% water cut was imposed in the city from June 5 to July 29 after lake levels had dipped. Civic hydraulic department chief engineer Purshottam Malawade said that water cuts had anyway been ruled out as the BMC dipped into reserves, which would have sustained the city's needs until July. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Memperdagangkan CFD Emas dengan salah satu spread terendah? IC Markets Mendaftar Undo "But now we have stopped taking water from reserves as they belong to the irrigation department and the BMC has to pay for use," he said. Mumbai has a daily water requirement of 4,200 MLD (million litres per day). Meanwhile, Ransai Dam has begun overflowing, bringing relief to Uran township. The MIDC-run dam, which provides 35 million litres of water a day to Uran, ONGC, defence facilities, JNPT, Nhava Sheva, and 22 grampanchayats in Uran taluka, has resumed regular distribution. The facility implemented twice-weekly water restrictions since December due to reduced levels but has now achieved its complete storage capacity of 10 million cubic metres following substantial rainfall. Earlier this week, Powai lake, which supplies 10 MLD of water for industrial purposes, overflowed. Concerns over the lake have been consistent as 16-18 MLD of sewage enters it. BMC said it has a plan that includes diverting sewage lines, setting up a sewage treatment plant, and intensifying the removal of water hyacinth to restore the ecological health of the lake. (Inputs from BB Nayak)


Hindustan Times
4 days ago
- Hindustan Times
Flood relief work in Hinjewadi continues despite PMRDA deadline
The flood relief and infrastructure works by Maharashtra Industrial Development Corporation (MIDC) and Maha-Metro Line-3 contractor Tata Projects is going on despite the June 15 deadline set by Pune Metropolitan Region Development Authority (PMRDA) commissioner Yogesh Mhase following severe waterlogging in Hinjewadi on June 7. PMRDA and MIDC officials conducted a joint review meeting and inspected the affected areas on Monday. Heavy waterlogging on June 7 and June 13 turned Hinjewadi IT Park roads into flood zones. MIDC inspection found that barricades installed by the metro authorities in the middle of roads had blocked natural rainwater flow, leading to flooding on one side. The barricades were removed the next day. MLA Shankar Mandekar visited the site on June 9 along with PMRDA, MIDC, and metro officials. Mhase chaired a meeting with officials on June 11 directing them to act swiftly. On June 16, MIDC joint CEO Vijay Rathod and PMRDA joint commissioner Deepak Singla visited the site again. 'Work will be completed in 2–3 days,' said Nitin Wankhade, chief engineer, MIDC. 'They have cleaned a few spots and helped reduce waterlogging,' said Pawanjeet Mane, president, Hinjawadi IT Park Residents Welfare Association. He has urged authorities to clean major junctions and the eight-km stretch from NH-48 to Phase 3. Ravindra Sinha, another resident member, said, 'They have made efforts like opening median gaps and clearing drains. But these are not enough to handle the 20 crore litres of runoff from the 5,000-acre catchment area. Reviving natural streams and removing illegal constructions are the only long-term solutions.' Mhase said, 'Officials will submit progress report to the chief minister on Wednesday. Road repairs are affected due to continuous rain.'


Time of India
6 days ago
- Time of India
Hinjewadi civic woes: PMRDA to ensure median gaps to prevent waterlogging
1 2 3 Pune: Considering the severe waterlogging in Hinjewadi, Pune Metropolitan Region Development Authority (PMRDA) has decided to ensure adequate gaps in the central medians along the ongoing Metro Line 3 corridor to facilitate proper drainage of rainwater, senior officials from PMRDA told TOI on Saturday. The decision comes following complaints of flooding during recent heavy rain. PMRDA commissioner Yogesh Mhase told TOI on Saturday that the move follows consultations with the traffic police, after multiple stretches in Hinjewadi witnessed water accumulation, disrupting traffic. "If there are adequate gaps, water will not clog," Mhase said, adding that work is already underway at several stretches to address the issue. He directed the Metro project concessionaire to clear all construction debris from roads, footpaths, and stormwater drains by June 22. "The work is in progress but has slowed due to persistent rain. However, efforts are being made at multiple locations along the corridor," he said. Median gaps have already been created in some areas, and trench work is also being carried out. "To ensure smoother coordination, we've formed a WhatsApp group with all stakeholders. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Invertir con Cervecería Nacional CFD, si tienes 30 o más, puede alegrar tu cuenta bancaria Empieza a invertir Inscríbete ahora Undo It's helping us respond quickly to issues like waterlogging and construction debris," Mhase said. He also noted that a recent review meeting was held, and a June 15 deadline was set for general civic works. Due to continued rainfall, clean-up and drainage efforts will now continue throughout the week. A detailed report on the ongoing civic issues and mitigation measures will be submitted to chief minister Devendra Fadnavis, who also chairs PMRDA. The commissioner confirmed that action against illegal constructions and industries is also being taken, and a separate report on the same will be ready by Monday. On June 7, severe rainfall led to flooding in the MIDC road stretch between Metro Stations 3 and 4 in Hinjewadi. Affected spots included areas near the Vilas Javadekar residential complex, Dohler Company, and Sahyadri Girls Hostel. Similar problems were reported in Hinjewadi Phases 1, 2, and 3, leading to traffic congestion and major inconvenience for residents. Pune: Considering the severe waterlogging in Hinjewadi, Pune Metropolitan Region Development Authority (PMRDA) has decided to ensure adequate gaps in the central medians along the ongoing Metro Line 3 corridor to facilitate proper drainage of rainwater, senior officials from PMRDA told TOI on Saturday. The decision comes following complaints of flooding during recent heavy rain. PMRDA commissioner Yogesh Mhase told TOI on Saturday that the move follows consultations with the traffic police, after multiple stretches in Hinjewadi witnessed water accumulation, disrupting traffic. "If there are adequate gaps, water will not clog," Mhase said, adding that work is already underway at several stretches to address the issue. He directed the Metro project concessionaire to clear all construction debris from roads, footpaths, and stormwater drains by June 22. "The work is in progress but has slowed due to persistent rain. However, efforts are being made at multiple locations along the corridor," he said. Median gaps have already been created in some areas, and trench work is also being carried out. "To ensure smoother coordination, we've formed a WhatsApp group with all stakeholders. It's helping us respond quickly to issues like waterlogging and construction debris," Mhase said. He also noted that a recent review meeting was held, and a June 15 deadline was set for general civic works. Due to continued rainfall, clean-up and drainage efforts will now continue throughout the week. A detailed report on the ongoing civic issues and mitigation measures will be submitted to chief minister Devendra Fadnavis, who also chairs PMRDA. The commissioner confirmed that action against illegal constructions and industries is also being taken, and a separate report on the same will be ready by Monday. On June 7, severe rainfall led to flooding in the MIDC road stretch between Metro Stations 3 and 4 in Hinjewadi. Affected spots included areas near the Vilas Javadekar residential complex, Dohler Company, and Sahyadri Girls Hostel. Similar problems were reported in Hinjewadi Phases 1, 2, and 3, leading to traffic congestion and major inconvenience for residents. Follow more information on Air India plane crash in Ahmedabad here . Get real-time live updates on rescue operations and check full list of passengers onboard AI 171 .