Pushing steel bridge over railway line for Indrali RoB in Udupi complete
The National Highways division of Karnataka Public Works Department achieved a major milestone, albeit with much delay, after it installed a bow string steel bridge atop the Mangaluru-Mumbai railway line at Indrali in Udupi for the additional Railway Over Bridge on Malpe-Tirthahalli National Highway 169A on May 13.
Pushing the structure atop the railway line using hydraulic jacks began on May 12 morning with the task getting completed in about 36 hours. The Konkan Railway Corporation Limited gave periodical line and power blocks to facilitate pushing of the structure on the girders placed over bridge cribs.
The NH-PWD has commenced lowering the steel bridge by removing bridge cribs gradually to bring the structure to the road level. Both the ends of the steel bridge would be placed on concrete embankments on the sides of the railway track, said a senior NH-PWD engineer. The process might take about 8-10 days, he added.
Once the bow string steel bridge is securely placed at its location, the department would put concrete on the bridge surface. The additional RoB between Udupi and Manipal should be ready to take vehicular traffic before the end of May, the engineer added.
The department used hydraulic jacks, girders and rails atop the cribs to push the 12 metre wide, 58 metre long and about 476-tonne pre-assembled bridge inch-by-inch.
SoS to Railway Minister
Sensing an abnormal delay from KRCL in permitting pushing of the structure despite the Research Design and Standards Organisation (RDSO) of the Indian Railways certifying the structure, Udupi-Chikkamagaluru MP Kota Srinivas Poojary had on May 10 petitioned Railway Minister Ashwini Vaishnaw to intervene. Thereafter, KRCL permitted pushing of the structure on May 12.
As the additional RoB construction on the busy Udupi-Manipal four-lane road was being delayed since 2018, Mr. Poojary feared that the work might get further delayed if the rains start. He stayed at the location on May 12 night to oversee the work. The Indrali stretch of NH169A had become an accident-prone spot with the general public and organisations coming down heavily on the administration for the enormous delay in completion of the additional RoB.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
a day ago
- Time of India
Rispana-Bindal road projects: Concerns grow over environmental impact, lack of rehab plan
Dehradun: Concerns over the Rs 6,500 crore Rispana-Bindal elevated road project, which is touted as a 'solution to Doon's traffic woes' have intensified with several stakeholders, including residents, activists, and thousands of slum dwellers who may be displaced, expressing apprehension regarding the proposed 26-km elevated corridor, planned over the Rispana and Bindal riverbeds, aims to ease city traffic and offer a quicker route to Mussoorie. But activists claim it may cause irreversible ecological damage and permanently alter Dehradun's skyline. On Tuesday, the Dehradun Citizens Forum hosted a Town Hall Meet on the project at The Doon Library & Research Centre. The session featured a presentation by PWD engineer Jitendra Tripathi and consultancy firm Spectrum. Attended by over 100 professionals from diverse fields, the event saw strong calls for the immediate public release of the Environment Impact Assessment (EIA) and an inclusive cost-benefit analysis. Participants also urged that river rejuvenation efforts proceed independently of the corridor project. Officials said detailed project reports (DPRs) have been prepared and submitted to the state govt for approval. The criticism about the project centres on two fronts -- environmentalists fear the project will severely impact the Doon valley's ecology, while social activists warn of the large-scale displacement of residents once construction begins. The project also contradicts previous claims by the state govt to rejuvenate the rivers. Activists fear that such a large-scale infrastructure undertaking will leave no scope for restoration and could mark the end of these rivers. They are demanding transparency, environmental safeguards, and clear rehabilitation policies before work starts on the elevated road network. "There is both curiosity and concern among residents across Dehradun about the elevated roads being built over the fragile riverbeds of Rispana and Bindal," said social activist Anoop Nautiyal. "With pillars up to 15 metres high, this corridor risks permanently changing the city's ecological fabric. We're demanding that the Environmental Impact Assessment report be made public so that citizens can engage meaningfully and assess the true costs." Activists also called for public involvement in planning major infrastructure projects, especially those that claim to serve public interest. "There is often a stark contrast between govt claims and ground realities," said Manoj Dewaria, a resident of Kanwali Road. "They say it's to ease traffic, but what about the thousands of families whose future now hangs in the balance? There's been no talk of compensation or rehabilitation. What kind of public policy is this?" With project details still unclear, activists have filed several RTIs, but responses have been vague. One such reply from the PWD, accessed by TOI, stated: "In light of increasing traffic pressure in Dehradun and unavailability of space for road widening, the construction of the Rispana-Bindal elevated corridor is proposed. This will provide relief from traffic congestion in Dehradun. The project is under process and until its completion, specific details cannot be provided. "


Time of India
2 days ago
- Time of India
NEET PG 2025 application edit window opens at natboard.edu.in: Check list of editable fields here
The National Board of Examinations in Medical Sciences (NBEMS) has reopened the NEET PG 2025 application edit window on June 20, 2025, providing applicants with a final chance to review and revise their submitted forms before the exam scheduled for August 3, 2025. Tired of too many ads? go ad free now This period, open until June 22, offers candidates the opportunity to update key details such as date of birth, academic qualifications, gender, category, PwD and EWS status, and to re-upload essential images—including photographs, signatures, and thumb impressions—ensuring compliance with prescribed formats. However, certain fields remain locked: name, category, nationality, email address, mobile number, and test city cannot be modified during this window. This proactive correction facility underscores NBEMS's commitment to preventing administrative errors and enhancing candidate readiness ahead of NEET PG 2025. Editable fields in NEET PG application form 2025 Candidates can make changes to the following fields in their NEET PG application form: Personal & Academic Updates Date of Birth Gender Category (Scheduled Caste/Scheduled Tribe/Other Backward Classes/General) PwD & EWS Status Academic Qualifications Image Corrections Photograph, Signature, and Thumb Impression—must adhere to the updated specifications. This image correction window operates across two phases: pre-final and final—ensuring any upload discrepancies can be rectified. Non‑editable fields The following critical details are locked and cannot be corrected at this time: Name Category Nationality Email Address Mobile Number Test City Steps to make edits in NEET PG application form Here is how candidates will be able to edit their NEET PG forms online: Visit and navigate to the 'NEET PG' section. Click the application correction link. Log in using your user ID and password. Make permitted changes, re-upload images if needed, then save and re-submit. Pay any balance fees required for category or PwD status changes. Remember to double-check all updated entries before submitting, as changes made now will reflect on your admit card, and any mistake could cause issues during counselling or admission stages.


Time of India
3 days ago
- Time of India
Over 4,100 Trees In Nagpur Found Choked, Just 1,100 Freed So Far: NMC to HC
1 2 Nagpur: The Nagpur Municipal Corporation (NMC) on Thursday informed the Nagpur bench of Bombay High Court that over 4,147 trees across the city were found choked by concrete, but only 1,104 were de-choked so far despite directives and multiple agency involvement. The data was submitted during the hearing of a public interest litigation (PIL No. 39/2024) filed by environmental activists Sharad Patil, Prachi Mahurkar, Yash Netke, and Preeti Patel through counsel Radhika Bajaj. As per petitioners, while executing road improvement projects, the work of concretisation by cement, asphalt, or bitumen is choking roots of trees. They claimed though administrative instructions are issued to the contractors and subordinate officers to ensure removal of concrete, asphalt, or bitumen near trees, effective steps are not being taken by respondents. NMC counsel Jemini Kasat submitted the affidavit and minutes of meetings with agencies such as NHAI, NIT, and PWD, confirming the extent of choking and partial progress on relief efforts. Kasat told the court two experts—Kaustav Chatterjee of Green Vigil Foundation and Dilip Chinchmalatpure—were included in official de-choking panel as per court's earlier order. The panel has begun conducting site visits to verify work and shared technical recommendations, including removing concrete as per Urban Green Guidelines 2014, ensuring soil aeration, and protecting root systems. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với mức chênh lệch giá thấp nhất IC Markets Đăng ký Undo "The experts delivered a presentation on best practices and are expected to submit their assessments during the next review," Kasat said, adding that officials from PWD and NHAI have also been included for effective implementation on the ground. The petitioners objected to their exclusion from committee despite prior experience in tree conservation. The bench, comprising Justices Nitin Sambre and Sachin Deshmukh, questioned the civic body on this omission. NMC also submitted various govt departments have started following the 2014 Urban Green Guidelines and cited ongoing environmental audits by NEERI. Kasat informed the court Environment Status Reports (ESR) for the years 2017–18 to 2023–24 (barring 2021–22 due to the pandemic) were prepared scientifically by NEERI and submitted. The 2024–25 ESR is currently under preparation. The division bench gave time to file compliance documents, directing the finalised ESR for 2024–25 to be submitted by July 1, and adjourned the matter to July 9. The PIL highlights the alarming decline in Nagpur's green cover, which decreased from 31 percent in 1999 to a mere 21 percent in 2018, as per a study conducted by ISRO's Regional Remote Sensing Centre in 2019. The petitioners attribute this drastic reduction to the rapid expansion of urban infrastructure projects, which have adversely affected the city's once-abundant greenery.