Kavalam-Thattassery bridge: revised estimate gets KIIFB nod
The Kerala Infrastructure Investment Fund Board (KIIFB) has approved a revised estimate of ₹63.59 crore for the construction of the Kavalam-Thattassery bridge across the Pampa river in Kuttanad.
Earlier, KIIFB had given financial approval for ₹60.03 crore. However, a revision in the schedule of rates by the Public Works department prevented the Kerala Road Fund Board (KRFB), which has been entrusted with the bridge construction, from proceeding to the tendering stage.
'We will soon launch the tendering process. The work is expected to be awarded in two months,' said a KRFB official.
Financial approval
Though land acquisition was completed in 2023, the delay in receiving the final nod from KIIFB had stalled the project. While KIIFB granted financial approval two months ago, the revision of the schedule of rates necessitated the estimate to be revised, causing further delay.
In 2016, the State government had allocated ₹30 crore for constructing the bridge and approach roads. Later, the project cost was increased to ₹52 crore. Initially, authorities planned to acquire the land needed through direct negotiated purchase. However, some landowners demanded a change in alignment. As the alignment was fixed by the Inland Waterways Authority of India, officials rejected the request. Later, the Revenue department dropped the plan to acquire land through negotiated purchase.
By November 2018, the department announced that the land would be acquired by invoking the Land Acquisition Rehabilitation and Resettlement Act. Landowners were given time until December 1, 2018, to hand over consent letters. However, no follow-up action was initiated until 2020. After prolonged delays and protests led by a people's committee, more than an acre of land in Kavalam and Kunnumma villages was acquired for the project. Demolition of structures was completed in 2024. Nevertheless, the project remained stalled due to the pending clearance from KIIFB.
Cost escalation
The project cost increased due to cost escalation. The bridge will be approximately 400 m long and 8.5 m wide.
Once completed, the bridge will connect the Alappuzha-Changanassery (AC) road and the Main Central (MC) road. It will help reduce the distance between Alappuzha and Kottayam by around 9 km. It will also facilitate development in Kuttanad's remote areas.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


New Indian Express
4 hours ago
- New Indian Express
Work on major drinking water projects in Kochi inaugurated
KOCHI: The work on two 15-lakh litre water tank projects sanctioned under KWA's Amrut 2.0 sheme for Kochi Corporation was inaugurated by Water Resources Minister Roshy Augustine at an event held in Pallimukku on Saturday. The project approved last year with an estimated cost of Rs 15.51 crore includes construction of a 15 lakh litre over-head tank and a 15 lakh litre on-ground tank in Ward 60 in Perumanoor. The project aims to ensure smooth water supply to General Hospital and Thevara zones. The project is expected to be completed in a year. Additionally, work on Karumalloor- Kunnukkara drinking water scheme of Kalamassery municipality was also inaugurated on Saturday. The project is aimed at solving the drinking water requirements of residents in Kunnukara-Karumalloor panchayats. The Rs 51.30-crore project that will be implemented using KIIFB funds includes a 20 mld water treatment plant, an over-head tank in Malayikunnu, pumping stations, a 10.50 lakh litre overhead tank in Manjali, and a 250mm DIK9 clear main line to UC College overhead tank. The capacity of the project has been increased to 20mld to include Alangad panchayat as well in the distribution network. 'The project aims to ensure adequate drinking water supply to Kunnukara and Karumalloor areas for the next 50 years,' said Industries Minister P Rajeeve who spoke at the inaugural function of the event.


Time of India
18 hours ago
- Time of India
Minister hands over compensation for Phase II of Pazhakutty–Mangalapuram Road project
Thiruvananthapuram : Food and civil supplies minister GR Anil on Saturday handed over the compensation for Phase II of the Pazhakutty–Mangalapuram Road project to district collector Anu Kumari. At a formal event held in collectorate conference hall, the minister handed over a cheque of Rs 44.64 crore. The 20km-long and 13m-wide Pazhakutty–Mangalapuram Road is being developed with a total investment of Rs 170 crore from the Kerala Infrastructure Investment Fund Board (KIIFB). The compensation covers land acquired for the second reach of the project, stretching from Mukkam Palamoodu to Pothencode. This phase involves the acquisition of 1 acre and 70 cents from 400 families. Additionally, eight individuals eligible under the resettlement package will receive Rs 9.5 lakh each. The minister directed officials to expedite proceedings and complete compensation disbursement by Sept so that the tendering process can be initiated without delay. In the first reach of the project, 73.4 cent was acquired from 203 families, for which Rs 5.61 crore was disbursed as compensation. The 7km road section from Pazhakutty to Mukkam Palamoodu incurred an expenditure of Rs 35.52 crore, with Rs 12.93 crore allocated for its completion. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Giao dịch vàng CFDs với mức chênh lệch giá thấp nhất IC Markets Đăng ký Undo The construction on this stretch is scheduled to begin on July 1. The third reach, from Pothencode to Mangalapuram, involved acquiring 66 cent from 247 families, with Rs 9.46 crore already distributed as compensation. An amount of Rs 47.83 crore has been sanctioned for the construction work, which is currently nearing completion and is expected to be finalised by the end of July. The minister also instructed officials to take necessary steps to ease travel difficulties faced by the public during the construction phase. The review meeting was attended by deputy collector Muhammad Safeer and representatives from various departments.


Time of India
4 days ago
- Time of India
Govt approves official title for Vattiyoorkavu project, KRFB set to float tender soon
Thiruvananthapuram: The state govt finally approved the nomenclature for the long-awaited Vattiyoorkavu road project, clearing a major administrative hurdle that stalled the project for months. Finance department's approval, granted on June 11, allows the Kerala Road Fund Board (KRFB), the implementing agency, to move forward with floating the tender for the project. Originally known as 'Vattiyoorkavu Junction Development', the scope of the initiative was later expanded to include road development from Sasthamangalam to Mannarakonam via Vattiyoorkavu. This led the govt to mandate a more comprehensive title —'Vattiyoorkavu Road and Junction Development'. However, the delay in finalising the name held up the entire tendering process, despite preliminary demolition works nearing completion. Vattiyoorkavu MLA V K Prasanth confirmed that all roadblocks were resolved. "A revised detailed project report (DPR) is currently being prepared and will be submitted soon for approval by the Kerala Infrastructure Investment Fund Board (KIIFB). However, this DPR approval will not delay the floating of tenders," he told TOI. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like 5 Books Warren Buffett Wants You to Read In 2025 Blinkist: Warren Buffett's Reading List Undo Prasanth added that with tenders likely to be floated by July or Aug, the project was expected to move into the construction phase by Sept this year. The project is being executed in three major phases. The first section spans from Sasthamangalam to Mannarakonam via Maruthankuzhy. The second phase continues from Mannarakonam to Peroorkada through Mannamoola, while the final section stretches from Vattiyoorkavu to Vazhayila via Nettayam. These segments collectively form a 10.75km corridor that is among the busiest in the city. The total cost of the project is estimated at Rs 385 crore. The public works department (PWD) will oversee the technical execution, which includes widening the road to 18.5m and upgrading it to a four-lane carriageway with a 0.5m median. The design aims to streamline traffic flow and significantly reduce congestion across this vital route. To mitigate the impact on local businesses affected by land acquisition, the govt has allocated three acres between Mannarakonam and Thoppumukku to construct a shopping complex. This facility will accommodate over 200 shops. Contractors have been deployed to raze about 487 buildings along the Sasthamangalam–Mannarakonam 3.7km stretch. This includes 174 structures on the left and 181 on the right. The project was first conceptualised in 2016 as part of a broader Thiruvananthapuram road-improvement agenda spearheaded by KRFB, TRIDA, PWD and local govt bodies. Initial cost estimates stood at Rs 341.79 crore, with Rs 95 crore earmarked for land acquisition and Rs 219.75 crore for actual road works. Land acquisition across all three reaches already notified includes approximately 273.6 ares, roughly 6.76 acres, stretching across Sasthamangalam, Vattiyoorkavu and Peroorkada. The infrastructure design includes not just the widened four-lane road but also footpaths and street lighting, enhancing pedestrian safety and urban mobility.