Water release slows down bridge construction across the Cauvery in Tiruchi

Water release slows down bridge construction across the Cauvery in Tiruchi

The Hindu19 hours ago

Construction of a new bridge across the Cauvery, connecting Srirangam and Tiruchi, has slowed down because of the flow of water for irrigation in the delta region.
The Highways Department, which had commenced work on the bridge in July 2024, could not achieve much progress at the site because of continuous flow of water in the river in the following months but had taken up several off-site works, including getting the pre-cast girders ready for the super structure of the bridge.
The work gathered pace only during the Mettur closure period (between January 28 and June 12, the customary dates for the closure and opening of the Mettur dam, respectively).
Although the State Highways Department was keen to complete the foundation work before the irrigation season, it could not achieve the objective. Once the pile foundations were raised, work on the superstructure can continue even when there is water flow in the river, the authorities had hoped.
But following the opening of Mettur dam, the water flow (now stepped up to 18,000 cusecs) in the river has been substantial and the korambu (a sand bund) built to channel the water away from the work site on the riverbed was washed away, disrupting the pile foundation laying work. A total of 120 piles will have to be erected for the new bridge which would have 16 spans. The work has not been completed yet.
However, sources were at pains to emphasise that the work had not been suspended entirely. 'Some of the works on the riverbed closer to the left bank and off site works will continue. The other works would resume when the water flow comes down,' the sources said.
The bridge was sanctioned at an estimate of ₹106 crore in the State Budget for 2024-25 and is being built adjacent to the existing bridge. The existing bridge would be retained to cater to traffic coming from Mambazha Salai while the new one would be for vehicles going in the opposite direction.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

₹3,858 crore allocated for development of 448 km of four-lane roads under the Chief Minister's Road Development Scheme since 2021
₹3,858 crore allocated for development of 448 km of four-lane roads under the Chief Minister's Road Development Scheme since 2021

The Hindu

time16 hours ago

  • The Hindu

₹3,858 crore allocated for development of 448 km of four-lane roads under the Chief Minister's Road Development Scheme since 2021

The Tamil Nadu government said on Sunday that ₹3,858 crore had been allocated for the development of 448 km of four-lane roads and ₹2,207 crore for 1,681 km of two-lane roads under the Chief Minister's Road Development Scheme since it was launched in 2021. 'Currently, work is in progress on 383 km of four-lane roads at a cost of ₹2,807 crore and 357 km of two-lane roads at a cost of ₹709 crore,' it said. Under the Comprehensive Road Infrastructure Development Programme, a sum of ₹17,154 crore was allocated for 9,620 km of road projects and ₹1,161 crore was allocated for 996 bridge/culvert projects, said an official release listing the achievements of the Highways Department. Under the Urban Area Development Scheme, work to an extent of 164 km has been carried out at a cost of ₹731 crore. Pavement surface improved The pavement surface of 6,805 km of roads has been improved at a cost of ₹2,074 crore and 1,652 road safety projects have been completed at a cost of ₹662 crore. A total of 10 bypass roads have been completed at a cost of ₹307.8 crore. They include Manachanallur (Phase 1), Illuppur, Parthibanur, Rasipuram (Phase 1 Division-2), Bhavani (Phase II), Mudukulathur, Tiruttani, Coonoor, and Namakkal (Phase I). Under the Tamil Nadu Road Infrastructure Development Corporation, the Vandalur-Walajabad Road has been upgraded from four-lane to six-lane at a cost of ₹180.09 crore, and ₹1,372 crore was allocated for the conversion of 1,049 causeways into high-level bridges, the release said. As for projects with NABARD loan assistance and State funding, 278 bridges have been constructed at a cost of ₹1,137.62 crore. Overbridges Eight road overbridges have been constructed at a cost of ₹813.25 crore. The ongoing major projects include Coimbatore Western Bypass, Mannargudi (Phase-I), Ambasamudram, Tiruchengode (Phase I & II), Bhavani (Phase I), Namakkal (Phase-II and III), Pollachi Western Bypass, Aruppukkottai Western Bypass, Kamuthi-Sivaganga (Phase-I), Uthiramerur, Thuraiyur (Phase-II), Tambaram Eastern Bypass (two sections), and Thiruporur/ Kelambakkam. Under the Integrated Road Infrastructure Development Scheme, 2,264 km of road projects are being implemented at a cost of ₹8,076 crore, and 69 bridge/culvert projects are being executed at a cost of ₹694 crore, 134 causeways are being converted into high-level bridges at a cost of ₹763.80 crore, 32 high-level bridges are being constructed under the NABARD loan assistance scheme at a cost of ₹375.32 crore, and 19 high-level bridges are being constructed under the State-funding scheme at a cost of ₹596.64 crore, the release said.

Water release slows down bridge construction across the Cauvery in Tiruchi
Water release slows down bridge construction across the Cauvery in Tiruchi

The Hindu

time19 hours ago

  • The Hindu

Water release slows down bridge construction across the Cauvery in Tiruchi

Construction of a new bridge across the Cauvery, connecting Srirangam and Tiruchi, has slowed down because of the flow of water for irrigation in the delta region. The Highways Department, which had commenced work on the bridge in July 2024, could not achieve much progress at the site because of continuous flow of water in the river in the following months but had taken up several off-site works, including getting the pre-cast girders ready for the super structure of the bridge. The work gathered pace only during the Mettur closure period (between January 28 and June 12, the customary dates for the closure and opening of the Mettur dam, respectively). Although the State Highways Department was keen to complete the foundation work before the irrigation season, it could not achieve the objective. Once the pile foundations were raised, work on the superstructure can continue even when there is water flow in the river, the authorities had hoped. But following the opening of Mettur dam, the water flow (now stepped up to 18,000 cusecs) in the river has been substantial and the korambu (a sand bund) built to channel the water away from the work site on the riverbed was washed away, disrupting the pile foundation laying work. A total of 120 piles will have to be erected for the new bridge which would have 16 spans. The work has not been completed yet. However, sources were at pains to emphasise that the work had not been suspended entirely. 'Some of the works on the riverbed closer to the left bank and off site works will continue. The other works would resume when the water flow comes down,' the sources said. The bridge was sanctioned at an estimate of ₹106 crore in the State Budget for 2024-25 and is being built adjacent to the existing bridge. The existing bridge would be retained to cater to traffic coming from Mambazha Salai while the new one would be for vehicles going in the opposite direction.

Continuing accidents turn the spotlight on greenfield project plan for Tiruchi-Karur Highway
Continuing accidents turn the spotlight on greenfield project plan for Tiruchi-Karur Highway

The Hindu

time3 days ago

  • The Hindu

Continuing accidents turn the spotlight on greenfield project plan for Tiruchi-Karur Highway

The road accident causing the death of the Revenue Divisional Officer of Musiri on the Tiruchi-Karur Highway on Thursday has brought to the fore the demand for building a greenfield highway between the two cities. Activists have expressed concern that there was no sign of accidents coming down even after the State Highways Department widened the stretch a few years ago. The National Highways Authority of India (NHAI) had widened the Tiruchi-Karur Highway beyond Thindukarai several years ago. A bypass was to be laid between Panjapur on Tiruchi-Madurai highway and Thindukarai. The 11-km stretch from Thindukarai to Tiruchi, with sharp and dangerous curves, was widened from its earlier width of seven metres to up to 10.5 metres under the Comprehensive Road Infrastructure Development Programme 2019-20. However, accidents continue unabated on the road, the most recent one claiming the life of the senior Revenue Department Officer at Kadiyakurichi near Jeeeyapuram. Locals cite overspeeding as the main reason for accidents. Commuters traversing the stretch every day face the brunt of the problem. Accidents are frequent in Jeeyapuram and Pettavaithalai police station limits. 'The widening of the stretch does not seem have to helped bring down accidents,' said P. Ayyarappan, a member of District Road Safety Council and president, Road Users Welfare Association. There has been a number of accidents involving barricades, which are placed to force the vehicles to slow down, at various places, he said. Conceding that there was a need to give a push to the greenfield highway project as a long term measure, Mr. Ayyarappan suggested that medians could be built wherever possible in the meantime. 'There is enough space to widen the road by another two metres on either side at various stretches of the highway,' Mr. Ayyarappan said. Once the Panjapur-Thindukarai bypass is built, traffic density is bound to increase beyond Thindukarai. Speed guns should be installed and overspeeding should be penalised. Besides, highway patrolling by the police should be intensified, he added. Although the NHAI is preparing a detailed project report for the greenfield highway from Tiruchi to Karur, it has been progressing at a slow pace. The new alignment is planned 'at an offset of 12 to 13 km from the existing highway.' However, according to sources, the DPR is expected to be completed in another 10 to 12 months. Plea rejected The NHAI had rejected a plea from the public to develop an alternative road between Allithurai and Mayanur Tollgate. N. Jamaluddin, a civic activist, said the NHAI, in a reply to his petition on the matter in September 2024, had said that the task of preparing the DPR for the greenfield highway had been given to a Hyderabad agency in December 2017. 'The DPR preparation is taking such a long time while fatal accidents are taking place every other week so much so that we are forced to avoid the highway. The NHAI should expedite the process,' he said. The plan was discussed at the recent meeting of District Development Coordination and Monitoring Committee by Tiruchi and Karur MPs Durai Vaiko and S. Jothimani and both had promised to take up the matter, Mr. Ayyarappan said. At a press conference on Thursday, Mr. Durai Vaiko said he would take up the issue with the NHAI officials soon.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store