15.52 lakh cubic metres silt removed, Vadodara civic body to install coir nets on Vishwamitri banks to prevent erosion
With the June 15 deadline for the Vishwamitri river revival and flood mitigation project drawing closer, the Vadodara Municipal Corporation (VMC) has removed 15.52 lakh cubic metres of silt from the water body.
To prevent a washout during monsoon, the civic body has decided to install coir nets for riverbank stabilisation.
Notably, the amount of silt removed from the river is only half of the 34.98 lakh cubic metre of sludge extracted from different water bodies, including lakes, reservoirs and drains, in the city as part of the project.
The civic body, meanwhile, said that 90% of the work on the Vishwamitri project had been completed.
The VMC has issued tenders to procure 1.35 lakh square meters of high-strength erosion control coir mats that will enable stabilisation and reinforcement of the riverbank once the ongoing work of desilting and dredging is complete.
Experts said coir matting is helpful in holding the soil in place.
In a statement, the civic body said, 'Following the work of resurfacing, currently ongoing in the Vishwamitri river, in order to arrest the erosion of the river bank, installation of 1.35 lakh square meters of coir will be undertaken… Similarly, directions have been issued to dismantle the ramps created for movement of machines at 60 points along the riverbank, immediately after the completion of the work.'
The VMC said, 'The work is currently on in the last phase, and close to 15.15 lakh cubic metres of silt has been removed while about five kilometre stretch is now remaining to be completed.'
On Friday, the VMC said that it had extracted a total of 34.69 lakh cubic metres of silt during simultaneous projects — the deepening of the Ajwa and Pratappura reservoirs, creation of pond in Dena, dredging of the lakes in the city as well as clearing of various storm water drains. A total of 8.5 lakh cubic metre and 3.92 lakh cubic metre of silt was removed from Pratappura and Ajwa reservoirs, respectively. The VMC further said it had cleared 175 hectares of shrubs from around the river periphery.
The civic body stated that a total of 967 metric tonnes of plastic waste had been extracted from the Vishwamitri river during the ongoing desilting and re-sectioning work, which has been sent for processing and recycling to the authorised agency of the Gujarat Pollution Control Board.
Speaking to The Indian Express, Rohit Prajapati of Paryavaran Suraksha Samiti said that the installation of coir mats was one of the significant steps in the restoration of the river. It was on the petition of this organisation that the National Green Tribunal (NGT) had issued directions on implementation of the 'Vishwamitri River Action Plan', including the action points.
Prajapati, who is part of the committee appointed by the Gujarat State Human Rights Commission (SHRC) to supervise the project and submit a report every fortnight, said, 'The installation of the coir mats is a mandatory step recommended by city-based environmentalists as per the order of the NGT. It is necessary and therefore, the civic body has accepted the recommendation and tendered for the same.'
Urban planner Neha Sarwate, who is part of the Paryavaran Suraksha Samiti, explained that coir mats dissolve in the soil over a period of time after anchoring vegetation growth to prevent erosion. 'The coir matting for bank stabilisation is helpful in holding the soil in place and also anchors vegetation. For alluvial plain and clay soil as in Vadodara's Vishwamitri river bank, the coir matting will be a protective layer as steep slopes need to be stabilised. It usually stays for two years and then dissolves into the soil…,' she told The Indian Express.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
2 days ago
- Time of India
VMC to deploy 200 contract swimmers for monsoon rescue operations
Vadodara: For the first time in its history, the Vadodara Municipal Corporation (VMC) will engage 200 swimmers on contract for monsoon rescue operations, following a proposal cleared by the standing committee on Friday. The initiative comes in the wake of last year's unprecedented floods and aims to strengthen the city's emergency response system. The swimmers will be deployed for three months starting in July and will function as rescue volunteers under the fire department. According to officials, the swimmers will be hired through a contractor rather than directly by the civic body. A Mehsana-based agency has been selected for the task, and VMC will pay Rs 95.58 lakh for providing the trained personnel. "This is the first time swimmers are being brought in through such a contractual arrangement," said Sheetal Mistry, chairman of the standing committee. "The administration had earlier considered hiring them directly, but we eventually agreed to engage them through an agency." The civic body has already undertaken significant work on the Vishwamitri river, stormwater drains, ponds, reservoirs, and recharge wells, but officials said they were not willing to take any risks during the upcoming monsoon. VMC typically employs skilled workers, including some fire department drivers, through agencies on a daily-wage basis. The same system will be used to engage the swimmers.


Time of India
4 days ago
- Time of India
Scarred by deluge, Vadodara to hire 200 swimmers
1 2 3 Vadodara: After the unprecedented flood last year, the Vadodara Municipal Corporation (VMC) does not seem to want to take any chances. Despite extensive flood mitigation work being carried out, the civic body will be enlisting 200 swimmers for rescue operations in the city in case of any extreme situations. This is the first time in the city's history that the Vadodara Fire and Emergency Response will be hiring swimmers beginning July. VMC will spend nearly Rs 95.58 lakh as wages for these 'rescue volunteers' hired through a Mehsana-based private agency. The floods last Aug submerged the entire city for several days. Under widespread criticism over poor urban planning, a flood mitigation plan was taken up based on the recommendations of a govt-appointed committee. VMC has a system of getting workers through agencies on a contract basis and paying them daily wages. Some drivers in the fire department are also employed in this manner. The swimmers will be hired using the same route. "The conditions include providing trained swimmers along with fitness certificates. In case of an emergency, they will be posted in small groups at locations where flooding is imminent along with our personnel," said VMC chief fire officer Vinay Patil. Patil said that the swimmers were being enlisted as a precaution, as extra hands that can be used if the need arises. Once the swimmers arrive, the rotation of their duties and other details will be worked out. VMC chief fire officer Vinay Patil said that the swimmers were being enlisted as a precaution, as extra hands that can be used if the need arises. Once the swimmers arrive, the rotation of their duties and other details will be worked out. Patil added that the decision to pay daily wages was made to motivate swimmers and compensate them for income forgone for these three months. A proposal to engage the agency providing swimmers has been put up before the standing committee of the civic body. The civic body has completed several flood mitigation tasks, including re-sectioning of the Vishwamitri, dredging ponds, and increasing the capacity of the Ajwa and Pratappura reservoirs. The fire and emergency services department has begun testing rubber boats, including eight newly acquired ones, and other equipment.


The Print
13-06-2025
- The Print
Confusion, debris & bodies at Air India crash site. Rescue worker first thought it was cylinder blast
It took a while for him to grasp the enormity of the situation. A London-bound Air India flight had crashed right in the middle of Meghaninagar, a residential area, soon after take off in what is now said to be one of the deadliest accidents in aviation history. 'I knew then something was wrong. Initially, I thought it must have been a blast—some cylinder blast somewhere. Then I slowly gathered what happened from the news, and then I got a call at 1.30 pm. Our team reached here by 1.45 pm,' Prajapati told ThePrint. Ahmedabad: On Thursday afternoon, Dharmendra Prajapati who works with the Gujarat State Disaster Response Force in its Ahmedabad unit saw an ominous thick black smoke blanketing the sky outside his office. Of the 242 people on board the aircraft, including crew members, only a British national of Indian origin survived the accident. The Boeing 787 Dreamliner crashed right on a hostel of the BJ Medical College. 'There was a lot of confusion. There were so many bodies strewn around and parts of the plane had been crushed to the ground,' Prajapati said, adding that 62 people from his team were deployed at the crash site to go through the debris. Prajapati and his team members worked until midnight, by which, he said, most of the plane debris had been cleared. 'The JCBs are doing their work now.' By 10 am on Friday morning, the rescue operation was still underway and Prajapati and his colleagues were standing outside on standby. Hari Om Gupta, a senior official of the NDRF, told reporters that six teams from the National Disaster Response Force were on the site. 'The rescue operation is still underway. We are still clearing the debris,' he said. Another NDRF official ThePrint spoke to said the teams have thoroughly searched the site of the crash. They are now checking the buildings around the affected area, he said. Meghaninagar, the affected site, is a thick densely populated residential cluster, mostly of two- and three-storeyed houses and buildings. Nitin Joshi, a 63-year-old resident of the area, had walked up the road to the now cordoned off crash site on Friday morning. 'I regularly come here for a morning walk,' he said. Recounting Thursday's crash, Joshi said, 'We were at home and heard a massive sound, it sounded like a big blast. We then saw very dark smoke which engulfed the entire area. The sound of the blast could be heard from more than 1 km away. We first went to our building roof and then also came to the crash site.' (Edited by Tony Rai) Also Read: Junaid came home to surprise his family on Eid. Now his father waits for DNA test to identify his body