logo
#

Latest news with #MMSEZ

Multi-billion Limpopo mega-project has ground to a halt
Multi-billion Limpopo mega-project has ground to a halt

The Citizen

time9 hours ago

  • Business
  • The Citizen

Multi-billion Limpopo mega-project has ground to a halt

Makhado Special Economic Zone, announced in 2018, was intended to attract investments of R40-billion. The mega industrial project in the Musina Makhado Special Economic Zone has ground to a halt. Photos: supplied by Living Limpopo The Musina Makhado Special Economic Zone in Limpopo, announced in 2018 by President Cyril Ramaphosa, was intended to attract investments of more than R40-billion. But seven years later, the project has all but ground to a halt. Only one company has made a firm commitment to invest. Though more than R100-million has been spent, there are no roads, electricity or water connections; and the company contracted to build roads has terminated the contract. However, the chair of the board says a turnaround plan is in place and construction on the first infrastructure projects will start in September. Seven years after its launch by President Cyril Ramaphosa, the multi-billion Musina Makhado Special Economic Zone (MMSEZ) in Limpopo is at a standstill. R67.5-million has been spent on consultants and R50-million on roads and infrastructure. But there is no infrastructure, no electricity connection, no roads and no water. Described on its website as 'a flagship of the Limpopo Provincial Government' the MMSEZ is 'a green field investment platform consisting of two sites' – Artonvilla, near Musina, intended for light manufacturing, and Mopani, near Makhado, intended for heavy industry. The zone claims to offer 'state of the art logistics facilities promoting operational excellence' But though the MMSEZ was touted to bring in R40-billion in investments, so far only one company has made a firm commitment to invest. ALSO READ: Revival of job-creating initiative in Limpopo A report by the chair of the MMSEZ board, Nndweleni Mphephu, to the Limpopo Economic Development, Environment and Tourism department, shows how little has happened in what was to be a mega industrial park in the heart of the Limpopo Valley. The report, dated 28 May, follows questions in Parliament and an oversight visit to the area by members of the Limpopo Economic Development, Environment and Tourism portfolio committee. According to the Minister of Trade Industry and Competition Parks Tau, R2.27-billion would be needed for bulk infrastructure on the site, and R1.07-billion had been set aside between 2020/1 and 2026/7 in the provincial budget. In response to a question in Parliament in May from the DA's Toby Chance, Tau added that the DTIC's Industrial Zones Programme was helping the MMSEZ with advisory support. Some of the money has already been spent, much of it on consultants. In his report, Mphephu gives a list of consultants, service providers and contractors who have benefited to date. Spending of just over R85.2-million was approved for consultants, of which just over R67.5-million has already been paid to 17 consultants, including engineers, planners, quantity surveyors, project managers and horticulturists. Just under R40-million has been paid to service providers, including Eskom. ALSO READ: Limpopo's special economic zones expected to create 21,000 jobs According to the report, three contractors have so far benefited, including Tshiamiso Trading 1 and Tshiamiso Trading 2, which received a R200-million contract for roads and stormwater infrastructure and a R99.3-million contract for bulk sewer and wastewater treatment works. A contract for R134-million was awarded to Rembu Construction, also for the construction of bulk sewer and wastewater treatment works. But though some earthworks have been done by Tshiamiso on the northern site, there are no finished roads, electricity or water on either site. After being paid just over R50.4-million, Tshiamiso had to stop work on the northern site, after beginning bush-clearing, because the land belonged to a different organ of state and transfer had to take place first, the report says. Tshiamiso has now terminated the contract and is claiming more money from the MMSEZ, citing non-payment for standing time. This dispute is currently in litigation. Tshiamiso Trading is also accused of unlawfully removing white rock materials from another site to the MMSEZ site without the owner's consent or any formal agreement or compensation. ALSO READ: Limpopo unveils R1.8 billion budget boost for economic development The MMSEZ southern site was gazetted as a Special Economic Zone in 2017, but it turns out that the northern site at Artonvilla has yet to be gazetted, according to a response by Tau to a question in Parliament. Tau said the Limpopo government had indicated it would submit a request before the end of June 2025 to gazette the northern site. In his report, Mphephu noted fierce 'oppositions, dissenting views and pushbacks' mostly from environmental groups, over the southern site. Some of these were challenging the Environmental Impact Assessment in the Polokwane High Court. But in the absence of an interdict, the report says, 'all activities leading to the development, including township establishment processes are expected to proceed.' Tshiamiso Trading is one of the contractors which has been paid. When President Cyril Ramaphosa publicly announced the MMSEZ in September 2018 following his return from the Forum for Africa and China Cooperation, it came with the promise of an initial investment value of more than R40-billion. To date, little of that money appears to have materialised. ALSO READ: It's war on power, water theft to save Limpopo economic zones Responding to questions in Parliament in May, Tau gave a list of investment pledges amounting to more than R8.64-billion, of which R2.1-billion has been verified and validated from eight prospective investors. But according to the report, only the China-based Kinetic Development Group has come to the party, with a R16-billion promise of a ferrochrome smelter on the southern site, once township development on the site is approved, and subject to EIA approvals. If investors do come, one of the biggest questions will be: where is the water going to come from in this semi-arid area? The MMSEZ has approached the Water Services Authority (Vhembe) and the catchment management agency (the Department of Water and Sanitation, DWS) in the region to determine whether they have capacity, either from treated or raw water, to supply the developments. According to the report, Vhembe agreed to provide the MMSEZ with some of its allocation for raw water to kickstart development on the northern site. The DWS said treated water could be brought from Zimbabwe by pipeline for the future development of the site. 'For the south, a few boreholes were drilled in order to start the development of the site. For further development, a pipeline needs to be built to connect to the bulk pipeline from Zimbabwe. Furthermore, two dams are earmarked to be constructed in future to specifically provide water to the site as it grows,' the report says. According to the report, the MMSEZ has now implemented a 'turnaround plan' including a review of the design of roads and stormwater. A division of the Industrial Development Corporation has been appointed as implementing agent, with four professional engineers assigned to the MMEZ full-time. Construction on the first projects will start in September, the report says. This article is published in association with the Limpopo Mirror/Zoutpansberger. Correction on 2025-06-19 09:53 This article has been amended to clarify that the visit to the site was by members of the Limpopo Economic Development, Environment and Tourism portfolio committee, not by MPs. This article was republished from GroundUp. Read the original here.

South Africa: Multi-billion Limpopo mega-project has ground to a halt
South Africa: Multi-billion Limpopo mega-project has ground to a halt

Zawya

time13 hours ago

  • Business
  • Zawya

South Africa: Multi-billion Limpopo mega-project has ground to a halt

Seven years after its launch by President Cyril Ramaphosa, the multi-billion Musina Makhado Special Economic Zone (MMSEZ) in Limpopo is at a standstill. R67.5m has been spent on consultants and R50m on roads and infrastructure. But there is no infrastructure, no electricity connection, no roads and no water. Described on its website as 'a flagship of the Limpopo Provincial Government' the MMSEZ is 'a green field investment platform consisting of two sites' - Artonvilla, near Musina, intended for light manufacturing, and Mopani, near Makhado, intended for heavy industry. The zone claims to offer 'state of the art logistics facilities promoting operational excellence'. But though the MMSEZ was touted to bring in R40bn in investments, so far only one company has made a firm commitment to invest. A report by the chair of the MMSEZ board, Nndweleni Mphephu, to the Limpopo Economic Development, Environment and Tourism department, shows how little has happened in what was to be a mega industrial park in the heart of the Limpopo Valley. The report, dated 28 May, follows questions in Parliament and an oversight visit by MPs to the area. According to the Minister of Trade Industry and Competition Parks Tau, R2.27bn would be needed for bulk infrastructure on the site, and R1.07bn had been set aside between 2020/1 and 2026/7 in the provincial budget. In response to a question in Parliament in May from the DA's Toby Chance, Tau added that the DTIC's Industrial Zones Programme was helping the MMSEZ with advisory support. Some of the money has already been spent, much of it on consultants. In his report, Mphephu gives a list of consultants, service providers and contractors who have benefited to date. Spending of just over R85.2m was approved for consultants, of which just over R67.5m has already been paid to 17 consultants, including engineers, planners, quantity surveyors, project managers and horticulturists. Just under R40m has been paid to service providers, including Eskom. According to the report, three contractors have so far benefited, including Tshiamiso Trading 1 and Tshiamiso Trading 2, which received a R200m contract for roads and stormwater infrastructure and a R99.3m contract for bulk sewer and wastewater treatment works. A contract for R134m was awarded to Rembu Construction, also for the construction of bulk sewer and wastewater treatment works. But though some earthworks have been done by Tshiamiso on the northern site, there are no finished roads, electricity or water on either site. After being paid just over R50.4m, Tshiamiso had to stop work on the northern site, after beginning bush-clearing, because the land belonged to a different organ of state and transfer had to take place first, the report says. Tshiamiso has now terminated the contract and is claiming more money from the MMSEZ, citing non-payment for standing time. This dispute is currently in litigation. Tshiamiso Trading is also accused of unlawfully removing white rock materials from another site to the MMSEZ site without the owner's consent or any formal agreement or compensation. The MMSEZ southern site was gazetted as a Special Economic Zone in 2017, but it turns out that the northern site at Artonvilla has yet to be gazetted, according to a response by Tau to a question in Parliament. Tau said the Limpopo government had indicated it would submit a request before the end of June 2025 to gazette the northern site. In his report, Mphephu noted fierce 'oppositions, dissenting views and pushbacks' mostly from environmental groups, over the southern site. Some of these were challenging the Environmental Impact Assessment in the Polokwane High Court. But in the absence of an interdict, the report says, 'all activities leading to the development, including township establishment processes are expected to proceed.' When President Cyril Ramaphosa publicly announced the MMSEZ in September 2018 following his return from the Forum for Africa and China Cooperation, it came with the promise of an initial investment value of more than R40bn. To date, little of that money appears to have materialised. Responding to questions in Parliament in May, Tau gave a list of investment pledges amounting to more than R8.64bn, of which R2.1bn has been verified and validated from eight prospective investors. But according to the report, only the China-based Kinetic Development Group has come to the party, with a R16bn promise of a ferrochrome smelter on the southern site, once township development on the site is approved, and subject to EIA approvals. If investors do come, one of the biggest questions will be: where is the water going to come from in this semi-arid area? The MMSEZ has approached the Water Services Authority (Vhembe) and the catchment management agency (the Department of Water and Sanitation, DWS) in the region to determine whether they have capacity, either from treated or raw water, to supply the developments. According to the report, Vhembe agreed to provide the MMSEZ with some of its allocation for raw water to kickstart development on the northern site. The DWS said treated water could be brought from Zimbabwe by pipeline for the future development of the site. 'For the south, a few boreholes were drilled in order to start the development of the site. For further development, a pipeline needs to be built to connect to the bulk pipeline from Zimbabwe. Furthermore, two dams are earmarked to be constructed in future to specifically provide water to the site as it grows,' the report says. According to the report, the MMSEZ has now implemented a 'turnaround plan' including a review of the design of roads and stormwater. A division of the Industrial Development Corporation has been appointed as implementing agent, with four professional engineers assigned to the MMEZ full-time. Construction on the first projects will start in September, the report says. This article is published in association with the Limpopo Mirror / Zoutpansberger. Published originally on GroundUp.© 2025 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

Limpopo's multibillion-rand Musina-Makhado Special Economic Zone has ground to a halt
Limpopo's multibillion-rand Musina-Makhado Special Economic Zone has ground to a halt

Daily Maverick

time2 days ago

  • Business
  • Daily Maverick

Limpopo's multibillion-rand Musina-Makhado Special Economic Zone has ground to a halt

The Musina-Makhado Special Economic Zone, announced in 2018, was intended to attract investments of R40bn, but so far only one company has made a firm commitment to invest. Seven years after its launch by President Cyril Ramaphosa, the multibillion-rand Musina-Makhado Special Economic Zone (MMSEZ) in Limpopo is at a standstill – R67.5-million has been spent on consultants and R50-million on roads and infrastructure, but there is no infrastructure, no electricity connection, no roads and no water. Described on its website as 'a flagship of the Limpopo Provincial Government', the MMSEZ is 'a green field investment platform consisting of two sites' – Artonvilla, near Musina, intended for light manufacturing, and Mopani, near Makhado, intended for heavy industry. The zone claims to offer 'state-of-the-art logistics facilities promoting operational excellence'. But though the MMSEZ was touted to bring in R40-billion in investments, so far only one company has made a firm commitment to invest. A report by the chair of the MMSEZ board, Nndweleni Mphephu, to the Limpopo economic development, environment and tourism department shows how little has happened in what was to be a mega industrial park in the heart of the Limpopo Valley. The report, dated 28 May, follows questions in Parliament and an oversight visit to the area by the Limpopo Economic Development, Environment and Tourism portfolio committee. According to Minister of Trade Industry and Competition Parks Tau, R2.27-billion would be needed for bulk infrastructure on the site, and R1.07-billion had been set aside between 2020/21 and 2026/27 in the provincial budget. In response to a question in Parliament in May from the DA's Toby Chance, Tau added that his department's Industrial Zones Programme was helping the MMSEZ with advisory support. Some of the money has already been spent, much of it on consultants. In his report, Mphephu gives a list of consultants, service providers and contractors who have benefited to date. Spending of just more than R85.2-million was approved for consultants, of which just more than R67.5-million has already been paid to 17 consultants, including engineers, planners, quantity surveyors, project managers and horticulturists. Just under R40-million has been paid to service providers, including Eskom. According to the report, three contractors have so far benefited, including Tshiamiso Trading 1 and Tshiamiso Trading 2, which received a R200-million contract for roads and stormwater infrastructure and a R99.3-million contract for bulk sewer and wastewater treatment works. A contract for R134-million was awarded to Rembu Construction, also for the construction of bulk sewer and wastewater treatment works. But though some earthworks have been done by Tshiamiso on the northern site, there are no finished roads, electricity or water on either site. After being paid just more than R50.4-million, Tshiamiso had to stop work on the northern site, after beginning bush-clearing, because the land belonged to a different organ of state and transfer had to take place first, the report says. Tshiamiso has now terminated the contract and is claiming more money from the MMSEZ, citing non-payment for standing time. This dispute is currently in litigation. Tshiamiso Trading is also accused of unlawfully removing white rock materials from another site to the MMSEZ site without the owner's consent or any formal agreement or compensation. The MMSEZ southern site was gazetted as a Special Economic Zone in 2017, but it turns out that the northern site at Artonvilla has yet to be gazetted, according to a response by Tau to a question in Parliament. Tau said the Limpopo government had indicated it would submit a request before the end of June 2025 to gazette the northern site. In his report, Mphephu noted fierce 'oppositions, dissenting views and pushbacks', mostly from environmental groups, over the southern site. Some of these were challenging the environmental impact assessment (EIA) in the Polokwane High Court. But in the absence of an interdict, the report says, 'all activities leading to the development, including township establishment processes are expected to proceed'. When President Cyril Ramaphosa publicly announced the MMSEZ in September 2018 following his return from the Forum for Africa and China Cooperation, it came with the promise of an initial investment value of more than R40-billion. To date, little of that money appears to have materialised. Responding to questions in Parliament in May, Tau gave a list of investment pledges amounting to more than R8.64-billion, of which R2.1-billion has been verified and validated from eight prospective investors. But according to the report, only the China-based Kinetic Development Group has come to the party, with a R16-billion promise of a ferrochrome smelter on the southern site, once township development on the site is approved, and subject to EIA approvals. If investors do come, one of the biggest questions will be: where is the water going to come from in this semi-arid area? The MMSEZ has approached the Water Services Authority (Vhembe) and the catchment management agency (the Department of Water and Sanitation, DWS) in the region to determine whether they have capacity, either from treated or raw water, to supply the developments. According to the report, Vhembe agreed to provide the MMSEZ with some of its allocation for raw water to kickstart development on the northern site. The DWS said treated water could be brought from Zimbabwe by pipeline for the future development of the site. 'For the south, a few boreholes were drilled in order to start the development of the site. For further development, a pipeline needs to be built to connect to the bulk pipeline from Zimbabwe. Furthermore, two dams are earmarked to be constructed in future to specifically provide water to the site as it grows,' the report says. According to the report, the MMSEZ has now implemented a 'turnaround plan', including a review of the design of roads and stormwater. A division of the Industrial Development Corporation has been appointed as implementing agent, with four professional engineers assigned to the MMSEZ full-time. Construction on the first projects will start in September, the report says. DM

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store