
BRT Line 2C delays spark conflicting claims as contractor denies payment issues
Motorists and residents continue to face frustration as the Bus Rapid Transit (BRT) Line 2C project on Lynnwood Road lags behind schedule, with delays now stretching the project's deadline to the end of June.
This comes after multiple deadline extensions, conflicting statements from Tshwane and the contractor, and growing safety concerns on the road.
The project, which began in May 2023, was initially scheduled to be completed by November 19 that year.
The deadline has since shifted several times, from March to mid-April and now to the end of June.
Previously, Tshwane spokesperson Lindela Mashigo said one of the factors behind the delays has been the contractor's failure to pay workers on site, along with rain delays and changes in scope.
However, the contractor for the project, Buhle Shabalala, has denied any issues with wage payments, saying all workers on site have been fully compensated.
Shabalala insists the real cause of the holdups lies in waiting for design drawings from the consultants and delays in approvals from the metro.
'It's not true that there were extensions due to non-payment of the workers. All of my workers on site are paid,' Shabalala said.
'The delays were due to heavy rainfall and the time it took to get design approvals from Tshwane.
'There's a large pipeline in one section that required changes to the original design, and that's added time.'
He explained that while most sections of Line 2C will be completed by June, one section still awaits approval so that a new pipe installation can proceed.
Shabalala also dismissed claims that rubble is being left on site.
'We remove rubble at the end of each workday. The only materials we stockpile are G1 and G5 construction materials.'
Responding to growing complaints from motorists about broken barriers and safety hazards, Shabalala said the barriers were damaged during heavy rains two months ago and were replaced when broken.
'We've completed several sections and are currently working on the remaining parts,' he said.
DA councillor Dikeledi Selowa confirmed that the latest deadline has been extended to June 23, as reflected in a council report.
She said that while the project is back on track, ongoing oversight is crucial.
'The issue is poor project management within the metro.
'These ongoing extensions beyond the initial contract period can potentially lead to extra, unforeseen expenses,' Selowa said.
Selowa acknowledged that the contractor has since caught up with wage payments and that progress on the ground is visible.
'We are monitoring the project closely. Once it's completed, we will call for a physical audit verification to ensure that every cent spent from the metro's grant funding delivered value for money.'
Selowa also pointed to issues of rubble not being cleared adequately, placing that responsibility on the contractor.
The contractor, however, strongly denies neglecting site cleanliness.
Mashigo confirmed that the project was 84% complete and gave non-payment of workers, slow progress, rain delays, and changes in project scope as reasons for the delay.
The city did not provide an updated comment by the time of publication.
Do you have more information about the story?
Please send us an email to bennittb@rekord.co.za or phone us on 083 625 4114.
For free breaking and community news, visit Rekord's websites: Rekord East
For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram
At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!
Stay in the know. Download the Caxton Local News Network App
Stay in the know. Download the Caxton Local News Network App here

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Citizen
17 hours ago
- The Citizen
Crèches are now ready to fight fires
Crèches are now ready to fight fires Tshwane has delivered fire safety equipment, including serviced and upgraded extinguishers, hose reels and hydrants, to nine early childhood development centres in regions 3 and 6. This comes after a routine inspection by the DA caucus's Section 79 Community and Social Development oversight committee, chaired by Phuti Kwenaite. 'Recently, we pointed out there are maintenance elements that have been neglected in Tshwane's ECDs.' She said the fire extinguisher problem was supposed to be addressed two years ago. Kwenaite highlighted the significant risk posed when fire extinguishers are neither present nor functional. 'It is a big risk for the extinguishers not to be there and functioning. 'This is why the fire department took some time for some of these ECDs to open.' MMC for Corporate and Shared Services Kholofelo Morodi confirmed that Tshwane has completed the servicing and upgrading of fire-fighting equipment, with a sharp focus on ECD centres. She said the initiative, executed by Group Property Management, ensures full compliance with national safety standards, specifically SANS 10400 Part T (fire safety) and SANS 1475 (fire extinguishers). Marodi added that these mandate the installation, maintenance and servicing of portable fire suppression equipment. 'It includes the maintenance of fire extinguishers, hose reels, and hydrants and forms part of the city's annual fire safety programme.' She said these maintenance efforts signal a broader shift in Tshwane's multiparty coalition prioritising the safety of employees, children and communities. Marodi added that maintaining a safe workplace supports an efficient municipality and reflects Tshwane's commitment to this principle. 'Reinforcing Occupational Health and Safety (OHS) standards remains pivotal to protecting employees and service users. 'This intervention forms part of an ongoing effort to strengthen internal systems, promote compliance, and safeguard infrastructure, all aimed at delivering reliable and dignified services to residents.' ALSO READ: Mamelodi youth punches back at crime through boxing Do you have more information about the story? Please send us an email to bennittb@ or phone us on 083 625 4114. For free breaking and community news, visit Rekord's websites: Rekord East For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading! Stay in the know. Download the Caxton Local News Network App Stay in the know. Download the Caxton Local News Network App here


Eyewitness News
4 days ago
- Eyewitness News
Sewage, garbage, dirty water: Theewaterskloof is in a mess after years of bad management
CAPE TOWN - In the list of comments on the Theewaterskloof Municipality draft budget, nine residents of Riviersonderend complained about the water being dirty, smelly and undrinkable. An 8% increase in the water tariff has since been passed, yet food and hospitality businesses have had to invest heavily in filtration systems or find alternative sources of water. DA Councillor Piet Stander said the town used to have the best quality water in the Overberg, as it was gravity-fed from the perennial Olifants River in the adjacent mountains, to the reservoir. But Stander said lack of maintenance meant pipe breakages and leaks had not been fixed, so for the past four years, water had been pumped from the Sonderend River, which was polluted by upstream effluent and agricultural runoff, including pesticides. He said the cost of chemicals now needed to treat the water has exceeded what it would have cost to fix the pipes. Riviersonderend is not the only town in the municipality in which the drinking water quality does not meet the minimum national standards. Besides Riviersonderend, the municipality includes Caledon, Greyton, Genadendal, Tesselaarsdal, Botrivier, Villiersdorp, and Grabouw. Only Tesselaarsdal and Botriver have acceptable quality drinking water, according to the Department of Water and Sanitation's Integrated Regulatory Information System (IRIS). The rest are all failing the microbiological standards, having more faecal bacteria in the water than is allowed. IRIS also shows that sewage treatment works in all eight towns are failing, and have been for years in most, releasing sewage that has not been properly treated into the streams and rivers in the area. The Caledon sewage treatment works has just had a R56-million upgrade, paid for in this financial year. But there have been 32 high-level failures this year, with effluent spewed out with E. coli counts of more than double what is allowed, along with high levels of ammonia and other pollution indicators. A visit to the plant found that although new infrastructure and equipment was installed, only half of it appeared to be working. Of four aerators, only two were working, and of two clarifiers, only one was operational. The landfill at Caledon was supposed to have been closed and rehabilitated years only is it still in use, but the refuse dumped there is uncovered, with wind blowing plastic into the surrounding landscape. The management of solid waste in Theewaterskloof is also problematic. The Caledon landfill, carved into the northern side of the Klein Swartberg mountain, is uncovered, and plastic waste is being blown across the landscape. It is also full. The municipality's Spatial Development Framework of 2023 states it should have been closed when a transfer station was completed in the 2020/21 financial year, and the landfill rehabilitated. The transfer station, from which waste is supposed to be taken to Karwyderskraal regional landfill site outside Hermanus, has been completed but is unused, with the paved road in the premises already needing repairs. In Villiersdorp, a transfer station to take waste to Karwyderskraal was built, but has been stripped for use as building material in informal settlements. The Spatial Development Framework states the landfill has been closed and is to be rehabilitated, but as the transfer station is dysfunctional, the landfill, while officially closed, is still used. Residents still use it to dump rubble and garden refuse provided the road there has been graded and is passable. When it is not, they dump their rubbish in the bushes alongside the road. A resident, who asked not to be named, said household refuse is collected and taken to the Caledon landfill. The crumbling pillars of municipal service are reflected in the lack of stability in municipal management. There have been four municipal managers in as many years since the municipal elections and the ousting of Danie Lubbe by the new coalition of the ANC, Patriotic Alliance (PA), EFF, and GOOD. Lubbe was subsequently employed by Langeberg Municipality. The contrast between the two municipalities is stark. The Auditor-General doubts Theewaterskloof can be considered a going concern and racked up more than R300-million in irregular and unauthorised expenditure in 2023/24. But Langeberg received an unqualified audit and no irregular or unauthorised expenditure, and just R5,000 in fruitless and wasteful expenditure. The ANC-led coalition, which was heavily reliant on GOOD joining in with its three seats in the 27-seat council, replaced Lubbe with Boy Manqoba Ngubo in June 2022. Manqoba Ngubo's position was finalised with a five-year contract in October that year, but he unexpectedly resigned five months later. The ANC-led coalition then controversially appointed Wilfred Solomons-Johannnes ahead of a better-qualified candidate. Western Cape MEC for local government, Anton Bredell, challenged the appointment, and the high court duly ruled it was illegal. Solomons-Johannes stood down as municipal manager in June 2024. He remains in the municipality as director of community services, but in April was placed on suspension while R41-million in missing disaster relief funds for floods in September 2023 is investigated. Reynold Stevens was then appointed in an acting position from July 2024 until replaced by Walter Hendricks in mid-February. Hendricks was officially appointed from his acting position on 30 May. New municipal manager Walter Hendricks is the fourth municipal manager since Daniel Lubbe was ousted after the 2021 local government elections. Hendricks hopes to get the municipality back on an even financial keel so that municipal services can be improved. Hendricks is frank about the challenges the municipality faces. 'We're in a mess, we don't have money,' Hendricks told GroundUp. 'The first thing we need to do is remain within the boundaries of the law.' Besides the coffers being left empty, he said there were internal challenges with certain people appointed who 'don't add the kind of value you need'. He said his aim was to focus on the municipality's core functions of water, electricity, roads and stormwater, refuse and waste water. 'Luckily, I have a mayor who has bought into that.' He said he was working closely with provincial and National Treasury officials and master plans were in place. Once Theewaterskloof was financially stable again, they could start looking at reinstituting facilities such as swimming pools in the towns, upgrading sports fields and improving libraries. 'We have to eat the elephant bit by bit.'


The Citizen
4 days ago
- The Citizen
Volunteers clean up tons of waste from polluted river
In a show of community spirit and environmental dedication, around 100 volunteers gathered on June 15 to clean up a heavily polluted stretch of the Hennops River. Recent flooding brought debris, plastic, and waste into the waterway. The clean-up was spearheaded by the World Mission Society Church of God as part of its ongoing global initiative, the 'Erasing Plastic Footprints' campaign. Recent flooding in Gauteng had caused the Hennops River to overflow, inundating the riverbanks with waste swept in from nearby residential areas and commercial zones. Plastic bottles, timber, clothing, and debris were found strewn across a 1.5km section of the river in Centurion. Donning bright yellow vests, volunteers comprising members of the church, their families, and residents from Centurion, Soshanguve, and Hammanskraal set out early in the morning on the public holiday. In just two hours, they managed to collect a staggering amount of trash equivalent to one 6-ton truckload, painstakingly separating recyclable materials and retrieving deeply buried plastics from the soil. The metro supported the effort by supplying bin bags, cleaning tools, and bottled water. Local political figures praised the initiative, including Leanne de Jager, a DA member of the Provincial Legislature. 'We are very grateful to them for their continued efforts and for trying to remove plastics from nature and communities by 2040. We are also grateful to all the volunteers who give up their time for this mission and always, never without fail, arrive in their numbers.' DA councillor Gert Visser echoed the concerns about the root causes of pollution in the area, specifying industries' and businesses' dumping, and waste from the informal settlements not being collected by the municipalities. 'All of this ends up in the river. One of the consequences is that the river has developed a stench, and it affects the health of many people in the area. It's not a simple, quick fix. So we are here to create awareness and also to ask residents to not use plastic but recyclable materials.' As part of a month-long global campaign to commemorate World Environment Day (June 5), this clean-up in Gauteng stands as a powerful example of what co-ordinated, grassroots action can achieve. Among the volunteers was Baby Makgoba, who diligently sorted plastic waste. 'We truly hope that we will contribute to making a better future for all,' said Makgoba. Do you have more information about the story? Please send us an email to bennittb@ or phone us on 083 625 4114. For free breaking and community news, visit Rekord's websites: Rekord East For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading! Stay in the know. Download the Caxton Local News Network App Stay in the know. Download the Caxton Local News Network App here