‘Constrained' water supply jeopardises new Dublin suburb with 6,000 homes

‘Constrained' water supply jeopardises new Dublin suburb with 6,000 homes

Irish Times12-05-2025

Uisce Éireann
has warned
Dublin City Council
over worsening water and sewage capacity that could jeopardise the local authority's plans for a new suburb of 6,000 homes on one of the capital's largest industrial estates.
Water capacity for Dublin has deteriorated to 'amber status' level, Uisce Éireann told the council, meaning supplies are now 'constrained'.
The utility company also said future population growth in Dublin is 'dependent' on the construction of a new municipal sewage plant.
Uisce Éireann wrote to the council in response to the draft Ballyboggan Masterplan, which will govern the redevelopment of the 77 hectare Dublin Industrial Estate opposite
Glasnevin Cemetery
.
READ MORE
The plan, the largest regeneration of industrial lands since the Dublin Docklands, is, the council said, crucial to meeting 'national targets for housing delivery on brownfield lands within urban areas'.
Uisce Éireann said housing growth for Dublin is dependent on the delivery of two large-scale water and wastewater projects, which have been long delayed and are not now expected to be in place within the development plan timeframe for the Dublin Industrial Estate.
The statement is at variance with the utility's position two years ago when the council began planning for the rezoning of the vast landbank, which is close to the suburbs of Cabra, Ashtown and Finglas.
In May 2023, Uisce Éireann said the industrial estate was in an 'established water network and is located adjacent to large trunk mains. In general, the area may require local upgrades', which would be examined when connections were requested.
In relation to wastewater, in the same letter Uisce Éireann said there was an 'established sewer network in this area' with possible upgrades to pumping stations required.
However, in recent days Uisce Éireann told the council that since it made its 2023 submission, Dublin's water supplies have 'turned to amber status' and were now constrained.
'This status will most likely remain in place until the [Shannon to Dublin] Water Supply Project is in place.' This project is not expected to be completed until after 2032.
I think we need to look at things like statutory timelines for connections to water, to electricity, because there's far too many delays

Tánaiste Simon Harris
Similarly, it said growth in the capital's population was 'dependent on the completion of the Greater Dublin Drainage Project' to process the sewage of north Dublin. This project has so far been in the planning system for seven years.
The submission to the council, is the latest in a series of warnings from Uisce Éireann on its ability to supply new homes.
Uisce Éireann chairman Jerry Grant recently told a
Royal Institute of Architects of Ireland
conference that the State's water and sewerage systems 'are in a desperate state' because of 'extraordinary complacency' and 'passive indifference'.
He warned that a new approach from the Government was needed if targets of 50,000 homes annually are to be met.
[
What is the water quality like at your local beach? Use our table to check
Opens in new window
]
[
Uisce Éireann's €1bn budget funding 'not additional' and 'contradicts' impression given to public
Opens in new window
]
Mr Grant also outlined funding concerns in a letter to previous minister for housing Darragh O'Brien.
Meanwhile, Tánaiste Simon Harris has indicated Uisce Éireann could face new legally binding deadlines for connecting new housing projects to the water system.
In an interview with The Irish Times Inside Politics podcast, the Fine Gael leader said he did not want to be 'provocative' in dealing with the utility or the ESB, 'but we need to know that in return for providing Irish Water X billion more, that would result in Y more homes. Similar for the ESB in connections'.
'I think we need to look at things like statutory timelines for connections to water, to electricity, because there's far too many delays in relation to that.'
Having such obligations for connections would, he said, 'make a very significant difference in terms of building up the delivery of homes'.
The council will review submissions on the masterplan before city councillors are later this year asked for approval to allow the land to be rezoned from industrial to residential use.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Rathmines locals protest over An Post move to sell ‘cultural icon' later this year
Rathmines locals protest over An Post move to sell ‘cultural icon' later this year

Irish Times

time3 hours ago

  • Irish Times

Rathmines locals protest over An Post move to sell ‘cultural icon' later this year

Protesters gathered outside Rathmines post office on Saturday morning in a demonstration against its relocation and planned sale of the building. The protest came after An Post this week confirmed its plans to move the Rathmines branch by September, paving the way for the sale of one of the most prominent buildings in the south Dublin suburb. Labour leader and local TD Ivana Bacik organised Saturday's demonstration, alongside local councillors Fiona Connelly and Dermot Lacey. Speaking at the protest, she said the building should be kept 'in community usage', adding that 'our priority is to keep the postal service in the retail hall'. Labour leader Ivana Bacik at the protest in Rathmines on Saturday. Photograph: Ella Sloane The imposing 1934 art deco building will be sold with two other Dublin post offices – Phibsborough and Tallaght – as well as a further three across the State, as part of the 'transformation of the national post office network,' An Post said previously. READ MORE At present, 95 per cent of the country's post offices are already contracted out to independent business owners, who often run post office services as part of a local shop. It is understood the Rathmines post office will move to a Centra store in the locality. Ms Bacik described the demonstration as 'a last-ditch appeal' to Minister for Communications Patrick O'Donovan and Minister for Expenditure Jack Chambers to not sign off on the property's divestment. 'The post office is a very well loved, much-used building. This is very much from the heart.' Ms Connelly stressed the importance of public buildings such as the post office 'as a community asset and a community resource'. Cllr Fiona Connelly at the protest. Photograph: Ella Sloane 'It's really sad to see a resource like the post office, that's in such demand and so heavily used, closing.' Enid O'Dowd, a local and regular user of the postal service, said the decision to sell the building was 'just ridiculous', expressing concern at the pressure the branch's relocation would place on the post office in Ranelagh. Speaking of the branch's speculated move to a nearby Centra, she said the shop 'is going to be a very crushed place with queues spilling out on to the pavement'. 'What's going to happen is people are going to start using the one in Ranelagh but that isn't big enough for the demand. They've only two cashiers there.' Enid O'Dowd at the protest. Photograph: Ella Sloane Cliona Buckley, who grew up on Leinster Road said: 'The last thing they [An Post] should be doing is shutting down memorable, protected, built for purpose buildings. What they should be doing is spending money cleaning up the front of it or they could have lovely potted plants or flower baskets and make it a feature.' She said the post office's planned closure and sale showed a failure by An Post 'to serve the Irish citizens'. Andrew Folan, Mary Freehill and Cliona Buckley at the protest. Photograph: Ella Sloane Another local demonstrator, Andrew Folan, said he felt 'absolutely outraged' by An Post's decision, adding that it was indicative of 'the digitalisation of our culture'. 'The analogue thing of writing letters, posting letters, distributing parcels and meeting the community while you do it is an essential part of our life. I think that the gradual shutting down of post offices is a very negative thing.' Mr Folan pointed to the need for 'a spacious building' due to demand for the service. 'This is a fantastic cultural icon, beautiful design and art deco, well built and a landmark for Rathmines. I think we should celebrate what we've got and show a bit more regard for our culture and our heritage,' he said. Former Labour councillor Mary Freehill, from Rathmines, said the recent loss of the suburb's citizen's information centre in 2022 had already taken a toll on the community. 'There isn't a place for people to come together.' 'Rathmines has very few publicly owned buildings,' said Ms Freehill, adding 'this is the only thing built by the Irish State in Rathmines. All of our other public buildings were built by the British.'

Ireland needs to ditch empty promises and economic fairy tales and start confronting reality
Ireland needs to ditch empty promises and economic fairy tales and start confronting reality

Irish Times

time14 hours ago

  • Irish Times

Ireland needs to ditch empty promises and economic fairy tales and start confronting reality

The next six weeks or so are going to go a long way to defining the Government's term in office. The printers are going to be busy. We are due an updated housing plan, a new strategy on competitiveness and productivity, the Summer Economic Statement and a new medium-term budget strategy along with a revised National Development Plan outlining state investment plans. Then, in the middle of all this, there is the deadline for the US/EU tariff talks on July 9th. The Government needs to use this crucial period to set some kind of coherent economic narrative for its term. So far it has been firing blanks. For example, bits of its housing plan are drip-feeding out in an often-disorganised fashion. Perhaps this is meant to give the impression of busyness, but all it does is confuse people. READ MORE At the heart of all this is credibility. A believable strategy must have some hope of delivery. And here the State – in the widest sense of the Government and the public service – is struggling. It is not just that things are happening late – like the National Children's Hospital. Or that there are signs of waste and carelessness with public money – step forward the Leinster House bike shed. It is that a lot of vital stuff is simply not happening at all. It is a stretch to believe that the Metro will ever get built. Or the giant project to bring water from Shannon across the State. Or the offshore wind infrastructure that is meant to be at the heart of our energy transition , where the Draghi report on EU competitiveness showed Ireland has one of the most long-drawn out consent mechanisms in Europe. In this context, government targets take on an air of fantasy. Less than six months into the Coalition's term, Minister for Housing James Browne told us this week that the target of building 41,000 homes this year is not going to happen. So why should we believe the target for 2026 or the 300,000 plus homes promised during the Coalition's term? The Departments of Finance and of Public Expenditure will publish a budget strategy over the summer, based, we must assume, on tighter control of day-to-day spending. But key spending targets have ended up being roundly ignored in recent years. Central Bank researchers estimated this week that permanent Government spending has risen by 37 per cent since 2021. Had the annual spending limits of 5 per cent set by the previous administration been adhered to, the increase would have been 16 per cent. That is a €16 billion difference. Official documents and targets seem to exist in some kind of parallel universe where no one really expects them to happen. They are more fairy stories than strategy. And the risk with the plans coming in the weeks ahead is that these are more endless checklists of stuff that is happening already and stuff that might or might not happen at all. Some central themes and directions are urgently needed. And some convincing messages of actual action to get things done. Investment is built on certainty, yet in key areas such as climate change and housing this is simply missing. The current drift has a cost. The stalling of investment across the economy is in part due to threats of tariffs from Donald Trump . There isn't much the Government can do about that. But it can start to get its own story straight. Lack of clarity about housing policy is causing parts of the construction industry to sit on its hands. With talk of more incentives and tax breaks on the way, and uncertainty on state commitment in areas of social housing, builders wait to see what emerges. House building volumes slipped by 4.3 per cent in the first quarter of this year, compared to the previous three months. Meanwhile, big foreign investors – and their international headquarters – are starting to realise that promises to deliver better energy and water infrastructure are simply not being met. Investment plans, on hold to see how the US/EU talks work out, will restart at some stage. Ireland is at risk of not being in the frame. The first real alarm bell for this was when Intel ditched Oranmore in Co Galway as a possible site for a big new plant in 2021 because the State could not guarantee how long planning would take on vital supporting infrastructure. This followed the seemingly endless planning saga for the Apple data centre in Athenry , also Co Galway. A convincing economic narrative needs a few central points that everyone has signed up to. Read the Central Bank research out this week for a convincing case on how state investment remains low here, despite tripling over the past decade. This is because the economy and population have grown so fast and the economy was already hobbled by years of underinvestment after the financial crash. To allow space for investment to continue to grow – and provide a buffer if the public finances tighten – other parts of the budget need to be under control. This means keeping the budget in surplus and continuing to put away excess corporate taxes in the funds for the future. This needs to be a central part of a coherent strategy. To be credible, the whole Government – including Micheál Martin and Simon Harris – need to explicitly sign up to this. If it is just a creature of the budget departments, then it will be there to be negotiated away during the budget process. It goes without saying that the second leg of any strategy needs to focus on prioritisation and delivery. Many thousands of words have been written about this. And the challenges are significant. But Ireland, for now anyway, is in a uniquely privileged position with a flush Exchequer and room for manoeuvre. The resources are there. Spending them well is the challenge. Ireland can consider how to respond as the Trump story plays out. The odds are that it will continue to do so long after the July 9th talks deadline. But the Government needs a convincing narrative of how it is going to manage what is under its control and use what may prove to be transitory budgetary riches. There are dangers ahead. But we are starting from a good position, with full employment and flush coffers that are the envy of many other countries. The Government needs to start telling a better story – not just to the public and investors, but also to itself.

Fingal council not only party to blame for farce of Dublin Airport passenger cap
Fingal council not only party to blame for farce of Dublin Airport passenger cap

Irish Times

time15 hours ago

  • Irish Times

Fingal council not only party to blame for farce of Dublin Airport passenger cap

Under a planning restriction imposed by Fingal County Council dating from 2007, Dublin Airport's passenger numbers are supposed to be capped at 32 million a year. But, as we all know, this restriction is pure fiction. More than 33 million passengers went through the doors of the airport last year and 36 million-plus are expected to use it this year as a result of court rulings that have put a stay on the cap while we await a ruling from Europe . It's an Irish solution to an Irish problem. To add to the confusion and mess, the council this week issued an enforcement notice to DAA on foot of complaints by local residents. Nobody comes out of this shambles well. Government should have moved long ago to sort out the cap and remove planning regulation of Dublin Airport from the remit of the council. Minister for Transport Darragh O'Brien promised a solution on taking office in January, but none has emerged to date. READ MORE DAA described Fingal's enforcement notice as a 'sorry indictment of the mess that is the Irish planning system, particularly when it comes to the most vital piece of transport infrastructure on this island'. That might be so, but it is also an indictment of DAA's dithering over 16 years before submitting an infrastructure application in December 2023 that would allow it to increase traffic through Dublin Airport. And it is not a good look for a state-owned company to breach legally binding planning rules. [ `Zombie' Dublin Airport passenger cap could be removed by legislation Opens in new window ] Willie Walsh, the former Aer Lingus and IAG chief who is now head of Geneva-based airlines trade body IATA, has said we are a laughing stock internationally, with people scratching their heads as to why a small island nation on the edge of western Europe that relies heavily on foreign direct investment would be tying itself up in knots with a cap on growth at its biggest international airport. He's not wrong.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store