Plans for Perthshire solar farm the size of 140 football pitches refused
Perth and Kinross Council felt the "excessive" scale had not been fully justified for such a "significant" loss of prime agricultural land
A planning application for a massive 49.9 MW Perthshire solar farm - the size of around 140 football pitches - has been unanimously refused by Perth and Kinross councillors.
Perth and Kinross Council's (PKC) Planning and Placemaking Committee met to consider the application - submitted by Solar 2 Ltd - on Wednesday, June 11.
Elected members upheld the reasons recommended for refusal by council planners that it would result in a "significant" loss of prime agricultural land and its "excessive" scale had not been fully justified.
Atmos Consulting submitted plans to PKC, on behalf of Solar 2, to develop Collace Solar Farm on around 100 hectares of land 500m north west of East Saucher House, Kinrossie.
Presenting officers' report of handling on the application to councillors, PKC's Major Applications and Enforcement team leader Sean Panton said: "Unfortunately we are recommending refusal of the application before you.
"Whilst National Planning Framework 4 and the Perth and Kinross Local Development Plan 2 offers support for renewable energy proposals, on this occasion the loss of prime agricultural land at this scale is not considered to have been suitably justified."
He added: "The site is located approximately one kilometre north of the Sidlaw Hills Special Landscape Area and is also in close proximity to a number of historical assets including a number of listed buildings and the Kinrossie Conservation Area.
"There are 82,000 solar panels proposed."
Mr Panton said Solar 2 was questioned as to why "so many solar panels were required when this amount of panels would exceed a 49.9MW output".
He told councillors: "The response was that it was commonplace to overplant solar farms. Consequently, we're of the view that 82,000 panels is an overprovision and this number of panels could be reduced obtaining the same output but with less prime agricultural land intake."
The solar panels would reach a maximum height of just over three metres above ground level, as they tilt. They would be supported by an aluminium frame mounted vertically into the ground to a depth of around two metres with the edge of the solar arrays varying in height above the ground but with a minimum clearance of about one metre. The panels would rotate vertically towards the sun from about 60 degrees below the horizontal when the sun is at its lowest to horizontal when the sun is at its highest.
As well as the solar panels, the proposal included plans for inverters, a substation, a substation compound, two containers, fencing, CCTV and access tracks.
There were 89 letters of objection and four letters of support for the proposal.
Objector Ian Thoms was born and raised in the area and has spent the past 11 years back there with his wife.
He said the proposal was "poorly sited" and there were "better alternatives near where the energy is actually required".
Mr Thoms cited a change.org petition - with over 300 signatures - launched by Collace Solar Objection Group. The group is calling for Perth and Kinross Council to "protect rural Perthshire" and "pause all solar development approvals until a robust, location-sensitive, and proportionate planning framework is in place—one that prioritises rooftop and brownfield solar, protects agricultural land, and mandates solar recycling measures".
He told councillors: "Walking along the core paths near our home, I often meet neighbours and strangers out enjoying the landscape. People come here for the peace, the view of the hills and the living countryside.
"This would all be fundamentally altered by an industrial-scale solar installation with at least 40 years of high fencing, CCTV and metal infrastructure blighting the countryside.
"The development would directly dominate the outlook from our homes, core paths and adjacent roads turning a living, working landscape into an industrial one."
He added: "This project is one of 11 similar proposals in the Strathmore area alone. We need a more coherent, balanced approach."
Fellow objector Jonathan Simpson said: "Scotland has over 9000 hectares of vacant and derelict land, yet this developer proposes to industrialise actively farmed prime land.
"Before turning to ground-mounted panels, we should prioritise solar on rooftops, brownfield sites and existing industrial infrastructure followed by poor quality soils."
Solar 2 project manager John Moisey argued it was a "temporary condition" and the land could continue to be used for "grazing beneath the panels".
The report of handling stated it was anticipated the solar farm would operate for up to 40 years then all infrastructure would be removed and the site reinstated to its former condition.
Mr Moisey said the 40-year set-aside could potentially "enhance" the soil by allowing it to "rest and regenerate" through a reduction in ploughing and ground disturbance.
He told councillors the energy generated would meet the energy demand of "over 11,000 homes" and be fed directly back into the local grid via a distribution connection at Coupar Angus.
Independent councillor Dave Cuthbert moved for refusal. It was seconded by Conservative councillor Keith Allan.
The proposal was unanimously refused.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Daily Record
a day ago
- Daily Record
Perth and Kinross Council decides not to object to 100MW energy plant
The application will be determined by the Scottish Government's Energy Consents Unit due to its size Perth and Kinross Council (PKC) has not objected to a proposed 100MW energy plant near Coupar Angus. The proposed electricity generation station at Kettins would be situated on 4.2 hectares of farmland currently used for crops. PKC's Planning and Placemaking Committee was asked on Wednesday June 11 to consider the application, submitted to the Scottish Government due to its size. In December 2024 Cogeo Planning and Environmental Services Ltd submitted a planning application to the Scottish Government, on behalf of Merseyside-based Balance Power Projects Ltd to build and operate the proposed electricity generating station. The application site, referred to as Hallyburton BESS, sits within the Hallyburton Estate, Kettins. Planning applications for battery energy storage systems which are 50MW or higher require approval from Scottish Ministers. The Scottish Government's Energy Consents Unit consulted PKC on the proposed development on land 260m south east of Colbeggie Farm Cottage, Kettins. The footprint of the built area would be 1.3 hectares - just smaller than the combined size of two football pitches. The built site would include: 28 battery blocks - with each block containing four battery containers; 28 inverter and transformer units; two auxiliary transformers; two control room and welfare units; two private substations; two storage rooms and two district network operator (DNO) rooms. The development would also include access, lighting, security fencing, drainage and acoustic fencing. The site is currently being used for crops and sits within an agricultural rural landscape of Coupar Angus bounded by hedgerows and post and wire fencing. Last week, PKC's Planning and Placemaking Committee was asked to consider whether or not to object to the application. If PKC had objected, it would have triggered the requirement for a public inquiry to be held to consider the application. The committee's convener SNP councillor Ian Massie put forward a motion not to object to the application. It was seconded by Conservative councillor David Illingworth. Conservative councillor Ian James raised concern "it was too large" and "on a prime agricultural site". Cllr Bob Brawn agreed but the pair were unable to table an amendment -to oppose the application - which was deemed legally competent. National planning policy does allow for energy developments to be built on prime agricultural land. The report of handling - put before councillors - said: "...the global/local need for energy is outweighed by the small loss of land proposed for this development. Furthermore, the site has been designed so the land is minimally disturbed." And councillors were told there was nothing to show the plant was taking more land than required for 100MW. The committee agreed to uphold planners' recommendation not to object to the application.

The National
a day ago
- The National
Community pub developed from old school in Perth and Kinross opens
The CornerStone Rannoch will officially open on Sunday, June 22. Formerly known as The Hub, the community-owned bar and restaurant will welcome the Kinloch Rannoch community in for a sneak peak on Saturday afternoon before officially opening to the wider public from 10am on Sunday. Back in September 2022, Rannoch Community Trust was granted planning permission to develop an £830,000 community hub in a former outdoors centre and school. READ MORE: SNP MSP Fergus Ewing to stand as independent at next Scottish Parliament election The consent was branded a 'major milestone' as the trust then sought to secure the remainder of the funding needed to complete the project at the Victorian building on Allt Mor Place. Originally built as the village school in 1840, it closed when a new school was opened in Kinloch Rannoch in 1965. In the 1980s it was transformed into a residential outdoors centre until Perth and Kinross Council deemed it 'surplus to requirement' and closed it in 2019. In July 2020, Perth and Kinross councillors voted to sell the former outdoors centre for £75,000 to Rannoch Community Trust to transform it into a multi-purpose facility for the community. A year later – in July 2021 – ownership of the building and grounds was legally transferred from Perth and Kinross Council (PKC) to Rannoch Community Trust. (Image: The CornerStone) Planning permission for the trust to develop it into a community-owned bar/restaurant was granted in September 2022, under delegated powers. The CornerStone features a social enterprise café/bar, manager's accommodation, office space, a meeting room, an outdoor seating area, new footbridge and a playpark. It will be run by a mixture of both paid and volunteer staff. The building was designed by Perth-based Studio East Architects to be 'as energy efficient as possible'. A spokesperson for The CornerStone said: 'Initially, we will be serving drinks only, until we hook a great chef onboard, so until then you can enjoy local beers on tap and so much more, we can't wait to host you in the heart of our village.' (Image: The CornerStone) There is also a meeting room with WiFi. The spokesperson added: 'Our flexible workspaces catering to groups or individuals is also now available to book: Work — The Cornerstone 'Our new website offers lots of information you might be interested in, so please feel free to take a look around there, or pop in to say hello, we'll be proud to give you a warm welcome.' Highland Perthshire ward councillor John Duff is delighted and said it looks 'fabulous'. The Conservative councillor said: 'I am delighted that the aspirations of the community have been achieved and that it will soon have this excellent venue for locals and visitors to come together, relax and socialise. 'The conversion of the former outdoor centre looks fabulous and I applaud the continued efforts of the community to deliver this exceptional facility providing food, drink, meeting and work space. I look forward to visiting the CornerStone myself in the near future.' Rannoch Community Trust was awarded £134,660 from the Scottish Government's Scottish Land Fund Award to cover the purchase of the building, legal expenses and essential repairs. It also received £250,000 from the UK Government's Community Ownership Fund and £308,000 from the Scottish Government's Place Based Investment Programme, which is aimed at supporting community-led regeneration.


Edinburgh Live
2 days ago
- Edinburgh Live
Edinburgh car park to be replaced by four-storey block of flats despite objections
Our community members are treated to special offers, promotions and adverts from us and our partners. You can check out at any time. More info Plans to build a new block of flats on an existing Edinburgh car park are set to be granted, despite objections. In September 2023, proposals were submitted to the council for the erection of a four-storey block between 36 and 37 Clovenstone Drive. A resident's car park is currently occupying the site. The application has been referred to the council's development management sub committee as more than 20 objections were received from locals, but the recommendation from officers is to grant permission. They say the development would make good use of the brownfield site and both the design and scale of the proposed building is appropriate, providing "appropriate levels of amenity." The existing site comprises 20 vehicle parking bays between number 36 and 37. Both buildings are end-of-terrace four-storey blocks with small garden plots to the front and rear. The proposed development would deliver eight two-bedroom flats accessed via a communal stair. Public open space in the form of communal gardens are proposed to the rear while private gardens for two ground floor flats would be provided at the front. Justifying their decision to recommend permission be granted, planning officers wrote: "The proposal complies with National Planning Framework 4 and the Local development Plan. The principle of residential development is acceptable on this site and the re-use of a brownfield site is supported by the development plan. Join Edinburgh Live's Whatsapp Community here and get the latest news sent straight to your messages "The design and scale are appropriate, and the development would provide appropriate levels of amenity. The landscape proposals will contribute positively to a sense of place and deliver biodiversity enhancement. "Parking levels are in line with the Council's guidance. The proposal is acceptable and there are no material considerations which outweigh the conclusion." The application is to be discussed among councillors next Wednesday, June 25.