Centre overhauls highways construction bid process, timelines set for pre-bid clearances
NEW DELHI
:
In a move to speed up highway construction, the Centre has synchronized project approvals, awards and appointment of developers with milestones for land acquisition, environment, forest and wildlife clearances.
These milestones will be applicable for highway building and awarding agencies including the National Highways Authority of India (NHAI), NHIDCL (National, Highways and Infrastructure Development Corporation Ltd) and the ministry of road transport and highways (MoRTH's) own road construction wing.
They reflect specific timelines for taking various statutory clearances before awarding any highway project.
Beyond land norms
Notably, the timeline goes well beyond the need to acquire 90% of land before inviting bids -- a practice that has been followed for highway awards for the past few years.
Also read: Independence Day: Toll relief, annual pass for pvt vehicles on highways from 15 Aug
Now, the ministry has mandated that work on securing forest, environment and wildlife clearances should begin on approval of a highway alignment and the process has to be completed before bids are received.
This assumes importance given that the Centre plans to award around 9,000 km of highways in FY26, with the pre-bid exercise seen as important to prevent contractual disputes, and time and cost overruns.
According to a MoRTH circular issued to all highway development and awarding agencies, specific timelines would have to be followed even for securing clearance from Indian Railways and Inland Waterways Authority of India and also for finalising certain estimates before bids are invited.
'Delays and disputes often stem from awarding projects before land acquisition and clearances are substantially completed. When contractors face site access issues, legal hold-ups, or pending compensation, it stalls progress from day one.
Synchronizing project awards with land readiness and statutory clearances isn't just good practice, it's a game-changer. It allows contractors to mobilize immediately, reduces redesigns, and brings greater cost control and timeline certainty," said Shailesh Agarwal, partner, risk consulting (infrastructure), EY India.
'For alignment to take root, clear intent must be supported by consistent execution. A centralised digital platform to track clearance progress, field-level empowerment to address last-mile issues, and the appointment of independent readiness verification agencies can ensure projects are awarded only when truly execution-ready," he added.
Land acquisition milestones
With respect to land acquisition itself, the MoRTH circular said that the process will begin 60 days after a highway's alignment is finalised, and notification regarding land acquisition is to be issued before receipt of bids. Also, 90% of right of way (RoW) length should be awarded before a letter of award (LoA) is issued.
RoW refers to the land required for building a highway.
Also read: Centre asks for measurable socio-economic benefits reports from highway development
In addition, timelines have also been provided for acquiring land to construct approach road to a highway project.
Accordingly, MoRTH has now decided that possession of 100% of RoW length should be available in an approach stretch of up to 1 km on either side of a standalone bridge or road over bridge project on or before issue of LoA. Also, possession of 100% of the ROW length has to be made available in an approach stretch of upto 1 km on either side of any project with a tunnel on or before issue of LoA.
'Assessment of value and payment for structures should be considered as an integral part of the compensation payment on land acquisition for the purpose of the above milestones," the MoRTH circular said.
PadmaPriya, Partner, Grant Thornton Bharat, said, 'Disputes frequently arise when projects are awarded before obtaining critical clearances such as land acquisition, environmental, forest, wildlife approvals, railways, archaeological survey etc.
Contractors face delays in mobilization and execution due to inaccessible project sites or regulatory restrictions, leading to claims for time and cost overruns. These unresolved issues can strain government-contractor relationships, invite arbitration or litigation, and ultimately slow down the speed of infrastructure delivery."
'However, the recent initiatives taken by MoRTH are very promising to overcome the hindrances occurring in providing unencumbered project sites to the contractors. If these initiatives are adopted with the fullest of their spirit, they may resolve upto 90% of such cases where the government faces delays and cost overruns," she added.
While highway projects are very complex in nature, synchronizing the award of projects with the completion of statutory milestones ensures that projects are 'shovel-ready" at the time of award. This reduces uncertainty and prevents post-award delays.
'Adherence to these timelines brings predictability, enables smooth contractor mobilization, and minimizes the scope for contractual disputes, thereby improving cost control and accelerating project completion," Padma Priya said.
The government has already implemented various initiatives such as the Bhoomi Rashi portal for ensuring that compensation is given for land acquisition on a real-time basis and Parivesh Portal, a single window system for obtaining all type of approvals.
'While milestone-based synchronization is a significant step forward, challenges still remain in terms of inter-departmental coordination, procedural bottlenecks, and real-time tracking of clearance statuses. Leveraging digital tools for transparency, creating single-window systems for approvals, and decentralizing certain decision-making powers can enhance efficiency," Padma Priya said.
Also read: India plans to offer grants, ease regulatory norms for rare earth processing amid China supply woes

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Mint
an hour ago
- Mint
Raymond Realty eyes higher sales, launches in FY26
Bengaluru: Raymond Realty, which is scheduled to list on the stock exchanges on 1 July, is looking at faster growth through higher home sales and several project launches in 2025-26, said a top company executive. The real estate firm was demerged from Raymond Ltd on 1 May and will list as a standalone entity. Mumbai-based Raymond Realty clocked around ₹2,300 crore of sales in FY25, and is targeting at least 20% growth this year. It also expects a 20% return on capital employed. Also read: Gautam Singhania meets European royal Prince Albert II: Here's why they met, what they discussed & more By the end of FY26, it plans to launch six projects - two in suburban Thane, where Raymond owns about 100 acres, and four projects in different locations across Mumbai Metropolitan Region (MMR) - Wadala, Sion, Mahim and Bandra. The developer currently has six projects under execution. Raymond Realty's residential portfolio, combining projects under execution and the ones to be launched, has a gross development value (GDV) of ₹40,000 crore. Of this, projects worth ₹25,000 crore GDV would be in Thane alone. The remaining projects of ₹15,000 crore GDV are in MMR. 'In the next 3-4 years, we will double our sales and portfolio size. As a company, we are trying to solve for two things in the industry - quality of projects and timely delivery. We also want to focus on post delivery service, and have started our own facilities management arm," Raymond Realty chief executive Harmohan Sahni said in an interview. Also read: Centre links part of state capex loans to new reforms in land, and digitization The demerger will consolidate the group's real estate business under a single entity, which, going forward, will further unlock the firm's potential as a pure-play property development vertical. The company will sell at a broad price range of ₹20,000-65,000 per sq ft, and is not looking to sell below that, or in the uber luxury category. 'We can't go lower than ₹20,000-22,000 per sq ft. We will not dilute the brand, and it is not a price-sensitive market," he added. MMR, India's most valuable property market, stands as one of the leading contributors to pan-India launches and sales. Most of the projects Raymond Realty has signed are redevelopment projects. The newly signed projects, in Mahim and Wadala, are a Maharashtra Housing and Area Development Authority (Mhada) redevelopment and a slum redevelopment project respectively. Also read: Centre weighs easing conditions for interest-free capex loans to states 'We will continue to pursue an asset-light model by signing projects through the joint development route as it is capital efficient. We are a net debt-free company," Sahni said. Beyond Mumbai, the company is exploring project opportunities to enter the Pune property market. 'We are choosy about the deals we want to sign," he added. MMR among all the top cities witnessed the highest sales of around 155,335 units in 2024, almost the same as 2023. Pune followed with around 81,090 units sold. The two western markets together led residential sales last year, said Anarock Property Consultants.


Mint
an hour ago
- Mint
Centre links part of state capex loans to new reforms in land, and digitization
New Delhi: The Centre has drawn up a new set of reform-linked conditions for states to access a portion of the ₹ 1.5 trillion interest-free capex loan for FY26, two people aware of the matter said, with a focus on digitization, governance, land reforms and urban planning. 'States will now be required to implement targeted reforms in key areas including digital public infrastructure (DPI) for agriculture, improvements in financial management systems, better urban planning, and streamlined land-related processes," said the first person mentioned above, speaking under the condition of anonymity. Of the ₹ 1.5 trillion earmarked for FY26, around 60% will be unconditional or linked to infrastructure spending, while the remaining 40% will be tied to reforms that states and Union Territories must undertake to access the funds, the person mentioned above added. Interest-free loans with a tenure of 50 years have played a vital role in stimulating capital spending by states and catalyzing the economy since the pandemic. As things stand, states account for 20–25% of India's total infrastructure spending, a critical priority for the government. 'This year's reform agenda puts a sharp focus on accelerating digital transformation in agriculture through federated farmer databases, digitized land records, and digital crop surveys,' the second person mentioned above said, requesting anonymity. Meanwhile, the central government has made Aadhaar-based Direct benefit transfer (DBT) integration with the Reserve Bank of India (RBI) and National Payments Corporation of India (NPCI) mandatory across all state-run schemes. "Land and regulatory reforms remain a key thrust as states are expected to enable flexible mixed-use development, digitize land use change approvals, rationalize industrial road width norms, and amend building rules to minimize land loss. These are critical steps to boost manufacturing, agriculture, and ease of doing business," the second person mentioned above said. 'The goal is to ensure that capital investment is not just about creating assets, but about improving the way states govern and deliver,' the person added. Launched in FY21, the Centre's 50-year interest-free capex loan scheme has played a key role in driving state-led capital spending and reviving the post-pandemic economy. For FY26, ₹ 1.5 trillion has been earmarked to accelerate infrastructure development and support state-level projects. Of this, about 60% will be either unconditional or tied to infrastructure spending, while the remaining 40% will be linked to specific reforms. The conditions states had to meet in the past two years to avail of the central loans included reforms in the housing sector, providing incentives for scrapping old government vehicles and ambulances, reforms in urban planning and urban finance, increasing housing stock for police personnel, and setting up libraries with digital infrastructure at panchayat and ward levels for children and young adults. Finance minister Nirmala Sitharaman ramped up allocations to ₹ 1.5 trillion each for FY25 and FY26—up from ₹ 1.10 trillion in FY24. However, the FY25 outlay was later revised to ₹ 1.25 trillion due to slower-than-expected spending in the first half of the fiscal, which was largely due to elections. A spokesperson of the Ministry of Finance didn't respond to emailed queries.


Mint
an hour ago
- Mint
Gujarat Electronics Component Manufacturing Policy aims to reduce import dependency
Ahmedabad, Jun 22 (PTI) Incentives for projects approved by MeitY, quick disbursal of assistance and reducing import dependency by attracting over ₹ 35,000 crore in new investments are among the prominent features of the Gujarat Electronics Component Manufacturing Policy-2025. The policy, which aims to transform Gujarat into a global hub for electronics manufacturing, was unveiled by Chief Minister Bhupendra Patel on Sunday. The policy states that projects approved and supported by the Union Ministry of Electronics and Information Technology (MeitY) will be eligible for 100 per cent Central assistance when established in Gujarat. Projects approved by the MeitY will receive incentives from both the Centre and the state government through a single approval and incentive assistance will disbursed within 30 days, a government release stated. "This means MeitY-approved projects set up in the state will receive dual incentive benefits from the Central and Gujarat governments," it said. Aligned with the Union government's Electronics Component Manufacturing Scheme (ECMS), the policy ensures "a 100 per cent top-up on Central support while guaranteeing timely disbursement of assistance. "Once a project is approved under the ECMS from MeitY, it will automatically become eligible for the same grant-in-aid in Gujarat. The state government will disburse its incentive within 30 days of the Centre releasing the assistance," the release said. The policy aims to reduce dependence on imports and improve technological resilience by attracting over ₹ 35,000 crore in new investments. It aims to create substantial high-skilled employment opportunities within the state's electronics component manufacturing sector. The policy hopes to boost investment in key segments, such as multi-layer and HDI printed circuit boards, lithium-ion cells, SMD passive components, display and camera modules, electronic parts, and the additional machinery for their production. "The policy's core focus is to bridge the talent gap, promote innovation, and offer support for research and development initiatives, with the recognised Gujarat-based institutions being eligible for assistance of up to ₹ 12.5 crore to establish centres of excellence, finishing schools, or applied research laboratories," the release stated. The policy aims to establish Gujarat as a prominent player in global electronics supply chains by promoting the manufacturing of local electronic components and sub-assembly production, reducing import dependency, and boosting exports, which will drive product value growth in global electronics value chains (GVCs). The Government of India (GoI) guidelines mandate the submission of applications to avail of the benefits of this policy by July 31, 2025. All MeitY-approved projects operating in Gujarat will automatically become eligible for availing of the policy benefits along with developing or proposed projects for incentives. The government said only the units other than those receiving assistance under Gujarat Electronics Policy 2022-28 will be eligible for benefits under this policy, and those availing benefits under this policy will not qualify under the Gujarat Electronics Policy.