MUMBAI: One of Mumbai's prominent slum redevelopment projects – Mata Ramabai Ambedkar Nagar and Kamraj Nagar in Ghatkopar – is raising eyebrows, but for the wrong reasons. MMRDA will redevelop Mata Ramabai Ambedkar Nagar and Kamraj Nagar slums in two phases. (Hindustan Times)
The project marks the debut of the Mumbai Metropolitan Region Development Authority (MMRDA) to slum rehabilitation, but the agency has committed to maintaining the 11 buildings under the rehabilitation component for just two years, not ten, as required by the Slum Rehabilitation Authority (SRA).
To be built on 31.83 hectares, the ₹ 8,498-crore project involves the rehabilitation of 16,575 tenements. Each eligible slum family will receive a one-bedroom apartment of 300sq ft. The developed space will include amenities such as gardens, healthcare centres and educational institutions. It will also include 5,000 apartments to accommodate people impacted by ongoing infrastructure projects.
While the project will be rolled out in two phases, MMRDA invited bids from developers for the first phase, involving 6,144 units, on Thursday.
In February 2024, the SRA had revised the maintenance criteria for slum rehabilitation projects, from three years to ten. This was done after a fire broke out at Unnat Nagar in Goregaon, killing seven people and injuring 62 others, a few months earlier. Safety concerns prompted the SRA to increase the maintenance period from three years to ten. This ensures better quality buildings for the residents.
Even buildings constructed under the Dharavi Redevelopment Project will be maintained by Navbharat Mega Developers, a special purpose vehicle between the Government of Maharashtra and the Adani Group, for ten years.
However, even before the Mata Ramabai Ambedkar Nagar and Kamraj Nagar project literally gets off the ground, the maintenance period is raising concerns. MMRDA documents accessed by Hindustan Times reveal that the developer of this project will need to maintain the buildings under the rehabilitation component for just two years, for the buildings' upkeep under the 'defect liability period' or DLP.
According to the document, the appointed developer 'shall complete the work and carry out testing & commissioning within 36 months inclusive of monsoon period + 24 months DLP for contractor's work'.
'For a developer, DLP is not a big deal. The buildings themselves will survive for a few decades; the challenge is always waterproofing. The developer must maintain the buildings for a minimum ten years,' said architect Nitin Killawala.
Failure to properly maintain the buildings is failure to provide dignified housing; they would turn into vertical slums. 'Water seepage could become a big issue, which is why a standard norm of ten years should be followed,' said Killawala.
Metropolitan Commissioner Sanjay Mukherjee did not respond to attempts by HT to reach out to him.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Metro, rail and bus hubs in MMRDA's plan for Dharavi, Infra News, ET Infra
Metro, rail and bus hubs in MMRDA's plan for Dharavi, Infra News, ET Infra

Time of India

time6 hours ago

  • Time of India

Metro, rail and bus hubs in MMRDA's plan for Dharavi, Infra News, ET Infra

Advt Advt By Join the community of 2M+ industry professionals. Subscribe to Newsletter to get latest insights & analysis in your inbox. Get updates on your preferred social platform Follow us for the latest news, insider access to events and more. Mumbai: Mumbai Metropolitan Region Development Authority (MMRDA) was appointed as the nodal agency to plan and develop a Multimodal Transport Hub (MMTH) as part of Dharavi Redevelopment Project (DRP). This move was formalised through a govt resolution issued on June 18, following a high-level meeting chaired by the chief minister on Apr proposed hub aims to bring Metro, suburban rail, buses, and non-motorised transport under one umbrella, offering seamless integration for commuters passing through Dharavi — one of the city's most densely populated and poorly connected neighbourhoods. MMRDA was asked to coordinate with Dharavi Redevelopment Authority and all transport bodies concerned to draft a comprehensive layout and implementation will also ensure easy access to Sion station on Central Railway and Mahim station on Western Railway, both located on either side of the redevelopment part of the larger redevelopment vision, a second Metro station is being considered for Dharavi. Besides the under-construction Metro Line 3 (Colaba-Bandra-Seepz), the area is expected to be connected by an extension of Metro Line 11 (Wadala-CSMT). Sources said this line is likely to be extended westward from Wadala to link with Metro Line 3 at Dharavi, enabling a crucial east-west and north-south interchange point. The Rs 16,000 crore Metro Line 11 project, implemented by the Mumbai Metro Rail Corporation Ltd (MMRCL), includes two proposed stations—one near Sion and another within support the bus component of the hub, DRP plans to build a modern depot for BEST. In return, 12 acres of land currently occupied by the Dharavi and Kalakilla bus depots in Sion East—which jointly accommodate around 300 buses and house key offices of the transport and power supply divisions—will be handed over for said the plan goes beyond Metro integration, with infrastructure for feeder buses, walking, and cycling for last-mile connectivity. "The intent is to build a future-ready mobility hub, not just a station," said an official. Feeder routes are being drawn up to link nearby areas with Metro and rail stations.

5 key highlights of Maharashtra's proposed housing society rules: 12% interest cap, redevelopment loans and more
5 key highlights of Maharashtra's proposed housing society rules: 12% interest cap, redevelopment loans and more

Hindustan Times

time7 hours ago

  • Hindustan Times

5 key highlights of Maharashtra's proposed housing society rules: 12% interest cap, redevelopment loans and more

The Maharashtra government plans to introduce revised rules for cooperative housing societies, which aim to simplify regulations and reduce bureaucratic involvement. The Maharashtra government plans to introduce revised rules for cooperative housing societies, which aim to simplify regulations and reduce bureaucratic involvement. (Picture for representational purposes only)(Mehul R Thakkar/HT) According to a report by Hindustan Times, the draft proposals include measures such as reducing interest on members' dues, enabling societies to raise redevelopment loans by linking them to land value, and revising maintenance fee structures. Here are five key highlights from the draft rules for Cooperative Housing Societies: 1) Lower interest on dues Maharashtra's draft rules propose reducing the interest on members' outstanding dues from 21% to 12%, easing residents' financial burden. 2) Easing redevelopment financing According to the draft, co-operative housing societies may be allowed to raise loans up to 10 times the land cost for redevelopment, supporting self-redevelopment or improved negotiations with builders. Also Read: Maharashtra approves new housing policy after nearly two decades: 5 key highlights 3) Modernising meeting protocols The draft proposes that annual general meetings (AGM) may incorporate virtual participation, with a quorum set at two-thirds attendance or 20 members (whichever is lower). Decisions require a simple majority (51%), and virtual meetings must be video-recorded if they are for redevelopment. 4) Empowering heirs/nominees The draft proposes introducing a new category called 'provisional members,' allowing nominees to exercise voting rights after a member's death, even before the ownership is formally transferred. Also Read: Mumbai Real Estate: Developers waive floor-rise premiums to attract buyers amid surging inventory 5) Standardise charge collection and funds According to the Maharashtra government's draft, common service charges will be equally divided among all flats, while water charges will be calculated based on the number of taps. The draft also mandates annual contributions to include a sinking fund of at least 0.25% and a repair and maintenance fund of 0.75% of the building's construction cost. Also Read: Dharavi Redevelopment: Maharashtra govt approves stamp duty concessions for Special Purpose Vehicle 'We will finalise the rules by incorporating the suggestions and objections in eight days, after which the draft will go to the principal secretary of the cooperation department. Once the rules are vetted by the law and the judiciary department, they will be notified. Many clauses, such as charges of sinking repair funds, were in the bylaws, but by bringing them into the rules, we have given them legal sanctity. Once the rules are finalised, we will reframe the bylaws to simplify them," Kiran Sonawane, deputy registrar of Maharashtra, told the Hindustan Times newspaper.

Maharashtra plans to open up plots reserved for abattoirs
Maharashtra plans to open up plots reserved for abattoirs

Hindustan Times

time12 hours ago

  • Hindustan Times

Maharashtra plans to open up plots reserved for abattoirs

MUMBAI: The Maharashtra government has decided to open up plots reserved for slaughter houses in all municipal corporations of the state and the Mumbai Metropolitan Region (MMR), except in Mumbai. It has offered private owners the option to use the land for a purpose of their choice if they build a slaughter house on part of the land. The owner will get to use the permissible floor space index (FSI) and transferable development rights (TDR) on the plot. Slaughter houses to be developed shall be used only for small animals (Ashok Dutta/Hindustan Times) These changes have been proposed by the state urban development department in the Unified Development Control and Promotion Regulations (UDCPR). The department has issued a notice seeking suggestions and objections from the public in the next 30 days. If the plan goes through, it would impact all major cities including those in the Mumbai Metropolitan Region (MMR). According to the proposed new provision, the planning authority or the appropriate authority may acquire and develop the reserved site for the same purpose, or it may allow the owner to develop the reservation, subject to certain conditions. 'It (the owner) has to develop a slaughter house on 60% of the plot along with the necessary amenities and hand it over to the municipal corporation or the planning authority,' said a senior official from the state urban development department. 'Slaughter houses to be developed shall be used only for small animals. Considering public health and safety, and also existing use of the surrounding area, the planning authority shall take a decision regarding the development of the slaughter house through accommodation reservation,' states the notice issued by the urban development department on June 6. 'Sufficient segregating distance shall be kept between the slaughter house and the residential or commercial use, and a no-objection certificate (NoC) from the Maharashtra Pollution Control Board MPCB) shall be obtained before allowing the development,' it adds. According to the notice, owners will be entitled to develop the remaining portion of the plot for the uses permissible in adjoining zones with full permissible FSI of the entire plot and permissible TDR potential of the entire plot. 'The authority, if required, shall allow the TDR for the unutilised FSI, if any (after deducting in-situ FSI), to be utilised as per TDR regulations,' it further stated. Aseem Gupta, additional chief secretary, urban development department, said the principle of 'accommodation reservation' is being made applicable to this provision. 'It allows development of a reserved plot without the need for acquisition, while the municipal corporation concerned gets a developed amenity free of cost. It also helps in expeditious development. The principle of accommodation reservation has already been applicable to many other reservations,' Gupta told HT. He added that the new provision would be implemented where the UDCPR is applicable in the state. The UDCPR was established to standardise construction rules and development regulations for various planning authorities and regional plan areas across the state. It, however, is not applicable in some areas such as the Brihanmumbai Municipal Corporation (BMC), Maharashtra Industrial Development Corporation (MIDC), Navi Mumbai Airport Influence Notified Area (NAINA), Jawaharlal Nehru Port Authority (JNPA), among others.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store