AGSA report reveals mismanagement in KwaZulu-Natal infrastructure projects

AGSA report reveals mismanagement in KwaZulu-Natal infrastructure projects

IOL News15-05-2025

The KwaZulu-Natal Legislature in Pietermaritzburg, where the Auditor General of South Africa (AGSA) presented its findings on contractors appointed to key infrastructure projects in KwaZulu-Natal that were not qualified or capable of performing the required work leading to substandard quality and cost overruns.
Image: Shan Pillay
The Auditor General of South Africa (AGSA) found contractors appointed to key infrastructure projects in KwaZulu-Natal were not qualified or capable of performing the required work, leading to substandard quality and cost overruns.
The AGSA found that the KwaNqetho Reservoir in the eThekwini municipality, a critical water infrastructure project, was delayed because of mismanagement. In addition, the material used around the reservoir platform indicated poor backfilling compaction, particularly on the steep slope of the reservoir.
Nomalungelo Mkhize, AGSA Business Unit Leader in KZN, presented the local government audit outcomes of the Municipal Financial Management Act (MFMA) to the KZN Legislature-Standing Committee on Public Accounts (SCOPA) and the Portfolio Committee on Cooperative Governance and Traditional Affairs (Cogta) on Tuesday.
The AGSA looked at 15 infrastructure projects in the eThekwini, Msunduzi, uMhlathuze, KwaDukuza, Okhahlamba and uMkhanyakude municipalities. The AGSA said there were five new projects and 10 projects where they did follow-ups on the prior year findings and continued auditing the project as part of its life cycle.
The AGSA also audited existing infrastructure which they identified in different stages of a project life cycle including wastewater treatment works, solid waste, landfill sites and roads.
The AGSA found that the Mkhizwana Water Treatment Works project in eThekwini was delayed by 221 days due to gross negligence in the preparation of designs and drawings. Also, the Nondabuya Water Supply Scheme in the Umkhanyakude was delayed with only 726 of 1,811 households being connected to the reticulation system. The AGSA found that installation was in a worse condition compared to the previous audit.
Other infrastructure delivery weaknesses include the Austerville Substation south of Durban, which was intended to supply increased and stable electricity to industrial, commercial and residential customers. The project has been in the planning phase for 15 years.
The AGSA stated that this project faced significant delays due to project mismanagement, planning inefficiencies, contractor-related issues and financial mismanagement. The AGSA said that the civil works portion of the Austerville project was originally planned to be completed by 18 August 2021. However, due to multiple stoppages, the project was delayed, ultimately leading to the termination of the contractor on 25 January 2023 with only 63.97% of the work completed.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad Loading
The Namibia Stop 8 Housing Project in eThekwini, aimed at delivering 343 housing units, remains behind schedule with only 29 units completed as of September 2024.
The AGSA raised concerns regarding project oversight, resource allocation, and contractor accountability. Its' report stated that causes of delays were due to poor quality cost overruns and service interruptions, largely due to inadequate project planning and needs assessment.
The AGSA found that many of the projects suffered from inadequate needs assessment and project planning.
It found numerous cases, where the contractors were appointed were not qualified or capable of performing the required work to meet the agreed upon standards.
This included delays in meeting milestones and failed to adhere to contract specifications leading to substandard quality and cost overruns.
zainul.dawood@inl.co.za

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

R1. 4bn wasted: Sapo's epic failure
R1. 4bn wasted: Sapo's epic failure

IOL News

time8 hours ago

  • IOL News

R1. 4bn wasted: Sapo's epic failure

THE SA Post Office (Sapo) has been declared financially 'unsustainable' and riddled with systemic mismanagement. Image: Independent Newspapers Archives THE SA Post Office (Sapo) has been declared financially 'unsustainable' and riddled with systemic mismanagement after receiving its fourth consecutive failed audit opinion from the Auditor-General of South Africa (AGSA), sparking outrage from MPs who demanded answers on why the failing institution keeps consuming public money. AGSA's damning report, presented to Parliament's Standing Committee on Public Accounts (Scopa) on June 11, exposed: R152 million lost to fruitless and irregular spending in 2023/24, with R136 million dismissed without repercussions. A dismal 13% achievement rate on performance targets, despite a R381m bailout from the Unemployment Insurance Fund (UIF) for staff salaries. R86 million paid to business rescue practitioners (BRPs) and advisors since 2023, with little progress to show. No stable leadership, severe staff shortages, and repeated violations of the Public Finance Management Act (PFMA). AGSA officials delivered a stark verdict: Sapo is being propped up by taxpayer funds. 'Costs keep outstripping income. Debts are mounting, and the organisation isn't earning enough to survive,' said AGSA's Makhai Motshekga. ActionSA's Alan Beesley was more blunt: 'It's time to pull the plug. Sapo cannot be saved.' The BRPs, brought in July 2023, have already burned through R86m, including payments to consultants, tax experts, and lawyers. The EFF's Ntombovuyo Mente-Nkuna demanded answers: 'Who are these advisors? What have they actually fixed? We can't keep throwing money at a sinking ship.' Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ AGSA's Nathan Lawnet said the BRPs — from firms SNG and Legae — were 'qualified' but admitted survival depends on 'new income sources and partnerships,' which still don't exist. MPs pressed AGSA on Sapo's unaccounted-for assets, with Mente-Nkuna noting rural branch closures force grant recipients to travel far. 'How many buildings does Sapo still control? Why aren't they helping our communities?' she asked. AGSA confirmed Sapo owns properties and old equipment, but said almost nothing has been upgraded in years. Postbank's separation from Sapo — required by banking laws — has created confusion. Though Postbank is now audited independently, it still depends on Sapo's failing systems. ANC's Gijimani Skosana warned: 'Postbank once helped fund Sapo. Now, both are drowning.' Wasteful spending continues unchecked, with R200m squandered since 2021. Mente-Nkuna slammed the impunity: 'R136 million just written off? Who checked this? Who was held responsible?' AGSA admitted probes were lacking, blaming write-offs on debt settlements, not internal crackdowns.

Enoch Godongwana to highlight public financial management at SAI20 Summit
Enoch Godongwana to highlight public financial management at SAI20 Summit

IOL News

time4 days ago

  • IOL News

Enoch Godongwana to highlight public financial management at SAI20 Summit

Finance Minister Enoch Godongwana is expected to deliver a keynote address at the SAI20 Summit. Image: Phando Jikelo / GCIS The Auditor-General of South Africa (AGSA), Tsakani Maluleke, will host a summit of supreme audit institutions (SAIs) of the G20 member countries, known as SAI20, on June 24-25, 2025, in Johannesburg. The summit is an event that will pave the way for the upcoming Group of 20 (G20) Summit to take place later in the year, and will bring together auditors-general from G20 countries to discuss key issues related to transparency and accountability in public financial management. Finance Minister Enoch Godongwana will deliver a keynote address at the summit, highlighting the importance of transparency and accountability in public financial management, according to the AGSA statement. The summit will provide a platform for SAIs to share insights and best practices in promoting good governance and oversight of sustainable development. 'The SAI20 Summit is a crucial event that will enable SAIs to drive collaboration and support their vital role in enhancing governance and fostering oversight of sustainable development within their respective countries. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ 'The gathering will also present an opportunity for SAIs to share insights that will create foresight for G20 governments to ensure that the plight of citizens in their respective countries continues to lead the developmental agenda,' said Maluleke. She said the summit will focus on two developmental themes: unlocking and leveraging public infrastructure funding for equality, sustainable growth, and bringing improvement to the lives of citizens; and collaborative and integrative efforts for a future-ready workforce – bridging the skills gap in sustainable economic growth. Auditor-General Tsakani Maluleke will host the SAI20 Summit next week. Image: Thobile Mathonsi / Independent Newspapers These themes are aligned with the G20's theme of solidarity, equality, and sustainability. 'The SAI20 Summit is a significant event that will have implications for global transparency and accountability. The summit will deliver a joint communique that will set out priorities for all member SAIs to implement until the next summit. This will ensure that SAIs continue to play a vital role in promoting good governance and oversight of sustainable development,' added Maluleke. According to Maluleke, the SAI20 Summit is an opportunity for SAIs to demonstrate their value and benefit by making a difference to the lives of citizens in their respective jurisdictions. 'The ultimate goal is to create an environment where public sector auditors all over the world can do their work to the best benefit of the citizens they are supposed to serve without any fear, favour or prejudice.'

ELM cuts wasteful spending, earns praise for financial reforms
ELM cuts wasteful spending, earns praise for financial reforms

The Citizen

time13-06-2025

  • The Citizen

ELM cuts wasteful spending, earns praise for financial reforms

Emfuleni Local Municipality (ELM) won a third-place runner-up award for managing to reduce the 2023/24 financial year's unauthorised, Irregular, Fruitless, and Wasteful Expenditure (UIFW) by 44%. The South African Local Government Association (SALGA) 3rd Annual Municipal Audit Awards were held in Johannesburg on May 30. The award signifies tireless work done by ELM towards attaining a clean audit by reducing financial transactions that violate the Municipal Finance Management Act (MFMA) and other procurement legislation. According to ELM spokesperson Makhosonke Sangweni, for the municipality, the award is not just an accolade, but an encouragement to improve financial management for progressive audit outcomes and service delivery. Reflecting on winning the award, Municipal Manager April Ntuli said ELM is proud to be considered part of municipalities that are committed to financial sustainability and the provision of improved services for consumers. 'I would like to thank the council and its committee for taking a bold decision to deal with all historical UIFW that was accumulating yearly and hampering service delivery for the people of Emfuleni. 'Notwithstanding the financial situation confronting the municipality regarding the high rate of unemployment and the impact it has on payment for services and the overall service delivery, ELM remains committed to being transparent and prudent on how it spends money meant for service delivery programs,' said Ntuli. In a statement, Sangweni said the municipality is aware that the community has lost trust in us and will only be happy when the award is supported by an improved commitment to service delivery. 'Part of the service delivery challenges we have is that of fleet; to mitigate this, the municipality has embarked on a project to improve fleet availability through leasing. This will assist with securing a significantly higher number of vehicles as opposed to outright purchasing,' he said. 'To ensure that the SALGA award is not in vain and that we perform better in the next financial year, the municipality is currently rolling out the installation of electricity meters and concluding the debt rehabilitation campaign in high hopes of improving revenue collection. The municipality is calling on all account holders to pay for services to improve the quality of life in Emfuleni,' he added. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!