New Cork motorway: Taoiseach Micheál Martin confident BAM can deliver project on time and under budget

New Cork motorway: Taoiseach Micheál Martin confident BAM can deliver project on time and under budget

The latest contract on the table is for the M28 Ringaskiddy motorway, which was signed this week to the tune of €206 million and has a completion date of Summer 2028.
The agreement came on the same date as the latest delay in the construction of the National Children's Hospital came to light, while closer to home the Dutch contractor has applied for a five-year extension on the Cork Events Centre, on which the sod was turned in 2016.
Alasdair Henderson, Executive Director of BAM Ireland said at the M28 launch that the project 'reflects our continued commitment to building sustainable, future-ready infrastructure that serves communities and commerce alike.'
That same day, BAM issued High Court proceedings against the Irish state over a €122m claim for extra costs resulting from delays in the National Children's Hospital.
That comes after the revelation that the final completion date of the hospital is now expected to be September 30, with an estimated final cost of €2.24bn.
The Taoiseach says, despite all the various delays, he is confident that BAM can deliver the M28 on time and under budget, but says that laws dictate the Government's decisions on contracts, regardless of public opinion or confidence.
'Under European Union procurement protocols, they're open, they're transparent, governments do have to adhere to them,' said the Taoiseach. 'BAM have come in on time on other road projects and on other civil engineering projects, and that is the position.
The Taoiseach was speaking outside Dosco cleaning supplies, a Cork-based firm that has been in business since 1884. Since then, the Cork-based company have been manufacturing brushes and other cleaning items for its140 years-plus.
'The public may or may not (have confidence) but the bottom line is that we have to adhere to the rules of procurement. We can't deviate from them, otherwise we face other potential legal penalties. If one was to say that a government was to…debar a company, there would be legal consequences for that.
'To be fair, and to be balanced, there are issues with the Children's Hospital that have been ongoing and unacceptable, but equally the company has executed projects in other parts of the country.'
Despite this, the Taoiseach says that the European Union needs to keep its procurement laws 'under review'.
'Where there's non-conformance…those contracting should have recourse to some actions in that respect.'

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Tech tycoon Mike Lynch's sunken super yacht lifted to surface
Tech tycoon Mike Lynch's sunken super yacht lifted to surface

Irish Independent

timean hour ago

  • Irish Independent

Tech tycoon Mike Lynch's sunken super yacht lifted to surface

Salvage experts lifted Mike Lynch's sunken superyacht to the surface and began pumping seawater out of it on Saturday, 10 months after it sank off the coast of Sicily, killing the British tech tycoon, his teenage daughter and five others. Mr Lynch was born to a Co Tipperary mother who was a nurse and a Co Cork father who was a firefighter. Work resumed at first light, with one of the most powerful maritime cranes in Europe having been used to haul the 56-metre-long (184-foot) Bayesian from beneath the waves. The upper decks appeared badly damaged while the blue hull was encrusted with mud. The Bayesian was moored off the small port of Porticello, near Palermo, in August last year when it sank during a sudden storm. The yacht was vulnerable to violent winds and was probably knocked over by gusts of more than 117 km (73 miles) per hour, an interim British report said last month. The vessel will be held in an elevated position over the weekend while checks and preparations are made, said TMC Marine, which has been leading the salvage operation, working with Dutch specialists Hebo Maritiemservice to lift the yacht 50 metres from the seabed over the past few days. It is then expected to be transported to the nearby port of Termini Imerese on Monday and handed over to the authorities who are investigating the sinking. The recovery process has been made easier after the vessel's 72-metre mast was detached using a remote-controlled cutting tool and placed on the seabed on Tuesday. In addition to Lynch, founder of the software company Autonomy, his daughter Hannah, lawyer Chris Morvillo and his wife Neda, banker Jonathan Bloomer and his wife Judy, and chef Recaldo Thomas were killed when the yacht sank. Nine other crew members and six guests were rescued.

€122 billion investment needed by 2030 to meet housing targets
€122 billion investment needed by 2030 to meet housing targets

RTÉ News​

timean hour ago

  • RTÉ News​

€122 billion investment needed by 2030 to meet housing targets

A new survey reveals that a total investment of €121.6 billion is needed between now and 2030 if Ireland is to meet its housing targets. Deloitte's new Crane Survey Report found that an investment of €16.4 billion is required this year, rising to €17.2 bilion in 2026, €19.3 billion in 2027, €21.3 billion in 2028, €23.3 billion in 2029 and €24.1 billion by 2030 to achieve the Government's target of 60,000 homes a year. Deloitte said that given the scale of the challenge, Ireland is unlikely to reach or maintain the annual output of 60,000 homes. The Deloitte Crane Survey Report is a comprehensive analysis of construction activity across Irish cities, tracking what is being built and where and what this means for the country's economic and social priorities. The latest Crane Survey report estimates a total housing output of 33,000 this year, below the Government's target of 41,000. Risks to delivery in 2025 are "tilted to the downside", according to the report, which adds that in the absence of a "healthy planning pipeline" it is very difficult to see the required level of 60,000 homes a year being achieved in the first instance or maintained. A total of just over 30,230 new homes were delivered in 2024, a drop of 7% on 2023. Meanwhile, just 32,400 homes were granted planning permission last year, down 3%. Deloitte said this figure is "particularly stark" as it represents just two-thirds of what is needed each year if Ireland is to deliver the 60,000 homes a year required to meet current housing need and future population growth. Its analysis shows the drop in granted planning permissions was driven by a substantial reduction in the number of apartments which received planning, down 39% year on year. It noted that commencements soared to 69,060 units in 2024, up 121% year on year, but this was linked to expiring incentives, which were ultimately extended. Commencements have been subdued in the opening months of this year, it added. Deloitte said the Government's decision last month to extend planning permissions for schemes due to expire shortly is welcomed. It also said the recently announced reforms to the current Rent Pressure Zone (RPZ) model are a welcome step in the right direction, but, on their own, are unlikely to yield a significant activation in commencements. Today's survey notes that just 895 purpose-built student accommodation bedspaces (PBSA) completed construction last year. This was down from 1,630 bedspaces in 2023 and represents the lowest level since Deloitte's records began in 2016. The delivery of PBSA bedspaces was confined to Cork and Dublin - with 620 at NovelBottle Works at the former Coca-Cola bottle factory on the Carrigrohane Road in Cork and 190 bedspaces at The Residence on Prussia Street in Dublin. The remaining bedspaces were delivered at Blackhall Place in Stoneybatter in Dublin where a refurbishment added an additional 80 beds. The report noted that by the end of the first quarter, 1,400 PBSA bedspaces were under construction across six schemes, compared to 1,160 bedspaces at the same time last year. Construction is spread across Galway, Dublin, Limerick and Kildare. Today's report also shows that completions in the Dublin office market rose last year to 169,500 square metres, a substantial increase on 2023 volumes of 95,400 square metres. But Deloitte said this rise was expected and should not be regarded as an indication of increased construction activity within the sector and reflects the completion of an overhang of stock. The report says that the only delivery expected in 2027 based on current construction statistics is 1 Adelaide Road, which is already pre-let in full. This means 2027 may be the first year since 2015 that no new office space will be delivered in the city, it added. Meanwhie, the volume of new rooms added to the hospitality market declined by 17% last year with just 1,358 new rooms. Some 4,060 rooms were under construction in the first quarter of this year, however, with Dublin absorbing the lion's share. This represents a significant rise on last year's Crane Survey (2,850 rooms) as several large hotels commenced construction, including at Dublin Airport, where 412 rooms are set to be delivered. In total, 1,410 new rooms are due to be added in 2025. A further 2,510 beds are due to be delivered in 2026, with the remaining beds under construction due to be delivered in 2027. Kate English, Chief Economist at Deloitte Ireland, said we are seeing cranes across the skyline, but not enough where they are needed most. "What this research reinforces is that the biggest issue facing Ireland right now isn't demand, it's supply. Whether it's homes, student beds, or affordable units, we're simply not building enough to meet the needs of a growing population and a resilient economy," Ms English said. "A stable policy environment is crucial in Ireland, as inconsistency in housing policy will deter and dampen investor confidence in Ireland. Without stability, capital will be redirected to jurisdictions offering more predictable and investor-friendly environments. This is not a hypothetical risk, it is a market reality," she cautioned.

Dublin Airport hits out at council's enforcement notice
Dublin Airport hits out at council's enforcement notice

Extra.ie​

time3 hours ago

  • Extra.ie​

Dublin Airport hits out at council's enforcement notice

Dublin Airport's operator has been hit with a planning enforcement notice for breaching the highly contested passenger cap, describing it as 'a sorry indictment of the mess that is the Irish ­planning system'. Describing the airport as the most vital piece of transport infrastructure in Ireland, a DAA spokesman said: 'The system is quite simply broken and needs to be overhauled.' The airport is limited to ­handling a maximum of 32 ­million passengers a year under a condition of the planning ­permission granted in 2007 for Terminal 2. Dublin Airport. Pic: Getty Images However, the DAA and many airlines have challenged that limit, saying it is limiting the country's economic growth and could result in higher fares for passengers. Earlier this month, Dublin ­Airport said it was expecting more than ten million ­passengers to pass through during the peak months. A High Court-imposed pause on the cap, won by the airlines, means more than 36 million ­people could use the airport this year. Last year, the airport handled 33.3million passengers. Dublin Airport. Pic: Getty Images Fingal County Council confirmed yesterday it had issued a planning enforcement notice to DAA for breaching the cap. The council is reported to have received complaints from 60 individuals about the alleged planning breach. In a statement, the council said its enforcement notice included a two-year period to comply with planning conditions imposed by An Bord Pleanála over passenger capacity at Dublin Airport. Pic: Mark Gusev/Shutterstock A council spokesman said: 'The two-year period provides an opportunity for DAA to ­progress their planning ­applications to increase ­passenger capacity at Dublin Airport or take such other steps as they consider appropriate to achieve compliance.' Mayor of Fingal Tom O'Leary, a Fine Gael councillor, said the county council had to follow the legal process. He continued: 'This makes it even more urgent for the Government to assist in any way that they can to try and sort out the capacity issue at Dublin Airport. They need to do whatever they can to ensure that the ­airport can grow in an orderly manner and that the residents around it are looked after.' However, the DAA said that until changes were made to the cap, Ireland's national airport was 'hamstrung' and could not get on with its mandate to grow Ireland's connectivity. 'The airport needs to be reclassified as national strategic ­infrastructure, with decisions made by a national planning body and not a local authority,' a spokesman said The High Court pause on the cap is likely to continue for a year while certain matters related to aircraft take-off and landing slot allocations are examined by the European Court of Justice. The Government plans to remove the cap through legislation, starting in autumn. Ryanair has called for urgent action from the Government, stating that local authorities should not oversee national transport infrastructure. A Department of Transport spokesman said it was aware of the enforcement notice. They continued: 'The minister has recently reiterated the importance of DAA continuing to engage proactively with the planning authority and the ­Aircraft Noise Competent Authority to facilitate progress on the two planning applications DAA has lodged.'

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store