Does Scotland really need more offshore wind farms?

Does Scotland really need more offshore wind farms?

Often critics will say there are already enough onshore wind, but what does that mean? And is that really seen in the figures? The claims are examined here, as well as key issues like constraint payments and why so many of the UK's onshore wind farms are in Scotland.
Claim: Scotland is already producing more electricity than it needs
Yes. Electricity transfers data show that Scotland exported 21.0 TWh of electricity and imported 1.3 TWh of electricity in 2024. This means that Scotland's net exports of electricity (exports minus imports) in 2024 was 19.7 TWh.
In 2024, Scotland generated a record 38.4 terawatt hours (TWh) of renewable electricity, suggesting that it exported around half.
Claim: Scotland already has enough onshore wind capacity to meet its total electricity 2050 demand.
Currently, according to DESNZ, Scotland has an onshore wind capacity of 10GW, and a gross peak demand of 4GW. However, NESO, in its Ten Year Statement estimates gross peak demand for Scotland in 2050 at between 8.5GW and 11GW depending on what degree of electrification takes place.
'Over the next 10 years,' it says, 'rapid growth in renewable -generated electricity in Scotland will mainly be attributed to offshore wind. This will cause far greater power transfer requirements across the Scottish boundaries, increasing the network reinforcement needs in some areas. Generation capacity in Scotland heavily exceeds demand, thus Scotland will be expected to export power into the rest of Great Britain most of the time except during periods of prolonged low wind, where the reverse may occur.'
Graph of Scotland's gross electricity demand from NESO's Ten Year Statement (Image: NESO)
However, in a renewable system, where generation is intermittent, capacity needs to be significantly higher than peak demand.
Since there are, as yet, no target figures for Scotland's wind generation for 2050 – though overall, according to the Climate Change Committee's Seventh Carbon Budget, UK is aiming for 125GW offshore wind, 27GW onshore wind and 106GW solar- it's hard to know by how much Scotland is likely to exceed its own demand.
Claim: Scotland already has enough wind consented and in planning for 2030 or 2035
One Caithness-bsed campaigner who has looked at the figures, is Kathrin Haltiner, who says, 'For the whole of Scotland for 2030 and even to 2035, what is already in the planning system, without any scoping applications, is more than enough to reach these caps and these caps are important because anything that goes over these caps is not going to help with net zero.'
In a recent analysis she writes about the North of Scotland, noting that the Clean Power Action Plan 'caps onshore wind farm development for North Scotland at 9GW for 2030 and only adds a very small capacity increase for the whole of Scotland until 2035. Clearly SSEN's ambitions are oversized.'
'North Scotland already has 6.3GW of additional onshore wind farm capacity in the pipeline: 0.2GW under construction, 3.2GW consented and awaiting construction, and 2.9GW in planning (excluding projects only at scoping stage).
"Together with the already built 3.8GW the potential capacity in North Scotland is 10.1GW, that is 1.1GW over the capacity advised in the Clean Power 2030 Action Plan. This means consents can be given more selectively from now on. The urgency used as an argument from developers to get a consent does not hold up anymore.'
Do these figures stack up?
What is current onshore wind capacity
According to DESNZ, at the end of last year Scotland had an installed onshore wind capacity of 10.3GW of onshore wind.
Haltiner came up with a slightly different figure when she added up all the operational capacity in the Renewable Energy Projects Database, making 9.4GW. This is also the figure I got when I did the same calculation.
How much more is already in the process of being built?
While recent official totals haven't been published, it is possible to total up the projects categorised as under construction on the Renewable Energy Planning Database, giving a figure for onshore wind under construction in Scotland of 1.7GW. A further list of projects consented to, but awaiting construction, totals 5.4GW. All together that's 7.1GW already underway.
What about projects that are already in the planning process?
Again, data in the REPD gives us an idea of what is a live planning application, as well as those projects that have been abandoned, refused or withdrawn. Kathrin Haltiner has totalled these up to 8.1GW.
How does this compare with the cap for Scotland for electricity generation for 2030?
The Clean Energy Action Plan, in its update on its annex, states that Scotland, as whole, has a cap for electricity generation for 2030 of 20.5GW. This is a massive leap from the current estimate of 10.3GW, and even more from the 9.4GW in the REPD.
But are we nevertheless, as Kathrin Haltiner, suggests already in danger of exceeding it?
According to Haltiner's calculations, if we add already operational wind to all the wind farms already under construction and consented to is, for the North of Scotland, 1.1GW greater than the sum of all onshore wind projects that are operational, in construction, consented to and in the planning system. For South of Scotland, the equivalent total is 2.5GW more than the 11.5GW cap. But the question remains, how many of those projects will make it through planning and become final operational projects?
Another way of looking at it is that if, across Scotland, we already have 16.5GW already in operation, in construction or consented to, leaving only 4GW still to take up. But there are actually twice as many (8.1GW) of projects sitting in the planning system and not all of those can happen.
Of course, some of those may, in any case, be withdrawn, some projects will be abandoned, others reduced, and some, even from the list of projects awaiting construction may not even happen. Others may not happen within the timeframe.
Does that mean we are set to have much onshore wind for current caps?
No, but in the unlikely event that every project that is sitting in planning were to be built Scotland would significantly exceed its cap. These figures suggest that only half of these projects can happen.
Is it a reason to slow down?
Not according to Scottish Renewables. Their director of onshore, Morag Watson put it this way, with different but similar figures - actually suggesting that even less of the projects currently in planning will be needed by 2030, but noting the need for continued urgency.
'Scotland has to increase its onshore wind capacity from 10GW to 20GW in about five years. In Scotland at the moment in the pipeline of projects that are consented but not yet built, we have 7.5 GW. So we need everything in the pipeline and just over 2 GW more. So this idea we have too much wind already is just not borne out by the strategic plans.'
She also points out that the process of going through scoping, planning and constructing a wind farm can be long. 'Viking windfarm on Shetland, that was a 15 year process to make the needs case for that. Renewable projects can wait up to ten years for a grid connection and you only get a connection to the grid when it's needed.'
'A project can go through the planning system, but just because they have planning permission doesn't mean they are about to get built and connected to the grid. Post planning they'll get a grid connection date and they will work to that grid connection date as to when they start building.'
Mostly Watson notes, the strategy up till 2030 is about reducing our dependency on gas, which is not only responsible for significant carbon emissions, but also, through its high price, drives up electricity bills. By 2030, the goal is to reduce the amount of gas used to generate electricity down to about 5% on the system.
She says: 'At the moment it's about taking the gas and other fossil fuel generation off the system – replacing it with renewables because they are cheaper and more reliable in terms of pricings that you pay. '
Is there also enough in the pipeline for 2035?
'Post 2030,' Morag Watson explains, 'what we start to see is the electrification of transport and heat really accelerating. That's when you see electricity demand really grow."
The next milestone and cap along the way is 2035, and what's striking is how little more capacity – just 700MW – is being allocated to Scotland over that period. This is a tiny fraction of what Scotland has already built and is set to achieve in the next five years.
Scotland's offshore wind industry has already flagged that up as a problem. A group of 13 developers signed an open letter to UK Energy Secretary Ed Miliband amid concerns of a 'de-facto ban' on Scottish onshore wind post-2030.
Earlier this year a group of In the letter, they stated: 'Currently, the cap in the Plan will allow only 700MW of additional Scottish onshore wind capacity to connect between 2031 and 2035.
'This would result in a decrease in the rate of installations allowed after 2030 of over 90%, and amounts to a de-facto ban on Scottish onshore wind post-2030.
What anti-wind farm campaigners see as ammunition for the argument that less windfarms should be consented, the industry itself is seeing as a threat, and reason to push for more capacity – but that capacity is determined by the grid, and therefore.
Claim: Scotland is already doing more than its fair share of onshore wind
Last year, Scotland, according to RenewablesUK, was operating 63% of the UK's onshore wind capacity. By 2030 Scotland will be producing 20.5GW of power, well over two thirds of the onshore wind generation in the UK, which is set at 27-29GW.
As this map shows, Scotland is doing a lot of the heavy lifting when it comes to onshore wind. Partly this is because previously England had a de facto ban on onshore wind developments.
But there are, as Morag Watson told me, other factors that feed in to why Scotland, in any case, is getting most of the wind. 'The reason for this is you can only put onshore wind where the wind consistently blows at 7ms or faster and there are chunks of England where that doesn't happen. You cannot build a wind turbine within 800m of someone's home, or with the bigger turbines, within 1km of someone's home.
"So if you take a map of the UK and take out everywhere where the wind is less than 7 m/s and then take out everywhere where you're within 800 m of someone's home, and then remove National Parks and national scenic areas, where you also cannot build wind, and again is why you don't see onshore wind predominantly down the west coast an central of Scotland, the only places you can build onshore wind are these parts of Scotland and mid Wales. This is why Scotland does do the heavy lifting on onshore wind.'
But, she notes, England is doing most of the heavy lifting on solar. Unsurprisingly, the south of England, where the sun is stronger, is also where there are more solar developments.
Why are wind farms so concentrated in the North East and Lanarkshire?
Wind farms tend to be where the grid is, so they can connect to them – and hence pattern of distribution across Scotland follows those powerlines. There is very little transmission infrastructure down the west coast of Scotland, which means relatively few turbines there.
It's often said that onshore wind developments in rural areas of Scotland are producing electricity for the cities to the south and England. But Morag Watson says, 'What is being built onshore in Scotland, is mostly what Scotland needs.'
The overhead powerline system, she points out, is not just about delivering energy to the south, but also about sending off connections along the way to power homes and transport in the areas the lines pass through.
Claim: Constraint payments are already costing millions and only going to rise – suggesting there is already too much onshore wind
A report published earlier this year by the Renewable Energy Foundation found that wind farm constraints continue to rise, both in total volume and in cost. In 2024 the consumer paid more than £393 million in direct costs to discard 8.3 TWh of wind energy. This was a rise from the previous year's cost of £310 million.
"Planning application data," the report said, 'shows that the, in our view, indefensibly high rewards for constraints continue to incentivise wind farm development in areas of the UK that have low demand and weak grid connection, resulting in high constraints.
More than 98% of the total constrained volume, it noted, arises from Scottish wind farms.
However, by far the biggest constraints wereapplied not to onshore wind, but offshore wind, including Seagreen.
'In particular, the offshore wind farm, Seagreen, whose majority owner is SSE, was alone responsible for 40% of the total volume of constraints. Seagreen is currently unsubsidised but 25% of its capacity has been awarded an as yet unimplemented Contract for Difference (CfD).'
The most constrained onshore windfarms were Viking (Shetland), Dorenell (Moray), which is currently proposing an extension which would make the area home to the largest onshore array of turbines, Stronelairg (Fort Augustus), which claims to be on of Scotland's windiest windfarms, Bhlaraidh (Glenmoriston). Of these four, all but Dorenell are owned by SSE Renewables.
However, Morag Watson points out that, relative to other impacts on electricity bills, like the fact gas prices set electricity prices 98% of the time in the UK (which has the highest electricity prices in Europe), the cost of curtailment is not that big.
'If you look," she saas, "at the cost of balancing the grid in the average electricity bill, which according to Ofgem is £929, £32 of that is the balancing, just under 3.5% and of that only part of that would be the cost of constraint payments. That's a vanishingly small part of your electricity bill. About £352 of your bill is driven by the wholesale cost of electricity – and that is driven by the gas price. So getting rid of the constraints and getting that gas down would be a really great thing for all of us.'
Part of what is driving constraints is the pinch point around what's called the B6 boundary in the grid between Scotland and England, which has a theoretic transfer capability currently of around 6.7 GW. But it isn't the only problem. Arguably the B4 boundary, between the North of Scotland and South of Scotland transmission areas, which has a capacity of only 3.4GW is still more important.
A recent blog published by UK Energy Research Centre, written by Professor Keith Bell and Callum MacIver of the University of Strathclyde looked at the 'impact of the role of transmission system availability (or rather unavailability) on rising curtailment costs in Britain'.
They noted the importance of the B4 boundary. 'Lots of the wind in Scotland is located in the far North, including all of that new capacity from Seagreen, Viking and Moray East, totalling around 2.5 GW. The B4 boundary is therefore often the primary pinch point on the system.'
The blog examines the impact of the failure to as yet build planned grid enhancement, especially the Peterhead to Drax undersea cable, which the system operator originally gave a delivery date of 2023, but is now not due till 2029.
'It seems clear we haven't built out enough North to South transmission capacity quickly enough, and that lies at the root of our current issues… but is there more to the story?'
It goes on to point that an additional issue is that 'often, the real-time capacity on the B4 and B6 boundaries is well below the maximum level, often even below 50%.'
The authors note also note that even these boundaries are not working to capacity. 'Not only have we, up to now, failed to add a 2 GW link across the congested Scottish boundaries, but B4 spent more than half of 2024 with an additional equivalent scale 2 GW reduction in operating capacity.'
The reason for this? 'Ironically,' they write, 'it is due to the implementation of network upgrades'. This illustrates that in a grid undergoing significant works over the coming years, transmission is likely to vary.
MacIver also looked at what the effect of additional network capacity across the B4 and B6 boundaries would have been and found that 'even a modest increase' across these boundaries of 500MW could have resulted in 'reduced curtailment costs by as much as 25% from the £1.65bn total in the 15 month period from the start of 2024 to the end of April 2025' and 'a 2000 MW uplift, in line with delivering the Peterhead Eastern Link project to its original schedule of 2023, then a full 73% of the thermal constraint costs could potentially have been avoided'.
Overall, therefore, the constraint problem is an argument for more grid enhancement, particularly the development of undersea links, rather than less windfarms.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Older windfarms won't increase East Ayrshire community benefit cash says council
Older windfarms won't increase East Ayrshire community benefit cash says council

Daily Record

timean hour ago

  • Daily Record

Older windfarms won't increase East Ayrshire community benefit cash says council

East Ayrshire Council said that other benefits, such as job training support were getting developer support Attempts to increase the amount of money older wind farms give East Ayrshire's communities were met with a firm 'No' according to East Ayrshire Council's head of economic development. However, other moves around training and employment are being backed by developers and energy companies. ‌ The likes of Whitelee Wind Farm, once the biggest in Europe, agreed their level of community benefits before the introduction of guidance from the Scottish Government more than a decade ago. ‌ While there is no legal requirement to offer money to create renewable energy funds, it has become standard practice to offer £5,000 per MW of power produced, as recommended by the Scottish Government. However, this figure was suggested in 2014, with older windfarms often agreeing far less. Whitelee Wind Farm, the largest in the UK and formerly in Europe, agreed to pay just £1,000 per MW, with a subsequent extension application securing an increase to £2,500. Many residents and groups have argued that they should be getting more, especially in areas where there is a significant density of facilities, such as the south end of East Ayrshire. But, David McDowall, Head of Economic Growth at East Ayrshire Council told councillors that many developers were also facing financial struggles. At a meeting of East Ayrshire Cabinet this week, he recommended that no changes be made to the way renewable energy funds are distributed and applied for. ‌ Currently, wind farm funds are limited to communities within 10km of a facility for the first 10 years of operation, with half then being opened up to the whole of East Ayrshire after that period. However, an amendment last year, saw that, before broadening to the whole of the authority, a review to determine whether there was a greater need to maintain the 10km restriction. Whitelee reached that threshold in 2023 and now splits the funding for both the original £1,000 and the subsequent £2,500 for the extension. ‌ Mr McDowall explained: 'A review will be undertaken to assess whether parts of the fund should indeed be made available to a wider spatial area. 'This review will take account of the ongoing need and demand for funding within the 10km buffer and the wider funding landscape beyond the 10km buffer taking cognisance of what funding will be available to the the other relevant communities.' He said the disparity had been discussed with Scottish Power and that they were looking a number of areas to provide 'real opportunities' for communities. ‌ Mr McDowall continued: 'We've recently introduced the Whitelee skills fund which will deliver 30 apprentices and 30 interns along with pre employment training.' However, a push to increase the amount provided by those who had agreed the lower payments per MW has been unsuccessful. He said: 'One of the kind of asks has been, can we get the the the funding updated from the £1,000 or £2,500 to £5,000. ‌ 'We were given a resounding no initially, but discussions are ongoing and there's a proposal to meet between the leaders of East Ayrshire, East Renfrewshire and South Lanarkshire to take forward discussions directly with the Scottish Government. 'It is now common place across Scotland that developers work directly with community groups to agree community benefits rather than paying into the the fund so while the renewable energy fund for East Ayrshire remains a viable option for developers it is now one that's being used far less.' Mr McDowall set out the work undertaken by the Nine CC group, a coalition of nine communities in the south of the authority, who have come to together to make better, more strategic, use of the funds each was receiving from community benefits. ‌ However, he did acknowledge that 'several in farm developers are facing challenging financial circumstances and and obviously issues like grid connections as well and that's requiring them in some industries to reprofile their community benefit commitments.' Councillor Iain Linton, Cabinet member for resources and economy said: 'I think it sums up well where we are just now. 'Obviously we're anticipating the Nine CC fund getting up and running in the the near future and that will take a bit of the strain off the the the sharing of the the Whitelee money. ‌ 'I think they seem to be quite keen in the projects that we've supported in the past.' He also said that Scottish Power had showcased a number of the projects in East Ayrshire and hoped that the company would work with the council to promote and potentially expand the apprentice and intern programme. Mr McDowall responded: 'I think they nearly bit my hand off when we suggested it. ‌ 'So they do want, let's say, the accolades that go along with their funding going towards these apprenticeships. 'We're also working with Ayrshire College and and looking at trying to bring some of the pre-apprenticeship training that is delivered both centrally in Glasgow and Edinburgh towards Ayrshire College. 'Obviously we know that there's a a gap in the renewable sector.' He said that both companies were losing staff but also investing in work in East Ayrshire. He added: 'What we're trying to do is to get a lot of those vacancies filled with residents within East Ayrshire.' Cabinet approved the report.

Celebrating the berry best of Scottish soft fruit
Celebrating the berry best of Scottish soft fruit

Scotsman

time2 hours ago

  • Scotsman

Celebrating the berry best of Scottish soft fruit

From juicy strawberries to plump blueberries, Scotland has a long and rich history of producing some of the world's most succulent soft fruit, with hundreds of farms up and down the country representing a growing and valuable part of our vibrant agricultural landscape. Sign up to our daily newsletter – Regular news stories and round-ups from around Scotland direct to your inbox Sign up Thank you for signing up! Did you know with a Digital Subscription to The Scotsman, you can get unlimited access to the website including our premium content, as well as benefiting from fewer ads, loyalty rewards and much more. Learn More Sorry, there seem to be some issues. Please try again later. Submitting... To champion and strengthen Scotland's nearly £198 million berry sector, Scotland Food & Drink, supported by the Scottish Government, is launching a brand-new celebration of Scottish-grown berries, encouraging shoppers, chefs, retailers and more to learn about the innovative industry, and add more delicious local fruit to their plates. Launched today, Friday, 20 June 2025, by Minister for Agriculture and Connectivity, Jim Fairlie, at an exclusive event at The Royal Highland Show, the four-month Berries of Scotland campaign will spread awareness of the heritage and impact of Scotland's berry sector, which comprises fruit farms of all shapes and sizes spread out from the Highlands all the way down the east coast. Advertisement Hide Ad Advertisement Hide Ad As well as showcasing tasty recipes and fascinating insights into the life of Scottish growers, Berries of Scotland will also bring together a curated map to show berry lovers where they can 'pick their own' at local farms around the country. Alexa King, age 10 and Erica King age 8 According to the Scottish Government's farm census, 1,000 hectares of farmland was dedicated to growing strawberries alone in 2024 – the equivalent of more than 1,200 football pitches – and Scotland has been the home of berry innovation for more than three quarters of a century, thanks to pioneering scientific developments at The James Hutton Institute. Experts from The James Hutton Institute – who attended the Berries of Scotland launch alongside growers from Castleton Farm and Angus Growers – have been breeding and trialing soft fruit for almost 75 years, including raspberries, blackberries, blackcurrants, blueberries, currants, gooseberries, tayberries, and honeyberries. Over the decades, Hutton has developed more than 40 soft fruit varieties, including berries that are resilient to climate change or require low input, reducing reliance on chemical pesticides which makes them more sustainable. With the berry category now worth £197.8m in the Scottish retail market, growing both in value (+14.8%) and volume (+9.8%) in the last 52 weeks to May 2025 versus the previous year, now is the perfect time to celebrate the scientists, farmers and businesses who contribute to Scotland's rich berry heritage. Advertisement Hide Ad Advertisement Hide Ad Iain Baxter, Chief Executive at Scotland Food & Drink, said: 'Scotland's berries are some of the best available anywhere in the world and it's right that we celebrate and champion both them and the people who grow them. Alexa King, age 10 and Erica King age 8 'The Berries of Scotland campaign is about reconnecting consumers with our berry growers and encouraging consumers and buyers to choose Scottish. Research from The Knowledge Bank, our insights team, found that 42% of Scots would like to be able to buy Scottish strawberries and other soft fruits more often, so the demand is there. 'It's a tough environment for many of our Scottish farmers, including berry growers, and it's right that we all work together with the berry sector, as consumers and across our partnership – to support local growers and celebrate Scotland's world-class berries here at home but also in the UK market and key markets overseas.' Jim Fairlie, the Scottish Government's Minister for Agriculture and Connectivityattended the launch event at The Royal Highland Show, and said: 'As someone who grew up in Perthshire I spent all my school summer holidays picking berries, it was something we did as a family and our wider community. There was definitely that thing about us townies getting out into the country and seeing the food that was grown on our doorsteps make its way into our local shops and our houses. Advertisement Hide Ad Advertisement Hide Ad 'That connection between town and country is brilliantly captured by the berry field stories right across Scotland. The launch of this berry campaign is about that heritage, the stories, those connections and a celebration of the history and science that has given Scotland its richly deserved reputation for the superb quality of our berries and the folk who grow and pick them. (L to R) Amanda Brown - Programme Director of Scotland Food & Drink, Jim Fairlie MSP and Eve Morton. 'This celebration is about bringing all of that together so that we have pride in our world class soft fruit sector and demonstrate that by making sure Scottish berries are a staple in our everyday diet, which helps our local economies our natural environment and of course, our own health. 'In collaboration with the many growers, the Scottish Government will help make sure this message goes out far and wide. I want this celebration of Scottish berries launched today to be the beginning of even greater success for the sector and an annual festival we grow, we anticipate and we enjoy as a nation.'

Grangemouth community demand 'less consulting, more action' from Falkirk Council
Grangemouth community demand 'less consulting, more action' from Falkirk Council

Daily Record

time2 hours ago

  • Daily Record

Grangemouth community demand 'less consulting, more action' from Falkirk Council

The draft of a new masterplan for Grangemouth will now go to public consultation but the public want to see changes soon Falkirk Council chiefs say they have heard 'loud and clear' that people in Grangemouth want them to 'stop consulting and start doing'. Members of Falkirk Council's executive agreed this week to launch a consultation on a new 'spatial vision and masterplan' that they hope will guide the transformation of the town over the next 20 years. ‌ Officers say the plan has been developed to tackle some of the key challenges currently affecting local residents, such as the closure of shops and businesses and a lack of high quality, family housing. ‌ But councillors made clear that Grangemouth cannot wait for change and that they want to see 'shovels in the ground' as soon as possible. Falkirk Council's head of growth, Michael McGuinness, told the meeting that he recognised that there have been a number of consultation exercises with the community in the last few years. "In engaging with our community, the feedback we've had is 'stop consulting, start doing'," he said. ‌ "They want to see changes happening in Grangemouth - that's a real concern." But Mr McGuinness said he believes that the draft plan they are now consulting on "will give us a really strong blueprint for allowing that change to happen". The main aims are: ‌ Make the town centre easier to walk and cycle around by improving paths and connections. Develop new housing in and around the town centre to bring more people into the area. Attract new businesses by offering better spaces and supporting mixed-use developments. Improve public spaces with more green areas, seating, and landscaping. As the industry in Grangemouth begins to transition away from fossil fuel-led businesses, the hope is that local people will start to see some of the benefits from an array of investment programmes, strategies and policies that have been introduced. Officers say that a masterplan is vital to pull together and oversee all of the changes that will inevitably affect the town over the next few years. ‌ But councillors questioned officers on the value of another consultation - which will cost £70,000. Director of Place Services, Malcolm Bennie, said the document would be crucial to attract funding for the ambitious plans that are being laid and make sure that everything happens "in a considered, planned way". Conservative councillor James Bundy asked how long it would take to see "shovels in the ground", once the final version of the document is ready. ‌ Mr McGuinness said that some projects are already ready to get underway as part of the Greener Grangemouth programme, which has funding from UK and Scottish Governments through the area's Growth Deal. "This masterplan leads directly to that so we'd expect to see some shovels in the ground next year but what scale is still to be determined." But Mr McGuinness did admit that masterplans were essentially a longterm commitment that can take "decades" to come to fruition and that funding will be a significant factor. ‌ "Our objective is to accelerate that as much as possible and bring forward as much investment into the town centre as we possibly can," he said. "This gives us a tremendous blueprint to do that." Councillors agreed that officers should progress with engagement on the draft masterplan. Once complete, the executive will be asked to approve the final version of the masterplan.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store