
Council leisure centre's swimming pool project takes on water – as costs of eight-year project set to rise to €20m
The pool facility, in Lucan in west Dublin, has been dogged by delays — and the final price of the project is now expected to come in at around €20m.
When it was originally costed in 2017, South Dublin County Council expected the final bill to be around €12.985m.
A project schedule from the time said that once the contract was awarded, it should only take 14 months to construct. Construction got under way in May 2019, but the Covid pandemic, severe weather and a variety of other issues have seen the project go way beyond schedule, with completion dates pushed back at least a dozen times.
A series of updates to queries from councillors, released under the Freedom of Information Act, show how the opening day for the swimming pool and leisure centre kept shifting.
In late 2020, a local representative was told the handover date had been meant to be February 2021, but that this had been moved back to June 2021.
I'm satisfied the council has done everything in their power to expedite the project
An update said: 'The project has been significantly delayed due firstly to poor weather conditions in the early part of 2020 and then the enforced closure of the site for a number of weeks during the Covid national lockdown.'
In late 2021, another councillor was given an update, saying the completion date was now likely to be in April or May of 2022. That date then got pushed to August 2022, though even that proved hopelessly optimistic.
Local Sinn Féin TD Eoin Ó Broin asked in January 2023 when the pool was likely to be open and was told that June 2023 was now the target, and that this was 'very disappointing' to the council.
A letter to him said: 'As you will be aware, the project has been impacted significantly by various construction sector challenges.'
By last year, the project still wasn't complete — and in August 2024 councillors were told that the local authority was still working with the contractor to 'agree a revised programme'.
ADVERTISEMENT
In February of this year, Mr Ó Broin again sought an update and was told more resources were being provided to 'expedite project completion'.
A letter to him said: 'The council understands both the importance of this project to the local community and the frustration that the delays have caused.'
An update to councillors in January said: 'Completion of the project continues to be challenging, primarily; as noted previously, due to contractor resources and sub-contractor availability.
'We are continuing to intensively manage the project and main contractor to achieve the earliest possible completion dates.'
South Dublin County Council had originally refused to provide details of how much they had so far spent on the project.
However, following an appeal under FoI laws, they disclosed that costs so far were €17.87m, which included €15.7m in payments to the main contractor.
A further €702,000 was paid to an architectural firm while fees of €33,919 were paid to Irish Water and just over €20,000 to ESB Networks.
That is unlikely to be the final bill, however, and local representatives have been warned that an overall cost of around €20m can be expected.
Parts of the facility are in use, but the main swimming pool has yet to be opened to the public.
'The ongoing delays have been enormously frustrating, but I'm satisfied that the council has done everything in their power to expedite the project,' said Mr Ó Broin.
'What I would say is the way in which procurement rules are imposed on local bodies is far too rigid. It means that when something goes wrong, it's very difficult to resolve those issues in a timely manner.
'The council has done a large number of capital projects, including housing and community facilities, and none of those have had the kind of delays that this centre has.'
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Irish Examiner
20 hours ago
- Irish Examiner
Housing commencements fall to 10-year low for the month of May
Home building has hit another dismal low-point, with new data confirming that last month's housing commencement figures were worst seen in May for 10 years. Last month, housing commencements - the number of new residential projects that have officially begun construction - were less than half the number of May last year. With the exception of May 2020, when covid-19 shut the construction sector, the May 2025 figure is the worst since 2015, with just 1,024 homes getting underway. Department of Housing statistics show that, in the first five months of the year, just under 5,000 homes have been officially commenced in Ireland, set against an initial government target to deliver 41,000 homes. Minister for housing James Browne has said this target is now 'not realistic' and that 'we're coming off a much lower base from last year than was expected'. The latest figures come as thousands of people are set to participate in a Raise the Roof protest at the National Monument in Cork City on Saturday, with trade unions and opposition parties urging the public to turn out to highlight the impact of the housing crisis on society. A commencement is a formal notice a developer must lodge to notify that that construction or a significant alteration to a building is beginning. There is no penalty if the work is never undertaken. Although it had been seen as an indication of how many homes would be built in the short-to-medium term, doubts have been cast on the reliability of these statistics, given a flood of notices were lodged at times last year prior to the expiry of Government incentives. Nevertheless, the fall in commencements to levels not seen since before the pandemic is viewed as a negative indicator of housing supply. The Central Bank has forecast that just 32,500 new homes will be built this year. Separately, the Central Statistics Office (CSO) said on Friday that the volume of building in the residential sector fell 10.6% in the first quarter of 2025 compared to the same time last year. Sinn Féin's housing spokesperson Eoin Ó Broin said the drop in housing commencements 'isn't surprising news'. Minister for housing James Browne has said he is committed to enacting a 'step change' in the housing department and will clear 'the dead wood out of the way so that homes can get delivered'. Photo: Leah Farrell/© 'It's why the Central Bank have revised their estimates and appears the Government will miss their targets not just this year but in 2026 and 2027 as well," he said. 'There's still an ongoing delay in the approval of vital social and affordable housing projects, and I suspect this accounts for a significant proportion of the shortfall in commencements. There is far too much bureaucracy and red tape.' Minister Browne has said he is committed to enacting a 'step change' in the housing department and will clear 'the dead wood out of the way so that homes can get delivered'. A spokesperson for the Department of Housing said the dip in commencement notices in the early months of 2025 "is not unexpected given the extraordinary number lodged in the last two years in response to Government measures to accelerate supply, principally through the Development Levy Waiver and Water Connection Rebate – notices were lodged for almost 102,000 new homes in 2023 and 2024 combined". The lower number of notices lodged over the first five months of 2025 likely reflects a shift in focus in the construction sector to progressing the homes already in the pipeline, they added. "Feedback from the sector suggests significantly increased activity on sites around the country – the Department of Housing is working with local authorities to gauge the level of activity currently underway in respect of the notices received in 2023 and 2024. Our initial analysis suggests almost 90% of the associated sites have been activated so far, auguring well for the completion of many of these units in 2025 and 2026."


Irish Independent
a day ago
- Irish Independent
‘Lit up like a Christmas tree' – Calls for vape shop restrictions in south Dublin
The motion, brought by Sinn Féin councillor William Casey, said that the 'proliferation of vape shops" in the centre of villages and near schools was an 'undesirable development' that should be tackled with a ban. During the Clondalkin, Newcastle, Rathcoole, Saggart and Brittas Area Committee meeting, Mr Casey said the growing number of vape shops were targeted at school-going children. "It's our children that they're aiming at. They're no longer aiming them at the adults who have taken to vaping because they couldn't get off cigarettes, they're being aimed directly as a first-choice product for children,' he said. Other councillors agreed, with Independent Francis Timmins saying that he wasn't only worried about the number of vape shops, but also their lengthy opening hours. "At 11 or 12 at night, a vape shop open in the middle of Clondalkin is a bit bizarre to me. I don't get it, I don't understand it,' he said. "I'm concerned about the opening times, I'm concerned about the litter of the vapes around the shops, we've had an issue with that, we've had an issue with signage, particularly the signage around the ACA (architectural conservation area). 'One of the vape shops is lit up like a Christmas tree, and it's lit up from early morning to late at night, and it's just diabolical to be quite honest with you for a heritage village,' he added. Mr Timmins said he thought there were four or five such shops in Clondalkin village, with several selling vapes and sweets alongside one another, a tactic that 'really worries' him. Independent Ireland councillor Linda de Courcy said 'nothing good is going to come' from the number of vape shops now open in Clondalkin, and said she had seen children buying sweets in them. A response from SDCC given to Mr Casey said that no policy on vape shops existed in the County Development Plan 2022-2028. ADVERTISEMENT Even if it were in the plan, the council said it would have a 'very limited effect' on the ground because shops benefit from significant exemptions under the Planning and Development Act 2001. "This means a wide range of commercial and retail premises in our villages and communities could be changed to vape shops without planning permission. This makes the planning system unsuited to the management of vape shops.'


Irish Independent
2 days ago
- Irish Independent
Survey records fall in hotel rooms and student places built last year
An analysis of the development landscape in Ireland, it found just 895 purpose-built student bedspaces were built, down from 1,630 the previous year, and the lowest level since Deloitte started the data series in 2016. In the hotels sector, 1,360 new rooms were added, a decrease of 17pc annually. Among the arrivals were the Ruby Molly, Leinster Hotel and NYX Hotel in Dublin, plus The Moxy and a Premier Inn in Cork, the Radisson Red in Galway and Ravenport Resort in Wexford. At the end of the first quarter of this year, 4,060 rooms were under construction, mostly in the capital city. Several large hotel projects commenced construction, including at Dublin Airport, where 410 rooms are being delivered by Accor and The Arora Group. That hotel, which is due to open at the end of next year, will operate as the first Sofitel Hotel in Ireland. Overall, 1,410 new hotel rooms are due to be added this year. These will include the recently reopened Mercantile Hotel in Dublin, with 105 rooms, and the CitizenM, St Patrick's Hotel, also in Dublin, with 245. The Point A Hotel in the Liberties will provide 95. A further 2,510 hotel beds are due to be delivered in 2026. In terms of student accommodation, the Crane Survey says all the delivery was in the country's two biggest cities, with 620 at Novel Bottleworks, on the former Coca-Cola bottle factory on the Carrigrohane Road, Cork and 190 at The Residence in Prussia Street, Dublin. The remainder were in Blackhall Place, Stoneybatter, where a refurbishment added an additional 80 beds. At the end of Q1 this year, there were 1,400 student places under construction across six schemes in Galway, Dublin, Limerick and Kildare. This stems from government funding announced last year, in which €100m was allocated to deliver accommodation at UCD, DCU and Maynooth, where 115 bedspaces are under construction and due to be delivered for the 2025/2026 academic year. Galway should get the largest increase in student accommodation, with construction under way across three schemes totalling 840 spaces. This would give a 16pc boost to the city's stock. The Deloitte survey points out there were 206,365 full-time students enrolled in third-level institutions in Ireland in the last academic year, a growth of 9pc since before the Covid pandemic. While the number of domestic students increased only slightly, the number of international students is up by 33pc during the same period. They account for almost one in five of the student population. 'In the medium term, enrolments in third-level students in Ireland are expected to peak at 240,000 full-time students in 2030, due to factors including domestic demographics and increased international enrolments,' the report says.