Bombay HC dismisses 2 PILs against Lloyds Metals
The Nagpur bench of the Bombay High Court has dismissed two public interest litigations (PILs) challenging the grant of permission to the capacity expansion of the Surjagarh iron ore mines of Lloyds Metals and Energy Ltd (LMEL) in Gadchiroli.
While the PILs were quashed on May 9, the order copy was uploaded on June 19. The high court found both the PILs to be without merit.
The PILs filed by Samarjeet Chatterjee, a mining contractor from Raipur, Chhattisgarh, alleged that the process of environmental clearance (EC) granted by the Union Ministry of Environment, Forest and Climate Change (MoEF&CC) for expansion of mining capacity from 3 million tonnes per annum (MTPA) to 10 MTPA and further Terms of Reference (ToR) towards expansion from 10 MTPA to 26 MTPA were 'illegal'.
The division bench comprising Justices Nitin Sambre and Abhay Mantri observed that 'the complete procedure based on the ToR is followed,' and found that both the PILs were devoid of merit.
The petitioner also alleged that the public hearing was conducted at a place far away from the project site. The court observed, 'The fact remains that in compliance with the Environmental Impact Assessment notification dated May 29, 2006, as amended on December 01, 2009, a public hearing was conducted at the [Gadchiroli] District Headquarters, which is perhaps properly secured in view of the Naxal menace.'
The counsel for the respondents submitted that the petitioner has no locus standi, and since he never attended the public hearing conducted by the collector at the district headquarters, he lost the opportunity to question the legality of the orders impugned in these PILs.
Further, the counsel submitted that the initial EC was granted in 2005-06 after the hearing conducted by the collector at the very same place, and the said hearing was never questioned by the petitioner for the last 20 years.
The counsel added that the EC for 10 MTPA was issued by the MoEF&CC under strict compliance with and adherence to the provisions of the EIA Notification dated May 29, 2006 and the SOP issued by the ministry.
Though the public hearing was conducted at Gadchiroli district headquarters on the recommendation of the Police Department as the project site fell within the Naxal-affected area, all the locals were given due opportunity to present their say on the mining project, the court observed.
The high court further stated that the courts should be sensitive and careful to the fact that the petitioner should not be allowed to indulge in making wild and reckless allegations. Since the petitioner stated that his annual income was Rs 4-5 lakh, the court observed, 'We fail to understand as to what is the source of expenses incurred by the petitioner as there is a serious doubt about his bona fides also'.
With due observations, the high court dismissed both the PILs without costs.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
26 minutes ago
- Time of India
Foundation stone for integrated steel plant soon at Konseri
Nagpur: The high court's decision to dismiss the public interest litigation (PIL) against the environmental clearance (EC) granted for Lloyds Metals and Energy Limited's (LMEL) iron ore mines clears the way for sourcing adequate raw material for the company's steel project at Konseri village in the same district, said managing director B Prabhakaran. The company will soon hold a foundation-laying event for its integrated steel plant at the site. This will be a facility producing a whole gamut of steel products. With a capacity of 4.5 million tonnes, it will be the biggest in Vidarbha, he said. The first phase pellet-making plant at the same site is also expected to become operational in the coming days. It has a capacity of 4 million tones. The slurry pipeline too will become operational along with it. The pipeline, which will transport iron ore in slurry form, will reduce the dependence on roads, he said. The second phase of the pellet making plant with a similar capacity is expected to get operational by December, said Prabhakaran. An integrated steel plant is akin to the facilities of Steel Authority of India Limited (SAIL) in Bhilai or Tata in Jamshedpur. Iron ore is the basic raw material for steel making. The clearance to expand the mining operation ensures a steady supply of ore, he said. The plant at Konseri is located around 100km away from the mines at Surjagarh. Currently, a direct reduced iron (DRI) plant is operational at the site.


The Hindu
2 hours ago
- The Hindu
Foremost priority is to ensure forest lease holders receive entitlements: Chhattisgarh CM
Even as joint security forces continue operations across several States to meet Union Home Minister Amit Shah's resolve on a 'Naxal-Mukt Bharat' by March 2026, Chhattisgarh Chief Minister Vishnu Deo Sai said that his government's 'foremost priority is to ensure that every forest land lease holding family received their rightful entitlements'. An official told The Hindu that this flows from the government's thinking that 'there is a clear correlation between FRA (Forest Rights Act) enforcement and reduced Naxal activity'. The Forest Rights Act, 2006, recognises and vests forest rights with Scheduled Tribes and forest-dwelling communities. 'The approach is holistic, combining rights recognition, economic empowerment, and security measures to strengthen tribal self-governance and counter extremism,' the official said, adding, 'Reports from the ground indicate that in districts with robust FRA implementation, Naxal recruitment has dropped. Gram Sabhas now resolve many local disputes without Maoist interference, showcasing the positive impact of tribal self-governance.' In response to questions on FRA implementation in the Bharatiya Janata Party (BJP)-ruled State, the Chief Minister told The Hindu that his government had streamlined the 'fauti naamantaran' — the process of transferring ownership of land after the death of the leaseholder as well, 'so that legal heirs face no hurdles'. 'By simplifying and streamlining the process of 'fauti naamantaran', we have made sure that after the demise of a lease holder, their legal heirs face no hurdles in claiming their rightful ownership,' Mr. Sai said. Also Read | Forest rights concerns could influence electoral results in nearly a third of constituencies, says study 'With their names now officially recorded, they not only become the lawful owners of the land but also gain easier access to various government schemes and benefits,' he said, adding that the streamlined process had 'provided forest rights holders with a new foundation of economic, social, and familial security'. 'It has boosted the confidence of our rural and tribal communities and strengthened their trust in the government,' the CM said. This thinking is also reflected in the State government's 2025 policy for the surrender and rehabilitation of Naxals and victims of violence, which has provisions to give land titles, financial aid, and livelihood assistance to surrendered Naxals and victims, the State government official further said. 'By recognising land and forest rights, the government has addressed long-standing tribal grievances, which Naxals previously exploited for recruitment. In conflict-prone areas such as Abujhmad, granting habitat rights has strengthened trust between tribal communities and the administration,' the official said. The State government has especially focused on granting community rights titles under the FRA, data showed, with officials adding that Chhattisgarh had been granted over 4,300 Community Forest Resource Rights (CFRR) titles in the past 1.5 years. Public data from FRA implementation further showed that while, as of 2018, individual rights titles under the FRA were more than twice the number of community titles granted, the dataset for the last one year showed community titles outnumbering individual titles. This comes in the backdrop of the Union government trying to give a fresh push to the implementation of the FRA across the country by funding the setting up of over 300 FRA cells to facilitate the law's implementation. This effort is the first time the Union government is setting up mechanisms to help in the implementation of the law, which was hitherto largely in the domain of State governments.


India Today
3 hours ago
- India Today
Rahul Gandhi accuses poll body for 'deleting evidence', calls polls 'fixed match'
Congress leader Rahul Gandhi on Saturday accused the Election Commission (EC) of "deleting evidence" instead of giving answers, after the poll body directed its officers to destroy CCTV, webcast, and video footage of elections 45 days after polling, if the results are not challenged in a post on X, Gandhi said, 'Voter list? Will not give a machine-readable format. CCTV footage? Hidden by changing the law. Election photos and videos? Now they will be deleted in 45 days, not 1 year. The one who was supposed to provide answers – is the one deleting the evidence.'advertisementHe added, 'It is clear that the match is fixed. And a fixed election is poison for democracy.' The Congress leader's statement came after the EC instructed its state poll officers to destroy all such data after 45 days unless a legal challenge to the result is filed. Gandhi has been demanding voter lists, polling data, and video footage, particularly in connection with alleged irregularities in the Maharashtra Assembly a letter dated May 30 to state Chief Electoral Officers, the EC said it had been using photography, videography, CCTV, and webcasting to record various stages of the election process. These recordings are not required by electoral law but serve as internal management the EC said that it has now reviewed the practice due to the "recent misuse of this content by non-contestants to spread misinformation and malicious narratives on social media by selective and out-of-context use of such content, which will not lead to any legal outcome."advertisement"Sharing of the footage, which would enable easy identification of the electors by any group or an individual, would leave both the elector who has voted and the elector who has not voted vulnerable to pressure, discrimination and intimidation by anti-social elements," Election Commission sources EC also said that making public CCTV footage from polling booths would violate the legal provisions of the Representation of the People Act and the directions of the Supreme Court of December last year, the government tweaked an election rule to prevent public inspection of certain electronic documents such as CCTV cameras and webcasting footage as well as video recordings of candidates to prevent their to the new instructions, if no election petition is filed within 45 days, the footage and images can be destroyed. An election petition must be filed in the relevant high court within 45 days of result clarified that if a petition is filed, the data is preserved and made available to the court when InMust Watch IN THIS STORY#Rahul Gandhi