Road ministry cites 'critical lapses', expands oversight on NH works implemented by states

Road ministry cites 'critical lapses', expands oversight on NH works implemented by states

The Hindu20-05-2025

The Ministry of Road Transport and Highways (MoRTH) has issued directives to expand oversight of regional officers on National Highway works implemented by state public works departments and road construction departments.
In a circular, the Highways Ministry said critical lapses have occurred due to a lack of due diligence in several projects pertaining to NH works implemented by state public works departments and road construction departments (PWDs/RCDs).
According to the circular, the ministry's regional officers (ROs) are sometimes neither consulted nor involved during the bidding process or while defending contractual disputes before arbitration tribunals or courts, wherein such disputes are dealt with mechanically often without adequately safeguarding the interests of the Central Government or aligning with the ministry's position.
'In order to prevent recurrence of such issues and to ensure greater due diligence in the bidding process... For all NH project works (including those costing less than ₹100 crore but excluding maintenance works), the bid documents, especially the Schedules prepared by State PWDs/RCDs shall be scrutinised by the concerned RO prior to the invitation of bids,' it said.
As per the circular, ROs shall examine the bid documents for any anomalies, inconsistencies, or deficiencies, particularly with respect to quantities, specifications, and contract conditions and also conditions imposed by the appraising and approving authority.
'It is imperative that ROs remain actively involved in all legal contractual disputes adjudication processes including arbitration matters related to NH works.
'State PWDs/RCDs shall not pursue such matters independently without consultation with ROs,' the circular said.
It also said all replies, statements of defence, and written submissions intended for courts / arbitrations shall be vetted by the ROs and returned after scrutiny with comments or amendments, as the case may be, before submission within a period of 15 days failing which, the replies, statements or submissions may be deemed cleared.
'ROs shall ensure that these submissions are aligned with contractual terms or Ministry policy and protect the interests of the Central Government,' the circular said.
Where necessary, it said, ROs may engage legal experts from NHAI-empanelled law firms for advice and support.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

NH 48 highway deaths & traffic: Thane MLA meets NHAI officials over Rs 600 crore project delays!
NH 48 highway deaths & traffic: Thane MLA meets NHAI officials over Rs 600 crore project delays!

Time of India

time9 hours ago

  • Time of India

NH 48 highway deaths & traffic: Thane MLA meets NHAI officials over Rs 600 crore project delays!

VASAI: Shiv Sena Boisar MLA Vilas Tare conducted a meet with NHAI officials and officials from the traffic department of Palghar and Mira Bhayandar Vasai Virar commissionerate to solve the issue of daily traffic jams on the Mumbai Ahmedabad national highway (NH48) even after spending 600 crores on the white topping. Representatives from the contractor Nirmal Build Infra were also present who are completing this white topping project, along with Suhas Chitnis, Project Director NHAI, the Highway police and the highway activists. For the last couple of days NH 48 witnessed traffic which was around 7/8 kilometers long with vehicle traffic on the wrong side on both the lanes. Highway deaths during this white topping project allegedly due to the negligence of the contractor and lack of safety measures on the site were also discussed. The NHAI was asked as to why there should be no legal action taken against them and the contractor for the highway deaths, confirmed a source. This is one of the important routes which connects Mumbai to the Northern states like Gujarat, Madhya Pradesh, Delhi etc. In Palghar, this route connects one of the biggest MIDC which is the Boisar Tarapur MIDC and often loaded trucks get stuck in hours of traffic further causing delays and damages to the respective company. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Buy Brass Idols - Handmade Brass Statues for Home & Gifting Luxeartisanship Buy Now Undo One of the chronic spots is the construction of the Sativili flyover in Palghar, the service road of which is potholed and has witnessed several fatal incidents. We have given them an ultimatum of 15 days to complete the service roads else legal action would be taken for the delays, said Boisar MLA Vilas Tare. He also demanded 60 traffic wardens from NHAI, which have been missing in action when required, at the earliest. Highway activist Harbans Singh said that this project of 600 crores was given so that we could travel smoothly and lives could be saved but at Sativali spot we have lost around 14 lives in recent time, so what have we achieved, he questioned. Contractor spotted cementing in heavy rains On Thursday, when Palghar district was receiving heavy rainfall, a citizen captured a video of the contractor pouring cement from a ready mix concrete (RMC) truck on the site where they were constructing a nullah slab. The entire exercise was futile as the video shows the concrete being literally poured in water. Activists questioned this act adn this exposed the quality of work in progress. This happened on Thursday at Nandgaon which is five kilometers from Manor naka towards Gujarat.

Government may slow down declaring more state highways as National Highways
Government may slow down declaring more state highways as National Highways

Time of India

time17 hours ago

  • Time of India

Government may slow down declaring more state highways as National Highways

Representative Image NEW DELHI: In a major policy change, the Centre is preparing a model to provide financial assistance to state govts for one-time improvement of state highways rather than declaring more of these as NHs. The road transport ministry will instead focus on building more new greenfield highways and expressways. This comes after PM Narendra Modi's direction to the ministry to come up with a model by July end for the purpose. State govts will maintain the upgraded state highways. TOI has learnt that in the last infrastructure review meeting, Modi had asked the ministry to come up with innovative models for supporting state highway projects and connecting non-major ports under state govts. This change in approach gains importance considering that in the last 11 years, govt has notified conversion of 55,000 km of state highways to NHs and now, the total length of NHs stands at 1.46 lakh km. This has been highlighted as one of the biggest achievements of govt. Sources said that after expanding the NH network, now there is a need to focus more on widening them and maintaining them. Data shows that till March, India has more than 63 lakh km of road network.

Shifting of high tension towers delay Vijayawada West bypass road works
Shifting of high tension towers delay Vijayawada West bypass road works

Time of India

time20 hours ago

  • Time of India

Shifting of high tension towers delay Vijayawada West bypass road works

Vijayawada: The full-fledged completion of the Vijayawada West bypass road is likely to be pushed to the end of the year or early next year. The shifting of the High Tension (HT) line towers spanning approximately 520 metre on the package-III stretch from Gannavaram to Gollapudi is expected to take another three months. Tired of too many ads? go ad free now The 47.8 km Vijayawada Western Bypass, being constructed under Bharat Mala Pariyojana, starts from Chinna Avutapalli in Gannavaram and culminates at Chinna Kakani on the outskirts of Mangalagiri. It will bypass the vehicular traffic going towards Chennai and Hyderabad from Visakhapatnam and vice versa, as vehicles could bypass without entering Vijayawada city, significantly reducing the traffic burden on the city. While the Bharat Mala Pariyojana road infrastructure project was divided into four packages, the works on the first two packages—package-I from Gundugolanu to Kalaparru and package-II from Kalaparru to Chinna Avutapalli, which includes the six-laning of the highway road—were completed. The completion of package-III and package-IV from Chinna Avutapalli to Gollapudi and Gollapudi to Chinna Kakani has hit multiple roadblocks, resulting in the delay of the inauguration of the Vijayawada Western Bypass. "Originally, the bypass road was to be completed by March 2025. However, govt objected to the bypass not having road cuttings to the roads within the Amaravati capital, which led to its delay for some time. Following this, the bypass road project hit the HT lines roadblock, wherein HT line towers near Nunna stretching nearly 1.2 km had to be shifted due to their positioning right within the project alignment," an NHAI official said. Tired of too many ads? go ad free now Earlier, chief minister N Chandrababu Naidu, during a review meeting, directed the officials to complete the bypass road works by June and to allow vehicles to ply along the bypass to ease the traffic congestion. "We missed the June deadline given by the chief minister as the problem to shift HT line towers in around a 520-metre stretch is still pending resolution. We are awaiting the shifting of the HT line towers, which is expected to take another three months, thus to fast-track the remaining works, which would be completed in a short span," the NHAI official said.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store