BMC floats ₹2,368-crore tender to clear Deonar landfill waste amid public scrutiny
Mumbai: The Brihanmumbai Municipal Corporation (BMC) on Wednesday issued a massive ₹2,368-crore tender for the remediation of legacy waste piled up to the equivalent of 12 storeys at the Deonar dumping ground, infamously referred to as Mount Garbage.
Touted as one of the largest tenders in recent years for solid waste management, the initiative aims to address decades of accumulated waste at one of the city's oldest dumping grounds.
The proposed project involves the bioremediation of 18.5 million tonnes of legacy waste and the disposal of excavated, processed, and segregated materials. According to the BMC, this will result in the reclamation of approximately 110 hectares (~272 acres) of land at the Deonar site.
The contract is set for a three-year period, inclusive of mobilisation and the monsoon season. Work is slated to begin upon the issuance of a letter of acceptance or a service order, whichever comes first.
The BMC's move assumes significance considering the Deonar dumping ground is slated to play a significant role in the redevelopment of Dharavi, one of Asia's largest slums.
In October 2024, the Maharashtra cabinet approved the transfer of 124 acres of the 311-acre Deonar landfill to the Adani Group-led Dharavi Redevelopment Project (DRP) for constructing rental homes for residents deemed ineligible for free housing within Dharavi. The decision sparked controversy due to environmental and health concerns, as the site remains an active landfill that emits toxic gases.
Activists and civil society groups have raised red flags about the BMC tender's timing and financial implications, despite the environmental promise of bioremediation. The Watchdog Foundation, an NGO, has openly criticised the move, citing concerns over the use of public funds to subsidise a private redevelopment project.
'While we acknowledge that bioremediation is an environmentally friendly process, we are perplexed by the timing and financial implications of this tender,' said advocate Godfrey Pimenta of the Watchdog Foundation.
'If a significant portion of the Deonar dumping ground has already been allotted to a private entity, why is the BMC spending ₹2,368 crore of taxpayers' money on its bioremediation?' he added.
The foundation has called for the immediate suspension of the tender, urging a comprehensive review of the project and an independent inquiry into the decision-making process.
'We believe that transparency and accountability are paramount, especially when significant public funds are involved,' said Pimenta. 'The citizens of Mumbai deserve clarity on how their money is being utilised, and whether such expenditures serve the public interest.'
Kiran Dighavkar, deputy municipal commissioner (solid waste management), defended the BMC's move, saying there is a significant amount of legacy waste at the Mulund and Deonar dumping grounds that needs to be removed.
'Mulund alone has around 60 lakh (6 million) tonnes of waste, while Deonar holds nearly 2 crore (20 million) tonnes, piled up to the equivalent of 12 storeys and spread over approximately 110 hectares. Regardless of the Dharavi Redevelopment Project, we are obligated to remove this legacy waste,' said Dighavkar.
'Work at the Mulund dumping ground has been ongoing for six years, and we expect to reclaim nearly 60 acres of land there. Now, the focus has shifted to Deonar, where biomining operations are underway. In the meantime, the DRP has progressed, and the state government has requested that the land originally allotted to us in the 1930s be returned in its current condition. It is our responsibility to clean the site and hand it back, in line with the state government's directives,' he added.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
9 hours ago
- Time of India
Metro, rail and bus hubs in MMRDA's plan for Dharavi, Infra News, ET Infra
Advt Advt By Join the community of 2M+ industry professionals. Subscribe to Newsletter to get latest insights & analysis in your inbox. Get updates on your preferred social platform Follow us for the latest news, insider access to events and more. Mumbai: Mumbai Metropolitan Region Development Authority (MMRDA) was appointed as the nodal agency to plan and develop a Multimodal Transport Hub (MMTH) as part of Dharavi Redevelopment Project (DRP). This move was formalised through a govt resolution issued on June 18, following a high-level meeting chaired by the chief minister on Apr proposed hub aims to bring Metro, suburban rail, buses, and non-motorised transport under one umbrella, offering seamless integration for commuters passing through Dharavi — one of the city's most densely populated and poorly connected neighbourhoods. MMRDA was asked to coordinate with Dharavi Redevelopment Authority and all transport bodies concerned to draft a comprehensive layout and implementation will also ensure easy access to Sion station on Central Railway and Mahim station on Western Railway, both located on either side of the redevelopment part of the larger redevelopment vision, a second Metro station is being considered for Dharavi. Besides the under-construction Metro Line 3 (Colaba-Bandra-Seepz), the area is expected to be connected by an extension of Metro Line 11 (Wadala-CSMT). Sources said this line is likely to be extended westward from Wadala to link with Metro Line 3 at Dharavi, enabling a crucial east-west and north-south interchange point. The Rs 16,000 crore Metro Line 11 project, implemented by the Mumbai Metro Rail Corporation Ltd (MMRCL), includes two proposed stations—one near Sion and another within support the bus component of the hub, DRP plans to build a modern depot for BEST. In return, 12 acres of land currently occupied by the Dharavi and Kalakilla bus depots in Sion East—which jointly accommodate around 300 buses and house key offices of the transport and power supply divisions—will be handed over for said the plan goes beyond Metro integration, with infrastructure for feeder buses, walking, and cycling for last-mile connectivity. "The intent is to build a future-ready mobility hub, not just a station," said an official. Feeder routes are being drawn up to link nearby areas with Metro and rail stations.


Time of India
17 hours ago
- Time of India
Metro, rail and bus hubs in MMRDA's plan for Dharavi
Mumbai: Mumbai Metropolitan Region Development Authority (MMRDA) was appointed as the nodal agency to plan and develop a Multimodal Transport Hub (MMTH) as part of Dharavi Redevelopment Project (DRP). This move was formalised through a govt resolution issued on June 18, following a high-level meeting chaired by the chief minister on Apr 21. The proposed hub aims to bring Metro, suburban rail, buses, and non-motorised transport under one umbrella, offering seamless integration for commuters passing through Dharavi — one of the city's most densely populated and poorly connected neighbourhoods. MMRDA was asked to coordinate with Dharavi Redevelopment Authority and all transport bodies concerned to draft a comprehensive layout and implementation plan. MMTH will also ensure easy access to Sion station on Central Railway and Mahim station on Western Railway, both located on either side of the redevelopment zone. As part of the larger redevelopment vision, a second Metro station is being considered for Dharavi. Besides the under-construction Metro Line 3 (Colaba-Bandra-Seepz), the area is expected to be connected by an extension of Metro Line 11 (Wadala-CSMT). Sources said this line is likely to be extended westward from Wadala to link with Metro Line 3 at Dharavi, enabling a crucial east-west and north-south interchange point. The Rs 16,000 crore Metro Line 11 project, implemented by the Mumbai Metro Rail Corporation Ltd (MMRCL), includes two proposed stations—one near Sion and another within Dharavi. To support the bus component of the hub, DRP plans to build a modern depot for BEST. In return, 12 acres of land currently occupied by the Dharavi and Kalakilla bus depots in Sion East—which jointly accommodate around 300 buses and house key offices of the transport and power supply divisions—will be handed over for MMTH. Officials said the plan goes beyond Metro integration, with infrastructure for feeder buses, walking, and cycling for last-mile connectivity. "The intent is to build a future-ready mobility hub, not just a station," said an official. Feeder routes are being drawn up to link nearby areas with Metro and rail stations.


Time of India
20 hours ago
- Time of India
Plan to allot houses on priority to urban poor lodged in transit houses
1 2 3 Bhubaneswar: To ensure timely allotment of units to urban poor in affordable housing projects, the Bhubaneswar Development Authority (BDA) and Bhubaneswar Municipal Corporation (BMC) have decided to collaborate with a focus on people staying in different transit houses in the city. A high-level meeting of the housing and urban development department was convened recently, where the decision was taken to ensure allotment of houses on a priority basis for beneficiaries staying in transit houses. BMC personnel shifted several people to the transit houses while BDA constructed affordable housing for them. Following the meeting, the department issued a notification mentioning the steps to be taken by the BMC and BDA to shift the beneficiaries to pucca houses, beginning with the transit house at Niladri Vihar, where 639 families are staying. BMC has been asked to shift these families to the affordable housing project in Chandrasekharpur. "A detailed enumeration is to be conducted by the joint enumeration team to be constituted from both the BMC and BDA to ascertain the exact number of families residing in the transit houses. The eligibility of the family for allotment of the dwelling units is to be ascertained as per the revised eligibility criteria of BMC," the notification read. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like One of the Most Successful Investors of All Time, Warren Buffett, Recommends: 5 Books for Turning... Blinkist: Warren Buffett's Reading List Click Here Undo The department has also asked both civic agencies to facilitate bank loans for the the beneficiaries. "Some families who have deposited part of the beneficiary contribution and are unable to pay the balance amount will be facilitated to avail bank loans. Based on the eligibility for allotment of dwelling units, a demand notice will be issued in their favour," the notification added. Officials also discussed the construction of the second phase of Shantipalli housing project at Satya Nagar. BDA has been asked to take immediate steps for the eviction of encroachments for the construction of the second phase of the project. The first phase of the project has been completed and houses were handed over to the beneficiaries, sources said.