Petroleum Minister inspects LNG infrastructure in Ain Sokhna ahead of summer demand surge

Petroleum Minister inspects LNG infrastructure in Ain Sokhna ahead of summer demand surge

Minister of Petroleum and Mineral Resources Karim Badawy conducted an inspection tour at Ain Sokhna's SUMED and Sonker ports to review infrastructure readiness for receiving additional Floating Storage and Regasification Units (FSRUs) as part of Egypt's summer energy preparedness plan.
Joined by senior petroleum sector officials, Badawy assessed progress on critical projects supporting the import, regasification, and delivery of liquefied natural gas (LNG) into the national gas grid—an essential step in securing fuel for electricity generation during peak summer months.
The minister began his visit at the marine berth in SUMED port, where the FSRU Hoegh Galleon is currently docked. He observed the vessel's ongoing operations, which include LNG unloading, regasification, and injection into the national grid.
Badawy also inspected the newly completed second marine berth at SUMED, which has been under development since September of last year. Designed to host an additional regasification vessel, the berth is now 100% complete, with trial operations underway ahead of the FSRU's arrival. The project is considered a key component of Egypt's national strategy to enhance natural gas infrastructure.
The tour continued at Sonker port, where the minister reviewed progress on laying horizontal pipelines that will connect a future regasification vessel to the national grid. He also examined the installation of a 36-inch, 17-kilometer gas import pipeline, which will serve as a vital conduit for the third FSRU expected to dock at the site.
During the visit, Badawy received detailed briefings from Yasser Salah, Chairperson of GASCO, and Walid Lotfy, Chairperson of Petrojet. The two entities are collaborating on LNG infrastructure projects at both SUMED and Sonker ports.
GASCO led the engineering and technical studies, sourced materials and equipment, and provided project management. Petrojet executed the construction, which includes two high-capacity marine and onshore pipelines, and the installation of two massive 16-inch-diameter loading arms—among the largest globally—to ensure efficient regasified gas handling.
The SUMED project has been finalized and is fully operational in anticipation of the second FSRU's arrival. Meanwhile, construction continues at Sonker port to ready the infrastructure for the docking of a third regasification vessel.
These developments are part of a broader national effort to reinforce Egypt's natural gas supply chain and ensure stable electricity production during the high-demand summer period.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Madbouly reviews LNG infrastructure readiness at Ain Sokhna Port
Madbouly reviews LNG infrastructure readiness at Ain Sokhna Port

Daily News Egypt

time2 hours ago

  • Daily News Egypt

Madbouly reviews LNG infrastructure readiness at Ain Sokhna Port

Prime Minister Mostafa Madbouly visited Ain Sokhna Port on Saturday to inspect the liquefied natural gas (LNG) regasification vessel Energos Eskimo, as part of the government's broader efforts to bolster energy security and ensure the continuity of natural gas supplies. At the start of his tour, the Prime Minister emphasised that the government is taking proactive steps to meet Egypt's natural gas needs by expanding infrastructure capacity for receiving imported LNG. Madbouly noted that the initiative aims to enhance the efficiency and flexibility of the national gas supply system to accommodate rising domestic demand, particularly during the summer months, and in response to recent regional developments following the Israeli military operation in Iran. He stated that these measures fall within a comprehensive governmental plan involving relevant ministries to safeguard the stability of the national power grid. Accordingly, the government aims to have three regasification vessels operational by early July, with a combined capacity of 2,250 million cubic feet per day. A fourth vessel will be kept on standby to provide additional support and ensure the availability of various petroleum products, Madbouly added. During his inspection of the Energos Eskimo vessel, the Prime Minister underscored that these strategic projects reflect the state's commitment to securing natural gas supplies and reinforcing the system's resilience during peak consumption periods in the summer. He highlighted that this vessel is the second of its kind stationed at Ain Sokhna Port, following the Hoegh Galleon, which entered service last year under the government's plan to operate four regasification vessels and expand LNG import capacity. Madbouly also reviewed the advanced technical works being finalised by Petrojet, a subsidiary of the petroleum sector, in preparation for the vessel's transfer to the SUMED port dock in Sokhna. The Energos Eskimo has a design capacity of 750 million cubic feet of gas per day. Minister of Petroleum and Mineral Resources Karim Badawi explained that petroleum sector teams have completed the development of a second berth at the SUMED Port to receive the vessel. This includes the installation of two loading arms and pipelines for transferring gas to the national grid. Badawi noted that the teams are working with high efficiency and speed to complete the required technical works, with ongoing field inspections to ensure timely progress. The Minister further highlighted the proactive steps taken by the Ministry since last year to secure gas supplies, diversify sources, and manage emerging challenges. He noted that the Ministry succeeded in contracting three LNG regasification vessels following a phase of political and commercial negotiations with various governments—leveraging Egypt's strong diplomatic ties with countries such as Jordan and Germany. These vessels were secured by the Egyptian Natural Gas Holding Company (EGAS) amid high global demand, as part of a broader strategy to achieve energy security in the face of geopolitical risks and global instability. The combined capacity of the three vessels stands at 2,250 million cubic feet per day, significantly enhancing Egypt's domestic gas supply capabilities to meet the needs of all consumer sectors. One vessel is currently operational at SUMED Port, while preparations are underway to commission the remaining two at the SUMED and Sonker terminals in Ain Sokhna. Badawi added that a fourth regasification vessel is scheduled to arrive in August and will be operated at Damietta Port on the Mediterranean Sea, further strengthening the resilience and diversification of Egypt's energy supply in the face of ongoing global challenges. The Minister also stressed that, alongside the urgent plan to cover local demand through LNG imports, the government is intensifying efforts to boost domestic natural gas production. He cited recent successes in curbing natural production decline by introducing incentive packages to attract investment and ensuring the timely payment of dues to partners. These actions are expected to gradually increase output, as exploration and production activities pick up momentum. During his tour aboard the Energos Eskimo, Madbouly received a technical briefing from Walid Lotfy, Chairperson of Petrojet, on the modifications and readiness efforts under way. Lotfy confirmed that the implementation timeline had been compressed from 29 days to just 10, thanks to round-the-clock work and intensified efforts. The works included mechanical modifications, control system adjustments, and commissioning tests to ensure the vessel's full readiness to receive LNG and convert it into its gaseous form for integration into the national grid.

OPEN// PM: Egypt to deploy 3 LNG regasification ships in July
OPEN// PM: Egypt to deploy 3 LNG regasification ships in July

Middle East

time13 hours ago

  • Middle East

OPEN// PM: Egypt to deploy 3 LNG regasification ships in July

CAIRO, June 21 (MENA) – Prime Minister Mostafa Madbouli announced that Egypt will have three LNG regasification ships operating by early July to supply the national gas grid, ensuring stable energy for households and industry during peak summer demand. The announcement came during a visit to Ain Sokhna to inspect final preparations at the new LNG import infrastructure. The second regasification vessel, Energos Eskimo, has arrived and will begin operations by the end of June, adding 750 million cubic feet of gas per day. A third ship is being prepared at Dekheila Port in Alexandria and will also start operation in early July. These ships join Hoegh Galleon, which has been operational since last year. Madbouli added that the move is part of a temporary strategy to cover gas needs while local production ramps back up. He also confirmed that two new gas production lines from Shell and Eni will start next month, including increased volumes from the Zohr field. Additionally, he emphasized that the LNG plan was initiated months before recent regional tensions and is not a response to external events. Egypt remains committed to increasing domestic gas output to reduce reliance on imports over time. (MENA) H A T/M N E

OPEN// PM starts tour at Ain Sokhna port to follow up importing natural gas
OPEN// PM starts tour at Ain Sokhna port to follow up importing natural gas

Middle East

time18 hours ago

  • Middle East

OPEN// PM starts tour at Ain Sokhna port to follow up importing natural gas

CAIRO, June 21 (MENA) - Prime Minister Moustafa Madbouli asserted on Saturday that the Egyptian government is actively working to secure the country's natural gas needs by enhancing the infrastructure required to receive imported liquefied natural gas (LNG). This move aims at boosting the efficiency and flexibility of Egypt's gas supply system to meet the growing domestic demand, particularly during the high-consumption summer months, he added. This came during an inspection tour on Saturday at Ain Sokhna port where Madbouli emphasized that these efforts are part of a broader, integrated package of measures being implemented by various ministries to ensure the stability of the national electricity grid. He particularly highlighted the importance of energy security in light of recent regional developments, notably the Israeli military operation in Iran. During the visit, Madbouli inspected the LNG regasification vessel Energos Eskimo, reflecting the government's commitment to strengthening energy security and ensuring the sustainability of gas supplies. He was accompanied by Petroleum and Mineral Resources Minister Karim Badawi. Madbouli revealed that Egypt is set to operate three regasification vessels starting from July. He also announced that a fourth regasification vessel would be held in reserve as a contingency measure to ensure continued availability of petroleum products and enhance national energy security. (MENA) M H K/Y R E